HomeMy WebLinkAbout31. Outstanding IssuesDate of Initial
Request
Affected
Department(s)
(If Applicable)
Title of Directive Current Status Next Status
Report/Update Other Notes
1/1/2018 Facilities-OPD-
OFD Facility Studies Draft Fire Department Facility Study is under review. Staff will schedule
workshop when report is finalized.5/10/2022
1/22/2019 Finance/DPW Fee to replace Special Assessments for Street Improvements Staff is working with RA Smith to proceed to next steps of process
toward utility creation.5/10/2022
11/12/2019 Finance & Public
Works
Study the feasibility of creating "Lifeline" rates for base level
utility usage "Lifeline" rate option to be considered in next rate application.7/12/2022
Next steps will be
determined by next rate
case
4/28/2020 Community
Development
Assistance for Landlords and Tenants during COVID
Emergency
Staff continues to work with advocacy and partner agencies using
funding assistance from HUD's CDBG program. 7/12/2022
6/9/2020 City Manager Community Conversations to address racism City Manager seeking contacts to initiate discussions with community
leaders to identify next steps.7/12/2022 Delayed due to COVID
pandemic
1/1/2021 City Manager
Identify and pursue a strategy for the city to provide support
for short and long-term solutions to reduce and end
homelessness.
Day By Day to purchase property from the Housing Authority after award
of grant. Tiny Homes has submitted application for zoning/site plan
approval.
5/10/2022
1/1/2021 City Manager
Continue incorporating equity and inclusion into the day-to-
day operations and structures of the Oshkosh city government
by doing the following: (a) Create employee DEI committee
and begin reporting on approved DEI measures; and (b)
Support DEI Committee and its consultant to create the DEI
Committee Strategic Plan.
Consultant is currently conducting DEI training with staff. DEI has
approved DEI metrics for departments.7/12/2022
1/1/2021 City Manager
Present funding options to begin implementation of ADA
improvements as recommended by SRF / Accessibility Audit
of Oshkosh Public Buildings and Facilities Report.
Follow up workshop with Council to be scheduled.5/10/2022
1/1/2021 City Manager
Continue participating in State multi-organizational
committee on Local Government Funding (LGFC) to address
Oshkosh’s shortfall in state-local funding, with particular
attention to Municipal Services Payment (MSP) program,
Shared Revenue, and Transportation Aids.
City Manager continues to participate as a member of statewide
committee to investigate local sources of revenue.7/12/2022
8/24/2021 Community
Development Convention and Visitors Bureau (CVB) Tourism Assessment
City staff will continue to work with the CVB on moving forward with
recommendations. CVB staff and city staff are working with a consultant
to start the rebranding process and are discussing the feasibility of a
downtown plaza. The City and the BID continue to work on
recommendations from the study to improve the downtown.
5/10/2022
04.12.22
City of Oshkosh Status of Outstanding Issues
Council Meeting
print date: 4/8/2022