HomeMy WebLinkAbout03-396
SEPTEMBER 23, 2003
03-396
RESOLUTION
(CARRIED
7-0
LOST
LAID OVER
WITHDRAWN
PURPOSE:
CHANGE ORDER NO.1 / CR MEYER & SONS - SAWYER
CREEK PEDESTRIAN TRAIL WEST LEG
INITIATED BY:
DEPARTMENT OF COMMUNITY DEVELOPMENT
BE IT RESOLVED by the Common Council of the City of Oshkosh that the
following Change Order, copy of which is attached, is hereby approved:
CR MEYER & SONS CO.
895 W. 20th Avenue
Oshkosh, WI 54902
Net Increase to Contract
$13,022.00
PURPOSE: See attached
BE IT FURTHER RESOLVED that money for this purpose is hereby appropriated
from Acct. No. 325-0610-6401-07205 Park Improvements / Pedestrian Bridges.
CHANGE ORDER NO.1
TO:
CR Meyer & Sons Co,
895 W. 20th Avenue
Oshkosh, WI 54902
Date: September 17, 2003
Your present contract with the City of Oshkosh for construction of a pedestrian trail known as the Sawyer Creek
Pedestrian Trail West Leg, is hereby amended and changed as follows:
ADD:
Per the attached letter dated September 17, 2003
$13,022.00
RECOMMENDED:
CITY OF OSHKOSH
BY:
City Manager
Director of Community Development
City Clerk
I certify that provision has been made to
pay the liability that will accrue to the City
of Oshkosh, Wisconsin, under the within
Change Order.
APPROVED AND ACCEPTED:
CR Meyer & Sons Co,
Finance Director
Approved as to form:
Lynn Lorenson, Assistant City Attorney
..-.. _.- -..-- . -^ ,..~v, ~~~"
September 18. 2003
Mr, Jackson Kinney
City of Oshkosh
P.O, Box 1130
Oshkosh,¥V153903-1130
Reference: Sawyer Creek Pedestrian Trail ¥Vest Leg
Change Request #1
Dear Mr. Kinney;
~NIMi~
Building Solutions Si7IJ:e 1888
Please review the following Change ,Request and call with any qlJestions,
The changes to the SCOPe" ofworl<are as follows:
Install a 11' high wall in lieu of a 4' high wall fur the bridge
abutment to reinforce the long-term viability of Ø1e
structure given the topographical conditions.
1. Form. reinforce, and pour extra wall.
2, Excavate êxtrasoil due to taller wall.
3. Extend boarðwalk is-feel
4, Add ñprap fòr erosion .control under boardwalk.
The folloWing items were not anticipated or seen during
the bidding process:
5. Remove trees from site.
6, Repair mlJddy 340-foot by 12-foot area by
removing 9 inches of material and installing 12
inches of3,inch minus base material.
Add per change reqùest #1,
Original lump sum price:
Revised Contract Amount:
$ 4.340.00
$ 945.00
$ 2,376.00
$ 400,00
$ 1,050.00
$ 3,911,00
$ 13,022,00
$ 94,124,00
$ 107,146,00
Thank you for the opportunity to provide you with this Change Request
Sincerely,
C~~~~ONSCOMPANY
Todd M. Dalbec, E.I,T,
Project Engineer