HomeMy WebLinkAbout03-182.docJUNE 24, 2003 03-182 RESOLUTION
(CARRIED 6-0 LOST LAID OVER WITHDRAWN )
PURPOSE:
CHANGE ORDER NO. 1, PUBLIC WORKS CONTRACT 99-02
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
BE IT RESOLVED by the Common Council of the City of Oshkosh that the following
Change Order, a copy of which is attached, is hereby approved:
PITT DES MOINES, INC.
(CB & I CONSTRUCTORS WATER DIVISION)
9550 Hickman Road
Clive, IA 50325-5316
Net Increase to contract:
None
PURPOSE: See attached Change Order.
CHANGE ORDER
No. 1 (REVISED)
DATE OF ISSUANCE: June 5, 2003 BpP~,CTIVE DATE: June 5, 2003
OWNER
CONTRACTOR
Contract:
City of Oshkosh
Pitt Des Moines, Inc. (CB&I Constructors Water Division)
Fernau Avenue Water Tower
Project:
OWNER's Contract No.
ENGINEER
99-02
ENGINEER's Contract No.
HNTB Corporation
27738
You are directed to make the following changes in the Contract Documents:
Description:
Add for increasing size of altitude valve and piping from 8-inch to 12-inch (add $6312.00).
Deduct for deletion of 16" butterfly valve and access manhole (deduct $5,800.00).
Deduct for providing and replacing joint filler. Work completed by City of Oshkosh (deduct $512.00).
$6,312- $5,800- $512 = $0 netchange
Reason for Change Order:
Final contract close-out
Attachments: (List documents supporting change)
January 2, 2002 letter from HNTB to CB&I summarizing anniversary inspection results
February 13, 2003 letter from CB&I to IrLNTB
CHANGE IN CONTRACT PRICE:
Original Contract Price
$1,588,194.00
Net Increase (Decrease) from previous Change Orders
No. N/A to N/A:
SN/A
Contract Price prior to this Change Order:
$1,588,194.00
Net increase (decrease) of this Change Order:
;0.00
Contract Price with all approved Change Orders:
$1,588;194.00
CHANGE IN CONTRACT TIMES:
Original Contract Times:
Substantial Completion: N/A
Ready for final payment: N/A
(days or dates)
Net change from previous Change Orders No. N/A to No. N/~A:
Substantial Completion: N/A
Ready for final payment: N/A
(days)
Contract Times prior to this Change Order:
Substantial Completion: N/A
Ready for final payment: N/A
(days or dates)
Net increase (decrease)this Change Order:
Substantial Completion: N/A
Ready for final payment: N/A
(days)
Contract Times with ali approved Change Orders:
Substantial Completion: N/A
Ready for final payment: N/A
(days or dates)
RECOMMENDED: · ~ APPROVED:
ENC:~qEER (Authtorized Signature) OWNER (Authorized Signature)
Date: ~ ~''5~-~/57 Date:
~ ACCEPT, ED:
CO~ACTOR(J. uthorized Signature)
Date: ~--~ [-¢'~
E~'CDC 1910-8-B (1996 Edition)
Prepared by the EngSneers loint Con~act Decun~nts Committee and endorsed by ]7ne Associated General Contractors of America and the Construction Specifications Institute.
Recommended:
~i~ ecC~c'r°]o f~p~b h c~-Q'~Wb r~s
Approved CITY OF OSHKOSH on June 24, 2003.
BY:
City Manager
City Clerk
I certify that provision has been made to pay the liability that will accrue to the City of
Oshkosh, Wisconsin, under the within Change Order.
Comptroller
Approved as to form:
City Attorney
tr
ARCHITECTS ENGINEERS PLANNERS
January2,2002
Mr. Darwyn Witte
CB&I Constructors, Inc.
9550 Hickman Road '
Clive, IA 50325-5316
Re: City of Oshkosh
Femau Avenue Water Tower - Contract 99-02
CB&I Contract No. 59522
53224
(414) 359-2300
FAX (414) 359-2310
10 East Dory
&cite 615
53703
(?508d 259-0045
FAX (608) 25)-0084
Dear Mr. Witte:
The anniversary inspection of this tank was conducted by representatives from the City of
Oshkosh, HNTB, and Dixon Engineering, Inc. on Tuesday, October 2, 2001. This letter
summarizes the results of the inspection. 'While the tank was found to be in generally good
condition, the following items need attention:
The guard posts at the overhead door need to be painted. This item was on the punch
· list first transmitted to you on Mar6h 30, 2001.
· The overhead door needs to be painted, removing all mst and touching up damaged
factory primer.
The mandoor sags and hits the top comer of the frame, scraping the paint. The sag
must be corrected and the frame repainted. Install a threshold at the mandoor to
provide a tight seal with the door bottom.
The joint filler has pulled away from the concrete in se~/eml' locations between the
floor and the ringwall and between the floor and the valve vault top slab.
· The ringwall leaks at three locations in the valve vault.
· Mount the valve vault heater and dehumidifier on wall shelves as shown on the plans.
· Repaint scrape on exterior near the base of the fluted column.
· See attached letter from Dixon Engineering, Inc. summarizing other needed paint
repairs.
The site landscaping is still unacceptable. Very little grass has taken root, and the
ground cover is mostly weeds. The City obtained a quote from a local landscape firm
to place topsoil, seed and mulch over the site for $8,161.62. A copy of that quote is
attached. We have not yet heard from you as to how you would like to proceed on this
matter.
Mr. Darwyn Witte
5anua[y 2, 2002
Page 2
You are reminded that the one year correction period under the Contract runs from the date of
Substantial Completion, and that the correction period for the items listed above will run for
one year from the date of their satisfactory correction. We are still prepared t9 grant
Substantial Completion as of February 1, 2001, but not until we have received your wdtten
request for a Certificate of Substantial COmpletion and the remaining supporting
documentation required by Section SC-14.8 of the Supplementary Conditions. The lien
waivers and prevailing wage rate affidavit you previously provided are acceptable, but we still
have not received acceptable operation and maintenance manuals. Shop drawings and catalog
cuts do not meet the requirements of Section 01001 for Equipment Manuals.
Also unresolved is the amount of the credit for the deleted valve and manhole. The Change
Order for the $6,312 additional cost of the 12" altitude_valve cannot be prepared until this
credit has been resolved. If it is your intention to offset these two amounts, we still need to
prepare a Change Order to cover the changes in the Work. See our Mamh 30, 2001 letter for a
discussion of this issue.
The City is anxious to close out this contract and is losing patience with the lack of progress.
Please advise us of your schedule for addressing these issues. If we have not received your
reply by January 18, 2002, the City will consider terminating your contract and using the
$25,000 currently being retained to complete the project.
Sincerely,
I-INTB CORPORATION
Project Manager
CC: Tom Konrad, City of Oshkosh
Mark Ellefson
CB&I Water
a division of CB&I Constructors, Inc.
February 13, 2003
9550 Hickman Road
Clive, IA 50325
HNTB
1 i414 Wets Park Place - Suite 300
Milwaukee, WI 53224
Attn: Peter Nilles
Fax: 414-359-2315
Re~
59522 - Oshkosh, WI
Fernau Ave water Tower
RECEIt/ o
51 $ 254 9228
Gentlemen:
Prior to submitting the final invoice, CB&I requests your concurrence that the following reflects
the mount due
Original Contract Price
Paid To-Date
Outstanding Balance
Add for By-Pass Piping Revision
Deduct for 16" Valve & Manhole
Balance Due
= $1,588,194
= $1,563,194
= $ 25,000
= $ 6,312
= $ (5,800)
= $ 25,512
Regarding the outstanding paperwork required it is CB&I's understanding that the following is
required inaccordance with 14.12 of the general conditions as modified by S.C. 14.12.
2.
3.
4.
5.
Item's
Evidence of Insurance
Contractor's Affidavit of Compliance with prevailing wage determination
Subcontractor's Prevai!ing Wage Affidavit
Consent of Surety
Lien Waivers
1,2, & 5 were submitted previously to your office on 7-12-01 (see attached transmittal).
Items 3 & 4 have yet to be submitted, please confirm that items 3 &4 are the only paperwork
items remaining to be submitted in order for the Final Invoice to be processed.
Upon your concurrence on the balance due and item 3 & 4 a Final Invoice will be prepared and
submitted with items 3 & 4.
Thank you for your consideration of this matter.
Very truly yours,
Darwyn G. Witte
Senior Project Manger
DGW/jjs