HomeMy WebLinkAbout07.22-371SEPTEMBER 13, 2022 22-371 RESOLUTION (CARRIED 7-0 LOST _______ LAID OVER _______ WITHDRAWN _______) PURPOSE: APPROVE CHANGE ORDER NO. 1 (FINAL) FOR PUBLIC WORKS CONTRACT NO. 21-11 SANITARY MANHOLE REHABILITATION / INFLOW / INFILTRATION REDUCTION PROGRAM / WOOD SEWER & EXCAVATING (+$32,688.54) INITIATED BY: PUBLIC WORKS DEPARTMENT BE IT RESOLVED by the Common Council of the City of Oshkosh that the following change Order, a copy of which is attached, is hereby approved: WOOD SEWER & EXCAVATING, INC. E9238 COUNTY ROAD X NEW LONDON, WI 54961 Net Increase to Contract: (+$32,688.54) PURPOSE: See attached Change Order. Acct. Nos. 03210410-6801-04011 Contract Control-Paving-Annual - I & I Sanitary Swr Rehab 03210410-6802-04011 Contract Control-Sanitary Sewer-Annual - I & I Sanitary Swr Rehab I:\Engineering\2021 - 2030 Contracts\2021 CONTRACTS\21-11 San MH Rehab\Project_Information\Correspondence\Memo\22-11 Memo for CO #1 (Final)_9-8-22.docx Page 1 of 2 TO: Honorable Mayor and Members of the Common Council FROM: Justin Gierach, Engineering Division Manager / City Engineer DATE: September 8, 2022 RE: Approve Change Order No. 1 (Final) for Public Works Contract No. 21-11 Sanitary Manhole Rehabilitation / Inflow/Infiltration Reduction Program / Wood Sewer & Excavating (+$32,688.54) BACKGROUND Change Order No. 1 (Final) for Contract 21-11 is scheduled for consideration by the Common Council at the September 13, 2022 meeting. The Contract was originally awarded to Wood Sewer & Excavating in August of 2021. This change order is for additional services requested by the City and to adjust quantities to match the necessary installation in the field. ANALYSIS Following is a summary of the significant changes to each section of the CIP:  Street – Final quantities were adjusted to match field conditions.  Sanitary Sewer – Original contract inadvertently missed a Bid Item that is required to complete the manhole rehabilitation. The price given by the Contractor was consistent from the last few manhole rehabilitation contracts. Additionally, final quantities were adjusted to match field conditions. FISCAL IMPACT Contract Section Change Order Amount Estimated Total Construction Costs CIP Budget Amount Street $1,283.58 $29,539 $50,000 Sanitary Sewer $31,404.96 $185,020 $200,000 Total $32,688.54 $214,558 $250,000 I:\Engineering\2021 - 2030 Contracts\2021 CONTRACTS\21-11 San MH Rehab\Project_Information\Correspondence\Memo\22-11 Memo for CO #1 (Final)_9-8-22.docx Page 2 of 2 Funding for the street and sanitary sewer portions of this Change Order is available from the 2022 Capital Improvement Program (CIP) (Account No. 03210410-6801- 04011/Contract Control-Paving-Annual - I & I Sanitary Swr Rehab and 03210410-6802- 04011/Contract Control-Sanitary Sewer-Annual - I & I Sanitary Swr Rehab). RECOMMENDATIONS I recommend approval of Change Order No. 1 (Final) to Contact No. 21-11 in the amount of +$32,688.54 to Wood Sewer & Excavating. Approved: Mark A. Rohloff City Manager JLG/tlt TO: WOOD SEWER & EXCAVATING E9238 COUNTY ROAD X NEW LONDON, WI 54961 Your present contract with the City of Oshkosh, Contract No. 21-11, awarded August 24, 2021, is hereby amended and changed as follows: ($12,040.88) $44,729.42 $32,688.54 $140,702.35 $140,702.35 $32,688.54 $32,688.54 $173,390.89 $173,390.89 CITY OF OSHKOSH BY: I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin, under the within Change Order. Approved as to form: City Attorney ______________________________ Approved and accepted: ______________________________ City Manager City Clerk ______________________________ ______________________________ Comptroller ______________________________ Contractor BID TOTAL CO #1 CONTRACT TOTAL CHANGE ORDER #1 (FINAL) DATE: AUGUST 23, 2022 NET DECREASE TO SECTION I: NET INCREASE TO ADDITIONAL WORK: NET INCREASE TO CONTRACT CONTRACT 21-11 REVISED CO #1 (FINAL) 21-11 ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE 1050 Mobilization; complete as specified Lump Sum 1.00 1.00 $28,750.00 1120 Removing concrete and asphalt sidewalk and driveway; complete as specified Square Feet 390.00 379.80 -10.20 $1.30 ($13.26) 1308 7" concrete pavement removal and replacement; including sawing; pavement ties; dowel bars; bond breaker; integral curb and fine grading; turf restoration; and traffic control; complete as specified Square Yards 175.00 128.60 -46.40 $82.00 ($3,804.80) 1309 7" concrete pavement HES removal and replacement; including sawing; pavement ties; dowel bars; bond breaker; integral curb and fine grading; turf restoration; and traffic control; complete as specified Square Yards 70.00 96.70 26.70 $72.00 $1,922.40 1318 8" concrete pavement removal and replacement; including sawing; pavement ties; dowel bars; bond breaker; integral curb and fine grading; turf restoration; and traffic control; complete as specified Square Yards 40.00 0.00 -40.00 $76.00 ($3,040.00) 1319 8" concrete pavement HES removal and replacement; including sawing; pavement ties; dowel bars; bond breaker; integral curb and fine grading; turf restoration; and traffic control; complete as specified Square Yards 270.00 321.60 51.60 $86.00 $4,437.60 1380 Cold weather covering (concrete pavement) - single visquine; complete as specified Square Yards 50.00 96.70 46.70 $0.01 $0.47 1382 Cold weather covering (concrete pavement) - double visquine; complete as specified Square Yards 25.00 0.00 -25.00 $0.01 ($0.25) 1390 Up-charge for late season cold weather concrete pavement; complete as specified Cubic Yards 30.00 18.80 -11.20 $11.00 ($123.20) 1510 6" concrete sidewalk/ driveway/ramp with 3" CABC and grading; complete as specified Square Feet 40.00 0.00 -40.00 $11.00 ($440.00) 1540 Curb ramp detectable warning field (natural/non- painted); complete as specified Square Feet 20.00 0.00 -20.00 $45.00 ($900.00) Page 2 of 5 CONTRACT 21-11 REVISED CO #1 (FINAL) ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE 1550 No. 4 reinforcing rods - deformed; epoxy-coated; complete as specified Linear Feet 30.00 0.00 -30.00 $5.00 ($150.00) 1560 Drilled No. 4 sidewalk tie bars - deformed; epoxy-coated; complete as specified Each 8.00 4.00 -4.00 $12.00 ($48.00) 1904 Remove and replace HMA pavement; including sawing; fine grading; turf restoration; and traffic control; complete as specified Square Yards 85.00 60.20 -24.80 $8.00 ($198.40) 1916 4" asphaltic surface LT with 6" CABC and grading; complete as specified Square Yards 35.00 31.40 -3.60 $62.00 ($223.20) 1918 Asphaltic cold weather paving; complete as specified Square Yards 25.00 0.00 -25.00 $62.00 ($1,550.00) 1930 Temporary cold mix asphaltic patch; complete as specified Square Yards 200.00 0.00 -200.00 $1.00 ($200.00) 2508 Furnish; install; maintain; and remove Type D modified inlet protection; complete as specified Each 4.00 16.00 12.00 $100.00 $1,200.00 2510 Sediment removal - Type D modified inlet protection; complete as specified Each 4.00 0.00 -4.00 $10.00 ($40.00) 2516 Furnish; install; maintain; and remove stone bag; complete as specified Each 8.00 0.00 -8.00 $75.00 ($600.00) 3000 Furnish and install 8" sanitary sewer (relay); complete as specified Linear Feet 20.00 19.00 -1.00 $268.00 ($268.00) 3004 Furnish and install 12" sanitary sewer (relay); complete as specified Linear Feet 5.00 0.00 -5.00 $960.00 ($4,800.00) 3101 Furnish and install standard sanitary sewer manhole (4' diameter) with slurry backfill; complete as specified Vertical Feet 13.00 4.96 -8.04 $868.00 ($6,978.72) 3114 Furnish and install external sanitary sewer manhole chimney seal; complete as specified Each 34.00 27.00 -7.00 $6.90 ($48.30) 3116 Furnish and install external sanitary sewer manhole chimney seal extension; complete as specified Each 2.00 4.00 2.00 $400.00 $800.00 3118 Furnish and install internal sanitary sewer manhole chimney seal; complete as specified Each 7.00 14.00 7.00 $460.00 $3,220.00 3123 Reconstruct sanitary sewer manhole (4' diameter) with slurry backfill; complete as specified Vertical Feet 11.00 18.06 7.06 $768.00 $5,422.08 3160 Pour and reshape manhole bench; complete as specified Each 3.00 3.00 $600.00 Page 3 of 5 CONTRACT 21-11 REVISED CO #1 (FINAL) ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE 3210 Furnish and install 8" x 6" sanitary sewer factory wyes or tees; complete as specified Each 1.00 1.00 $510.00 3214 Furnish and install 12" x 6" sanitary sewer factory wyes or tees; complete as specified Each 1.00 0.00 -1.00 $860.00 ($860.00) 3234 Furnish and install 4"/6" sanitary sewer lateral (relay); complete as specified Linear Feet 10.00 21.00 11.00 $99.00 $1,089.00 3235 Furnish and install 4"/6" sanitary sewer riser (relay); complete as specified Linear Feet 10.00 0.00 -10.00 $99.00 ($990.00) 3236 Furnish and install sanitary sewer lateral marker balls; complete as specified Each 4.00 1.00 -3.00 $43.00 ($129.00) 3300 Furnish and install connection to existing 8" sanitary sewer mains; complete as specified Each 3.00 3.00 $500.00 3304 Furnish and install connection to existing 12" sanitary sewer mains; complete as specified Each 2.00 0.00 -2.00 $600.00 ($1,200.00) 3314 Furnish and install connection to existing 30" sanitary sewer mains; complete as specified Each 1.00 1.00 $1,500.00 3892 Excavation special (sanitary); complete as specified Tons 10.00 0.00 -10.00 $32.00 ($320.00) 3974 Furnish sanitary sewer manhole grouting setup; complete as specified Each 4.00 3.00 -1.00 $1,500.00 ($1,500.00) 3975 Furnish and install sanitary sewer manhole grouting; complete as specified Gallons 30.00 78.00 48.00 $7.50 $360.00 3976 Furnish sanitary sewer manhole cementitious liner setup; complete as specified Each 4.00 3.00 -1.00 $850.00 ($850.00) 3977 Furnish and install sanitary sewer structural cementitious liner-PERMACAST by AP/M PERMAFORM; complete as specified Vertical Feet 25.00 18.42 -6.58 $185.00 ($1,217.30) SECTION I - (BID ITEMS 1050-3976) - SUBTOTAL $18,451.55 ($30,492.43) ($12,040.88) ADDITIONAL WORK REQUIRED: CO #1 ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE 1-1370 Turf restoration; complete as specified Square Yards 0.00 48.70 48.70 $14.00 $681.80 NET DECREASE TO SECTION I: Page 4 of 5 CONTRACT 21-11 REVISED CO #1 (FINAL) ITEM NUMBER DESCRIPTION UNIT CONTRACT QUANTITY INSTALLED QUANTITIES NET INCREASE NET DECREASE UNIT PRICE INCREASE IN CONTRACT PRICE DECREASE IN CONTRACT PRICE 1-1373 Replace and set City- Supplied manhole castings and frames; complete as specified Each 0.00 34.00 34.00 $380.00 $12,920.00 1-1374 Furnish and install concrete adjustment rings; complete as specified Vertical Feet 0.00 7.30 7.30 $370.00 $2,701.00 1-1375 Furnish and install rubber adjustment rings; complete as specified Vertical Feet 0.00 1.84 1.84 $1,400.00 $2,576.00 1-1376 Tuck point manhole; complete as specified Each 0.00 16.00 16.00 $200.00 $3,200.00 1-1500 Install 4" concrete sidewalk with 3" CABC and grading; complete as specified Square Feet 0.00 97.20 97.20 $9.00 $874.80 1-3018 Furnish and install 30" sanitary sewer (relay); complete as specified Linear Feet 0.00 8.00 8.00 $392.74 $3,141.92 1-3103 Furnish and install standard sanitary sewer manhole (5' diameter) with slurry backfill; complete as specified Each 0.00 1.00 1.00 $17,796.25 $17,796.25 1-3222 Furnish and install sanitary sewer 6" insert-a-tee or kor-n- tee; complete as specified Each 0.00 1.00 1.00 $837.65 $837.65 ADDITIONAL WORK REQUIRED: CO #1 (BID ITEMS 1-1370 - 1-3222) SUBTOTAL:$44,729.42 $0.00 $44,729.42 NET DECREASE TO SECTION I ($12,040.88) NET INCREASE TO ADDITIONAL WORK CO #1: $44,729.42 NET INCREASE TO CONTRACT:$32,688.54 NET INCREASE: Page 5 of 5