PLAN COMMISSION STAFF REPORT JULY 18, 2023 ITEM VI: ARCHITECTURAL BUILDING PLAN REVIEW FOR A PROPOSED POLICE DEPARTMENT EVIDENCE STORAGE BUILDING GENERAL INFORMATION Applicant: Kueny Architects, LLC Property Owner: City of Oshkosh Action(s) Requested: The applicant is requesting an architectural building plan review for construction of a Police Department evidence storage building at 640 W 3rd Avenue. Applicable Ordinance Provisions: State Statute 62.23(5) requires the Plan Commission review the “location and architectural design of any public building”. Property Location and Background Information: The subject site is located on the north side of W. 3rd Avenue, west of Ohio Street, and is part of a City-owned lot containing City garage, waste, and street facilities. The surrounding area consists primarily of institutional and storage land uses as well as commercial uses to the east. Page 1 Item VI – 640 W 3rd Ave. - Arch Review 2 Subject Site Existing Land Use Zoning Government I Recognized Neighborhood Organizations None Adjacent Land Use and Zoning Existing Uses Zoning North Government I South Government I East Commercial UMU West Storage I Comprehensive Plan Land Use Recommendation Land Use 2040 Land Use Recommendation Government ANALYSIS The Oshkosh Police Department has submitted plans for demolition of two existing storage buildings and a shed and construction of a new 7,200 sq. ft. evidence storage building. New building Page 2 Item VI – 640 W 3rd Ave. - Arch Review 3 The proposed evidence storage building is planned to be 60’ wide by 120’ deep and 28’ tall. The side (east/west) and rear (north) facades of the building will be composed of architectural metal panel and insulated grey glass, with overhead doors on the north and east elevations. The front (south) façade of the building will be clad in architectural block, face brick, and insulated grey glass. The roof material will be architectural metal. Page 3 Item VI – 640 W 3rd Ave. - Arch Review 4 The applicant has stated that they selected the proposed materials to match the adjacent Public Works building to the north. The material breakdown is as follows: NORTH ELEVATION (Total Area - 1,431 sf) 1. Architectural Metal Panels 73 % 2. HM Doors & OH Doors 27 % SOUTH ELEVATION (Total Area - 1,839 sf) 3. Block 58 % 4. Brick 38 % 5. Glass 4 % EAST ELEVATION (Total Area - 2,602 sf) 6. Block 1 % 7. Architectural Metal Panels 52 % 8. Glass 4 % 9. HM Doors & OH Doors 43 % WEST ELEVATION (Total Area - 2,602 sf) 10. Architectural Metal Panels 97 % 11. Glass 3 % Page 4 Item VI – 640 W 3rd Ave. - Arch Review 5 Public Works building along Witzel Ave. Staff believes that the evidence storage building will not have a negative impact on the surrounding area as the structure will have a consistent appearance with the neighboring City buildings (Parks and Public Works buildings) and be compatible with the surrounding area. Sufficient façade articulation will be provided and appropriate materials utilized for a utility structure. RECOMMENDATION/CONDITIONS Staff recommends approval of the architectural design of the evidence storage building as proposed. Page 5 jurben@ci.oshkosh.wi.us Page 6 Page 7 June 5, 2023 City of Oshkosh Police Storage 640 West 3rd Avenue Oshkosh, Wisconsin Dear Reviewer Kueny Architects, LLC The City of Oshkosh Police Department is looking to construct a new evidence storage building at the existing site. Three existing structures totaling 5,697 sq/ft will be demoed to make way for the 7,200 sq/ft new structure. The new structure will be located on the southwest side of the site. The facility will be 22’-0” in height to the gutter line and 28’-0” to the roof peak. The existing asphalt pavement will be removed and new pavement will be installed. The asphalt pavement that is in the current right away will be removed to the north edge of the street line. A new 24-foot-wide entrance drive will be created on the south side. The existing impervious area is 31,693sq/ft or 83%. The proposed impervious area is 30,796sq/ft or 81%. Existing site is operating under the same conditions as the proposed new structure. Please let me know if you have any comments/questions. Sincerely. Kueny Architects, LLC Jon P. Wallenkamp, AIA Page 8 TA X K E Y #9 0 6 - 2 3 3 1 - 2 0 0 1 6" 6" BM K HY D - N W F L A N G E B O L T ( B U R Y TA G ) E L E V = 7 5 4 . 6 9 STORM SEWER MH RIM = 753.30 IE (E,S) 15" = 747.35 SANITARY MH RIM = 754.44 IE (E,W) 8" = 744.84 CATCH BASIN RIM = 753.88 IE (W) 15" = 749.13 IE (N) 8" = 749.43 CATCH BASIN RIM = 754.15 IE (S) 8" = 749.83 BU I L D I N G BU I L D I N G BU I L D I N G BU I L D I N G BU I L D I N G 39 . 6 8 ' 49.74' 42.01' 85.36' CPCP 12 IE = 749.61 CPCP 12 IE = 750.98 70.23' 60.32' 20' X 12' SHED 15.36' 25.12' 45.17' 40.92' 10.27' 9.48' 11.18' ST CB CB ST SA IP IP WV WV WV 754 7 5 5 754 7 5 3 750 753754 753 755 754 N 82°03'18" W 183.26' S 8 9 ° 3 6 ' 0 6 " W 1 8 3 . 5 4 ' N 00°05'18" E 239.94' S 00°09'59" W 312.92' N 82°03'18" W 140.78' 75 4 . 6 0 75 5 . 1 0 75 5 . 4 1 75 5 . 3 9 75 5 . 5 4 75 4 . 5 1 75 4 . 4 9 75 4 . 4 7 75 4 . 4 8 75 5 . 0 9 24 3 O H I O S T R E E T TA X K E Y #9 0 6 - 0 3 7 8 - 0 0 0 0 BM K HY D - N W F L A N G E B O L T ( B U R Y TA G ) E L E V = 7 5 4 . 6 9 STORM SEWER MH RIM = 753.30 IE (E,S) 15" = 747.35 SANITARY MH RIM = 754.44 IE (E,W) 8" = 744.84 CATCH BASIN RIM = 753.88 IE (W) 15" = 749.13 IE (N) 8" = 749.43 CATCH BASIN RIM = 754.15 IE (S) 8" = 749.83 BU I L D I N G BU I L D I N G BU I L D I N G CPCP 12 IE = 749.61 CPCP 12 IE = 750.98 70.23' 60.32' 15.36' 25.12' 45.17' 40.92' 10.27' 9.48' 11.18' POSSIBLE UNDERGROUND ELECTRIC FROM MAPPING ST CB CB SA IP IP WV WV WV 754 7 5 5 754 7 5 3 750 753754 753 755 754 N 00°05'18" E 239.94' S 00°09'59" W 312.92' N 82°03'18" W 140.78' 75 4 . 6 0 75 5 . 1 0 75 5 . 4 1 75 5 . 3 9 75 5 . 5 4 75 4 . 5 1 75 4 . 4 9 75 4 . 4 7 75 4 . 4 8 75 5 . 0 9 C F N C C F N C C FNC C FNCC FNC C FNC C FNC C FNC C FNC C FNC C FNC C FNC C FNC C FNC C FNCC FNC C FNC C FNC C FNC C FNC C FNC C FNC C FNC C FNC C FNC C FNC C F N C C F N C C F N C C F N C C FNCC FNC C F N C C F N C (D E M O E X I S T I N G ) (D E M O E X I S T I N G S T R U C T U R E ) SE E S H E E T S C 1 A N D C 2 F O R SI T E S C O P E O F W O R K Fo r e x i s t i n g c o n d i t i o n s : Im p e r v i o u s a r e a = 3 1 , 6 9 3 Pe r c e n t i m p e r v i o u s = 8 3 % Fo r p r o p o s e d c o n d i t i o n s : Im p e r v i o u s a r e a = 3 0 , 7 9 6 s f Pe r c e n t i m p e r v i o u s = 8 1 % EX I S T I N G B U I L D I N G T O R E M A I N (D E M O E X I S T I N G S T R U C T U R E ) 13 14 1516 60 ' - 0 " 120'-0" 7'- 6 " 25'-0" 7'- 6 " 30'-0" 2'- 0 " 2'-0" PR O P O S E D N E W B U I L D I N G 75 5 . 1 0 F F SE E S H E E T S C 3 A N D C 4 F O R SI T E S C O P E O F W O R K SE E S H E E T S C 3 A N D C 4 F O R SI T E S C O P E O F W O R K REAR YARD SETBACK SI D E Y A R D S E T B A C K SI D E Y A R D S E T B A C K FRONT YARD SETBACK A2 1 0 1 A2 1 0 4 A2 1 0 3 A2 1 0 2 EX I S T I N G B U I L D I N G T O R E M A I N ku e n y a r c h . c o m © 2 0 2 3 K u e n y A r c h i t e c t s L . L . C . - Al l R i g h t s R e s e r v e d PL A N N O R T H KE Y N O T E L E G E N D SC A L E : 1 " = 2 0 ' - 0 " A 1 0 1 Ci t y o f O s h k o s h - P o l i c e S t o r a g e G a r a g e Ju n e 5 , 2 0 2 3 Ex i s t i n g a n d P r o p o s e d S i t e P l a n s 64 0 W e s t 3 r d A v e n u e 1" = 2 0 ' - 0 " 1 Ex i s t i n g S i t e P l a n 1" = 2 0 ' - 0 " 2 Pr o p o s e d S i t e P l a n Page 9 15 16 21'-8" AR C H I T E C T U R A L ME T A L R O O F SH E E T M E T A L C A P 4'X 4 ' 1 " I N S U L A T E D G R E Y G L A S S IN S U L A T E D G A R A G E D O O R 28'-0" 31'-0" AR C H I T E C T U R A L M E T A L PA N E L -- CO L O R # 1 AR C H I T E C T U R A L M E T A L PA N E L -- CO L O R # 2 13 14 22'-0" 28'-4" 31'-1 5/8" SH E E T M E T A L C A P AR C H I T E C T U R A L B L O C K FA C E B R I C K 4' X 4 ' 1 " I N S U L A T E D G R E Y G L A S S AR C H I T E C T U R A L B L O C K 10'-4" 9'-8" 8" S M O O T H F A C E B L O C K B A N D 15 16 AR C H I T E C T U R A L ME T A L R O O F SH E E T M E T A L C A P 4'X 4 ' 1 " I N S U L A T E D G R E Y G L A S S IN S U L A T E D G A R A G E D O O R AR C H I T E C T U R A L M E T A L PA N E L -- CO L O R # 1 AR C H I T E C T U R A L M E T A L PA N E L -- CO L O R # 2 AR C H I T E C T U R A L M E T A L PA N E L -- CO L O R # 1 AR C H I T E C T U R A L M E T A L PA N E L -- CO L O R # 1 8'-0" 11 ' - 0 " 22'-0" 28'-0" 31'-0" 13 14 SH E E T M E T A L C A P 7'-2" 28'-0" 22'-0" AR C H I T E C T U R A L M E T A L PA N E L -- CO L O R # 2 AR C H I T E C T U R A L M E T A L PA N E L -- CO L O R # 2 BA C K S I D E O F S O U T H E L E V A T I O N W A L L ku e n y a r c h . c o m © 2 0 2 3 K u e n y A r c h i t e c t s L . L . C . - Al l R i g h t s R e s e r v e d SC A L E : 1 / 8 " = 1 ' - 0 " A 2 1 0 Ci t y o f O s h k o s h - P o l i c e S t o r a g e G a r a g e Ju n e 5 , 2 0 2 3 Ex t e r i o r E l e v a t i o n s 64 0 W e s t 3 r d A v e n u e 1/ 8 " = 1 ' - 0 " 1 El e v a t i o n E a s t 1/ 8 " = 1 ' - 0 " 2 El e v a t i o n S o u t h 1/ 8 " = 1 ' - 0 " 3 El e v a t i o n W e s t E l e v a t i o n 1/ 8 " = 1 ' - 0 " 4 El e v a t i o n N o r t h Page 10 BUILDING DESIGN REVIEW 640 W 3RD AVE PC: 7/18/2023 STEVEN/KAYLA M DUKE 225 IDAHO ST OSHKOSH, WI 54902 BLUE MOON HOLDINGS LLC PO BOX 3808 OSHKOSH, WI 54903 BOARD OF REGENTS UNIV OF WI 1220 LINDEN DR MADISON, WI 53706 CITY OF OSHKOSH PO BOX 1130 OSHKOSH, WI 54903 JAMES H LANG PROPERTIES INC 615 S MAIN ST OSHKOSH, WI 54902 AMERCO REAL ESTATE COMPANY PO BOX 29046 PHOENIX, AZ 85038 D R HANSEN PLUMBING LLC 522 W 12TH AVE OSHKOSH, WI 54902 JACOB F/CHELSEA L SARAUER 690 W 4TH AVE OSHKOSH, WI 54902 JONATHAN P BERGER 684 W 4TH AVE OSHKOSH, WI 54902 ELIZABETH M NIEMUTH 676 W 4TH AVE OSHKOSH, WI 54902 SHELTER FROM THE STORM LLC 1511 OREGON ST OSHKOSH, WI 54902 BRADLEY J/ANGELA M MELUM 668 W 4TH AVE OSHKOSH, WI 54902 FOX VALLEY TECH & ADULT 1825 N BLUEMOUND RD APPLETON, WI 54914 BOARD OF REGENTS UNIV OF WIS SYS PO BOX 2884 OSHKOSH, WI 54903 AUTO AUTHORITY PROPERTIES LLC 804 WITZEL AVE OSHKOSH, WI 54902 VERVE A CREDIT UNION PO BOX 3046 OSHKOSH, WI 54903 KUENY ARCHITECTS, LLC 10505 CORPORATE DR SUITE100 PLEASANT PRAIRIE, WI 53158 Page 11 DAKOTA ST BISMARCK AV W 4TH AV N C A M P B E L L R D S C A M P B E L L R D IDAHO ST W 5TH AV W 4TH AV D E M P S E Y T R W 3RD AV OHIO ST WISCONSIN ST WITZEL AV FVTCAthleticField CampbellCreek Marsh Carl E.SteigerPark Seniors Center Boat Launch William A. Steiger Park J:\GIS\Planning\Plan Commission Site Plan Map Template\2023 Plan Commission Site Plan Map Template.mxd User: hannahs Prepared by: City of Oshkosh, WI Printing Date: 6/16/2023 1 in = 320 ft1 in = 0.06 mi¯640 W 3RD AVE City of Oshkosh maps and data are intended to be used for general identification purposes only, and the City of Oshkoshassumes no liability for the accuracy of the information. Those using the information are responsible for verifying accuracy. Forfull disclaimer please go to www.ci.oshkosh.wi.us/GISdisclaimer Page 12 W 7TH AV W 8TH AV W 6TH AVW 6TH AV M A R IONRD RUGBY ST DAKOTA ST OSCEOLA ST W 4TH AV W 7TH AV W 8TH AV W 7TH AV S C A M PBELL RD W 4TH AV BISMARCK AV W 5TH AV W 5TH AV PEARL AV W 3RD AV D E M P S E Y T R N CAMPBELL RD N C A M PBELL R D MICHIGAN ST DAKOTA ST IDAHO ST WISCONSIN ST WITZEL AV HIGH AV OHIO ST OHIO ST I I I-PD I-PD I-PD I-PD-UTO MR-12 NMUNMU NMU RMU RMU RMU RMU-PD RMU-PD-RFO RMU-PD-RFO SR-5 SR-9 TR-10 UI UI UI-RFO UMU UMU UMU UMU UMU UMU-PD UMU-PD-UTO J:\GIS\Planning\Plan Commission Site Plan Map Template\2023 Plan Commission Site Plan Map Template.mxd User: hannahs Prepared by: City of Oshkosh, WI Printing Date: 6/16/2023 1 in = 500 ft1 in = 0.09 mi¯640 W 3RD AVE City of Oshkosh maps and data are intended to be used for general identification purposes only, and the City of Oshkoshassumes no liability for the accuracy of the information. Those using the information are responsible for verifying accuracy. Forfull disclaimer please go to www.ci.oshkosh.wi.us/GISdisclaimer Page 13 BISMARCK AV W 4TH AV DAKOTA ST N CAM PBELL RD S C A M P B E L L R D IDAHO ST W 4TH AV D E M P S E Y T R W 3RD AV WITZEL AV WISCONSIN ST OHIO ST J:\GIS\Planning\Plan Commission Site Plan Map Template\2023 Plan Commission Site Plan Map Template.mxd User: hannahs Prepared by: City of Oshkosh, WI Printing Date: 6/16/2023 1 in = 300 ft1 in = 0.06 mi¯640 W 3RD AVE City of Oshkosh maps and data are intended to be used for general identification purposes only, and the City of Oshkoshassumes no liability for the accuracy of the information. Those using the information are responsible for verifying accuracy. Forfull disclaimer please go to www.ci.oshkosh.wi.us/GISdisclaimer Page 14