HomeMy WebLinkAbout03-359.docAUGUST 26, 2003 03-359 RESOLUTION
(CARRIED 7-0 LOST
LAID OVER
WITHDRAWN
PURPOSE:
ACCEPT AND APPROVE WAIVER OF SPECIAL ASSESSMENT
NOTICES AND HEARING IN CONNECTION WITH
IMPROVEMENTS - FOSTER HEIGHTS
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the Waiver of
Special Assessment Notices and Hearing under Section 66.0703(7)(b) of the Wisconsin
Statutes, for public improvements and services, for the premises described in the attached
Waiver is accepted and approved.
WAIVER OF SPECIAL ASSESSMENT NOTICES AND
HEARING UNDER SECTION 66.0703, WISCONSIN STATUTES
The undersigned, owner ofpr0perty benefited by the following improvements to be made by the
City of Oshkosh, Wirmebago County, State of Wisconsin, to wit:
For public construction, surveying and inspection of sidewalk and concrete paving and for the
design of the concrete paving.
For Private construction and public surveying and inspection for sanitary sewer, stom~ sewer,
water main, laterals, grading and graveling.
In consideration of the construction of s~id improvements by the City of Oshkosh, Wisconsin, I
hereby admit that such public improvement will benefit said property and consent to the levying
of special assessments against the premises under Section 66.0703 of the Wisconsin Statutes for
the cost of such improvements. In accordance with Section 66.0703 of the Wisconsin Statutes, I
hereby waive ail special assessment notices and hearings required by Section 66.0703 of the
Wisconsin Statutes; and I further agree and admit that the benefit of my property from the
construction of such improvements is in proportion to the footage thereof.'
Description of Premises
Foster Heights
Lots 1-24 (24 Lots)
Foster Street, Bismarck Avenue Cul-de-Sac, Sanitary Sewer from Guenther Street to Bismarck
Avenue and Storm Sewer along Foster Ave. from Northerly Plat Boundary to West 4th Avenue.
Sanitary Sewer (Private Construction)
Estimated Construction Cost
6% Survey and Inspection
$45,536 Private
$ 2,732 Invoice
The estimated construction cost for sanitary sewer includes the cost to relay sanitary sewer (at
the developers expense) along Bismarck Avenue from Guenther St. to the westerly plat
boundary of Foster Heights. The estimated cost for the sanitary sewer relay along this section
of Bismarck Avenue is $16,475. The developer reserves the right to request reimbm-sement for
a portion of this cost from the 2004 City of Oshkosh Capital Improvement Budget.
2. Water Main (Private Construction)
Est/mated Construction Cost
6% Survey and Inspection
$44,525 Private
$ 2,672 Invoice
Sanitary and Water Laterals (Private Construction)
Bsthnated Construction Cost
6% Survey and Inspection
$36,971 Private
$ 2,218 Invoice
Page 2
Foster Heights
Storm Sewer Laterals (Private Construction)
Estimated Construction Cost
6% Survey and Inspection
$13,583 Private
$ 815 Invoice
5. Storm Sewer (Private Construction)
Estimated Cons~x-uction Cost
6% Survey and Inspection
$ 64,896 Private
$ 9,886 Invoice
o Includes Construction of Storm SeWer in existing Foster Street from the Northerly Plat
Boundary to West 4~h Avenue.
Sidewalk (Public Construction)
Assessment Rate = $20.00 per from foot of each lot
Includes 6% for inspection and surveying. Includes Handicap ramps
Lot # Front Feet
Sidewalk and Handicap Ramps/Lot
1 62.86 $1,257.20
2 66.90 $1,338.00
3 63.16 $1,263.20
4 48:10 $ 962.00
5 41.14 $ 822.80
6 37.07 $ 741.40
7 42.08 $ 841.60
8 43.24 $ 864.80
9 55.33 $1,i06.60
10 48.10 $ 962.00
11 70.88 $1,417.60
12 68.t2 $1,362.40
13 55.77 $1,111.50
14 44.37 $ 887.40
I5 71.81 $1,436.20
16 77.25 $1,545.00
17 i03.91 $2,078.20
18 101.12 $2,022.40
19 164.41 $3,288.20
20 69.57 $1,391.40
21 60.25 $1,205.00
22 60.20 $1,204.00
23 61.55 $1,231.00
24 82.04 $1,640.80
TotaI 1,599.23 $31,980.70
7. Grading and Graveling (Private Construction)
Center Line Feet of Roadway = 680.66
Cost per Center Line Foot = 36.00
Estimated Construction Cost
6% Survey and Inspection
$24,503.00
$ 1,470.00
8. Concrete Paving (Public Construct/on- Year 2006)
Center Line Feet of Roadway
Cost per Center Line Foot
883 (~cludes 1351fx 1.5 = 203 lffor cul-de-sac)_
$120.00
Estimated Construction Cost $105,960.00
6% Survey and Inspection $ 6,358.00
6% Design $ 6,358.00
Total $118,676.00
Lots 1-24 ($1 I8,676/24 lots) = $4,944.83 ASSESS
3 - Year Letter of Credit for Private Construction = $230,014
4 -Year Letter of Credit for Public Services = $19,793
2 - Year Letter of Credit Guarantee After
Acceptance of Private Construction = $46,003
Signature of Owner:
(Tritt Cons traction, L.L.C.
Date