HomeMy WebLinkAboutTID #42 Project Plan        City of Oshkosh, Wisconsin Organizational Joint Review Board Meeting Held: Scheduled for April 1, 2022 Public Hearing Held: Scheduled for April 5, 2022 Approval by Plan Commission: Scheduled for April 5, 2022 Adoption by Common Council: Scheduled for April 26, 2022 Approval by the Joint Review Board: TBD April 5, 2022 Project Plan Tax Incremental District No. 42 Morgan Crossing Phase II Page 3   Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 2  Table of Contents Executive Summary.................................................................................................................................. 3 Preliminary Maps of Proposed District Boundary ........................................................................ 6 Maps Showing Existing Uses and Conditions .............................................................................. 10 Preliminary Parcel List and Analysis ................................................................................................. 13 Equalized Value Test ............................................................................................................................. 14 Statement Listing the Kind, Number and Location of All Proposed Public Works or Improvements Within the District ..................................................................................................... 15 Maps Showing Proposed Improvements and Uses ..................................................................... 21 Detailed List of Estimated Project Costs ...................................................................................... 24 Economic Feasibility Study, Description of the Methods of Financing Estimated Project Costs and the Time When Related Costs or Monetary Obligations are to be Incurred ....................................................................................................................................................... 25 Annexed Property .................................................................................................................................. 30 Estimate of Property to Be Devoted to Retail Business ......................................................... 30 Proposed Changes of Zoning Ordinances, Master Plan, Map, Building Codes and City Ordinances ................................................................................................................................................ 30 Statement of the Proposed Method for the Relocation of any Persons to be Displaced ......................................................................................................................................................................... 31 How Creation of the Tax Incremental District Promotes the Orderly Development of the City ......................................................................................................................................................... 31 List of Estimated Non-Project Costs ............................................................................................... 32 Legal Opinion Advising Whether the Plan is Complete and Complies with Wis. Stat. § 66.1105(4)(f) ..............................................................................................................................................33 Calculation of the Share of Projected Tax Increments Estimated to be Paid by the Owners of Property in the Overlying Taxing Jurisdictions .....................................................35       Page 4 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 3    SECTION 1: Executive Summary Description of District Tax Incremental District (“TID”) No. 42 (“District”) is a proposed 1.41-acre Blighted Area district consisting of tax parcel 01-02440-200 located at the southwest corner of Pearl Avenue and Riverway Drive. The District will be created to pay the costs of development incentives, public infrastructure and other related costs needed to facilitate construction of a 5-story 83-unit multi- family building (“Project”) to be developed by Morgan Crossing 2, LLC (“Developer”). In addition to the incremental property value that will be created, the City expects the Project will result in the provision of housing units geared towards young professionals, University of Wisconsin – Oshkosh staff, co-living, and senior living residents. The Project will also result in the creation of interim construction jobs, and an estimated five new permanent jobs related to the operation of the Project. Authority The City is creating the District under the provisions of Wis. Stat. § 66.1105. Estimated Total Project Cost Expenditure The City anticipates making total expenditures of approximately $2,467,000 (“Project Costs”) to undertake the projects listed in this Project Plan (“Plan”). Project Costs includes $2,250,000 in development incentives, $122,000 for public infrastructure, $2,678 in interest expense related to projected advances, and $92,060 for District administrative costs related to its creation and ongoing administration. Incremental Valuation The City projects that new land and improvements value of approximately $10 million will result from the Project. Creation of this additional value will be made possible by the Project Costs made within the District. A table detailing assumptions as to the development timing and associated values is included in the Economic Feasibility Study located within this Plan. Expected Termination of District Based on the Economic Feasibility Study located within Section 9 of this Plan, the City anticipates that the District will generate sufficient tax increment to pay all Project Costs within 13 of its allowable 27 years, representing 11 years of actual tax increment collection. Page 5 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 4    Summary of Findings As required by Wis. Stat. § 66.1105, and as documented in this Plan and the exhibits contained and referenced herein, the following findings are made: 1. That “but for” the creation of this District, the development projected to occur as detailed in this Plan: 1) would not occur; or 2) would not occur in the manner, at the values, or within the timeframe desired by the City. In reaching this determination, the City has considered a review undertaken by Ehlers in 2020 of the original Project’s sources and uses, and cash flow proforma. (The originally proposed Project consisted of a 4-story 74-unit multi-family building). Due to costs associated with environmental remediation and provision of underground parking, the Project’s projected returns on investment over 10 years without TIF assistance were negative. The Developer initially requested that the City provide incentive payments on a pay as you go basis with a future value of $1,850,000. With this level of TIF assistance, cash on cash returns reached only 2% by the third year of operations, and 6% in year ten with an adjusted internal rate of return slightly less than breakeven. The Developer subsequently paused the Project due to issues related to utilities and in 2022 submitted a revised assistance request for $2,250,000 in future value incentive payments based on further increases in cost. The size of the Project was also increased to a 5-story building with a total of 83-units. Based on Ehlers original review, provision of pay as you go incentives in the amount requested was necessary to provide an acceptable return on investment for this Developer and indicated that “but for” the incentives, the project would not likely proceed. Given the additional costs now associated with the Project, the City concludes that the “but for” test continues to be met. 2. The economic benefits of the District, as measured by increased employment, business and personal income, and property value, are sufficient to compensate for the cost of the improvements. In making this determination, the City has considered that in addition to the incremental value expected to be created, the Project will result in development of a blighted area, remediation of contaminated soils, creation of market rate multi-family housing to meet market demand, and provision of employment and commercial opportunities related to the construction and operation of the Project. 3. The benefits of the proposal outweigh the anticipated tax increments to be paid by the owners of property in the overlying taxing jurisdictions. As required by Wis. Stat. § 66.1105(4)(i)4., a calculation of the share of projected tax increments estimated to be paid by the owners of property in the overlying taxing jurisdictions has been prepared and can be found in this Plan. However, because the Project would not occur without the use of tax incremental financing, these tax increments would not be paid but for Page 6 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 5    creation of the District. Accordingly, the City finds that the benefits expected to be realized as set forth in this Plan outweigh the value of the tax increments to be invested in the Project. 4. As detailed in Section 4 of this Plan, not less than 50% by area of the real property within the District is a blighted area as defined by Wis. Stat. § 66.1105(2)(ae)1. 5. Based on the foregoing finding, the District is designated as a blighted area district. 6. The Project Costs relate directly to the elimination of blight in the District, consistent with the purpose for which the District is created. 7. Improvements to be made in the District are likely to significantly enhance the value of substantially all of the other real property in the District. 8. The equalized value of taxable property in the District, plus the incremental value of all existing tax incremental districts within the City does not exceed 12% of the total equalized value of taxable property within the City. 9. The City estimates that none of the territory within the District will be devoted to retail business at the end of the District’s maximum expenditure period, pursuant to Wis. Stat. § 66.1105(5)(b). 10. That there are no parcels to be included within the District that were annexed by the City within the preceding three-year period. 11. The Plan for the District is feasible and is in conformity with the Master Plan of the City. Page 7 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 6    SECTION 2: Preliminary Maps of Proposed District Boundary Maps Found on Following Pages. Page 8 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 7    Page 9 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 8    Page 10 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 9    Page 11 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 10    SECTION 3: Maps Showing Existing Uses and Conditions Maps Found on Following Pages. Page 12 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 11    Page 13 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 12    Page 14 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 13    SECTION 4: Preliminary Parcel List and Analysis The District will consist of a single tax parcel: Parcel Number: 01-0244-02-00 Address: 0 Pearl Avenue Owner: Morgan Crossing 2 LLC The parcel is also presently located within the City’s Tax Incremental Districts No. 13 and No. 21. The parcel is a “blighted area” as defined in Wis. Stat. § 66.1105(2)(ae), as an area which is predominantly open that consists of land upon which buildings or structures have been demolished and which because of obsolete platting, diversity of ownership, deterioration of structures or of site improvements, or otherwise, substantially impairs or arrests the sound growth of the community. In its current state, development of the property has not occurred as the land contains soil contamination resulting from prior uses. Developer, working with an environmental engineering consultant, has prepared a plan to remove or cap all contaminated soils on the site. Costs associated with this remediation have resulted in the property not developing under normal market conditions, substantially impairing and arresting the sound growth of the community, rendering the parcel blighted. Details regarding the environmental conditions at the site are described within Phase I and Phase II Environmental Site Assessments, and within a Remedial Action Plan prepared for the site. These reports are on file with the City and further support the finding that the site is a blighted area. Page 15 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 14    SECTION 5: Equalized Value Test The following calculations demonstrate that the City expects to be in compliance with Wis. Stat. § 66.1105(4)(gm)4.c., which requires that the equalized value of the taxable property in the proposed District, plus the value increment of all existing tax incremental districts, does not exceed 12% of the total equalized value of taxable property within the City. The equalized value of the increment of existing tax incremental districts within the City, plus the base value of the proposed District, totals $258,409,200. This value is less than the maximum of $578,533,500 in equalized value that is permitted for the City. Page 16 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 15    SECTION 6: Statement Listing the Kind, Number and Location of All Proposed Public Works or Improvements Within the District Project Costs are any expenditure made, estimated to be made, or monetary obligation incurred or estimated to be incurred as outlined in this Plan. Project Costs will be diminished by any income, special assessments or other revenues, including user fees or charges, other than tax increments, received or reasonably expected to be received in connection with the implementation of the Plan. If Project Costs incurred benefit territory outside the District, a proportionate share of the cost is not a Project Cost. Costs identified in this Plan are preliminary estimates made prior to design considerations and are subject to change after planning, design and construction is completed. With all Project Costs, the costs of engineering, design, survey, inspection, materials, construction, restoring property to its original condition, apparatus necessary for public works, legal and other consultant fees, testing, environmental studies, permits, updating City ordinances and plans, judgments or claims for damages and other expenses are included as Project Costs. The following is a list of public works and other tax incremental financing eligible Project Costs that the City expects to make, or may need to make, in conjunction with the implementation of the District’s Plan. The map found in Section 7 of this Plan along with the Detailed List of Project Costs found in Section 8 provide additional information as to the kind, number and location of potential Project Costs. Property, Right-of-Way and Easement Acquisition Acquisition of Rights-of-Way The City may need to acquire property to allow for installation of streets, driveways, sidewalks, utilities, stormwater management practices and other public infrastructure. Costs incurred by the City to identify, negotiate and acquire rights-of-way are eligible Project Costs. Acquisition of Easements The City may need to acquire temporary or permanent easements to allow for installation and maintenance of streets, driveways, sidewalks, utilities, stormwater management practices and other public infrastructure. Costs Page 17 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 16    incurred by the City to identify, negotiate and acquire easement rights are eligible Project Costs. Relocation Costs If relocation expenses are incurred in conjunction with the acquisition of property, those expenses are eligible Project Costs. These costs may include but are not limited to preparation of a relocation plan; allocations of staff time; legal fees; publication of notices; obtaining appraisals; and payment of relocation benefits as required by Wis. Stat. Chapter 32 and Wis. Admin. Code ADM 92. Site Preparation Activities Environmental Audits and Remediation If it becomes necessary to evaluate any land or improvement within the District, any cost incurred by the City related to environmental audits, testing, and remediation are eligible Project Costs. Utilities Sanitary Sewer System Improvements To allow development to occur, the City may need to construct, alter, rebuild or expand sanitary sewer infrastructure within the District. Eligible Project Costs include, but are not limited to, construction, alteration, rebuilding or expansion of collection mains; manholes and cleanouts; service laterals; force mains; interceptor sewers; pumping stations; lift stations; wastewater treatment facilities; and all related appurtenances. To the extent sanitary sewer projects undertaken within the District provide direct benefit to land outside of the District, the City will make an allocation of costs based on such benefit. Those costs corresponding to the benefit allocated to land within the District, and necessitated by the implementation of the Project Plan, are eligible Project Costs. Implementation of the Project Plan may also require that the City construct, alter, rebuild or expand sanitary sewer infrastructure located outside of the District. That portion of the costs of sanitary sewer system projects undertaken outside the District which are necessitated by the implementation of the Project Plan are eligible Project Costs. The improvements to the wastewater treatment facilities, although not within the ½ mile radius, is an eligible project cost under Wis. Stat. § 66.1105(2)(f)1 k. Page 18 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 17    Water System Improvements To allow development to occur, the City may need to construct, alter, rebuild or expand water system infrastructure within the District. Eligible Project Costs include, but are not limited to, construction, alteration, rebuilding or expansion of distribution mains; manholes and valves; hydrants; service laterals; pumping stations; wells; water treatment facilities; storage tanks and reservoirs; and all related appurtenances. To the extent water system projects undertaken within the District provide direct benefit to land outside of the District, the City will make an allocation of costs based on such benefit. Those costs corresponding to the benefit allocated to land within the District, and necessitated by the implementation of the Project Plan, are eligible Project Costs. Implementation of the Project Plan may also require that the City construct, alter, rebuild or expand water system infrastructure located outside of the District. That portion of the costs of water system projects undertaken outside the District which are necessitated by the implementation of the Project Plan are eligible Project Costs. Stormwater Management System Improvements Development within the District will cause stormwater runoff. To manage this stormwater runoff, the City may need to construct, alter, rebuild or expand stormwater management infrastructure within the District. Eligible Project Costs include, but are not limited to, construction, alteration, rebuilding or expansion of: stormwater collection mains; inlets, manholes and valves; service laterals; ditches; culvert pipes; box culverts; bridges; stabilization of stream and river banks; and infiltration, filtration and detention Best Management Practices (BMP’s). To the extent stormwater management system projects undertaken within the District provide direct benefit to land outside of the District, the City will make an allocation of costs based on such benefit. Those costs corresponding to the benefit allocated to land within the District, and necessitated by the implementation of the Project Plan, are eligible Project Costs. Implementation of the Project Plan may also require that the City construct, alter, rebuild or expand stormwater management infrastructure located outside of the District. That portion of the costs of stormwater management system projects undertaken outside the District which are necessitated by the implementation of the Project Plan are eligible Project Costs. Page 19 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 18    Electric Service To create sites suitable for development, the City may incur costs to provide, relocate or upgrade electric services. Relocation may require abandonment and removal of existing poles or towers, installation of new poles or towers, or burying of overhead electric lines. Costs incurred by the City to undertake this work are eligible Project Costs. Gas Service To create sites suitable for development, the City may incur costs to provide, relocate or upgrade gas mains and services. Costs incurred by the City to undertake this work are eligible Project Costs. Communications Infrastructure To create sites suitable for development, the City may incur costs to provide, relocate or upgrade infrastructure required for voice and data communications, including, but not limited to telephone lines, cable lines and fiber optic cable. Costs incurred by the City to undertake this work are eligible Project Costs. Streets and Streetscape Street Improvements To allow development to occur, the City may need to construct or reconstruct streets, highways, alleys, access drives and parking areas. Eligible Project Costs include, but are not limited to: excavation; removal or placement of fill; construction of road base; asphalt or concrete paving or repaving; installation of curb and gutter; installation of sidewalks and bicycle lanes; installation of culverts, box culverts and bridges; rail crossings and signals; utility relocation, to include burying overhead utility lines; street lighting; installation of traffic control signage and traffic signals; pavement marking; right-of-way restoration; installation of retaining walls; and installation of fences, berms, and landscaping. Streetscaping and Landscaping To attract development consistent with the objectives of this Plan, the City may install amenities to enhance development sites, rights-of-way and other public spaces. These amenities include but are not limited to landscaping; lighting of streets, sidewalks, parking areas and public areas; installation of planters, benches, clocks, tree rings, trash receptacles and similar items; and installation of brick or other decorative walks, terraces and street crossings. These and any other similar amenities installed by the City are eligible Project Costs. Page 20 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 19    Community Development Cash Grants (Development Incentives) The City may enter into agreements with property owners, lessees, or developers of land located within the District for sharing costs to encourage the desired kind of improvements and assure tax base is generated sufficient to recover Project Costs. No cash grants will be provided until the City executes a developer agreement with the recipient of the cash grant. Any payments of cash grants made by the City are eligible Project Costs. Miscellaneous Projects Outside the Tax Increment District Pursuant to Wis. Stat. § 66.1105(2)(f)1.n, the City may undertake projects within territory located within one-half mile of the boundary of the District provided that: 1) the project area is located within the City’s corporate boundaries; and 2) the projects are approved by the Joint Review Board. The cost of projects completed outside the District pursuant to this section are eligible project costs and may include any project cost that would otherwise be eligible if undertaken within the District. The City intends to make the following project cost expenditures outside the District: installation of cul-de-sacs at the present terminations of Dawes Street and Riverway Drive. Professional Service and Organizational Costs The costs of professional services rendered, and other costs incurred, in relation to the creation, administration and termination of the District, and the undertaking of the projects contained within this Plan, are eligible Project Costs. Professional services include but are not limited to architectural; environmental; planning; engineering; legal; audit; financial; and the costs of informing the public with respect to the creation of the District and the implementation of the Plan. Administrative Costs The City may charge to the District as eligible Project Costs reasonable allocations of administrative costs, including, but not limited to, employee salaries. Costs allocated will bear a direct connection to the time spent by City employees relating to the implementation of the Plan. Page 21 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 20    Financing Costs Interest expense, debt issuance expenses, redemption premiums, and any other fees and costs incurred in conjunction with obtaining financing for projects undertaken under this Plan are eligible Project Costs. Page 22 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 21    SECTION 7: Maps Showing Proposed Improvements and Uses Maps Found on Following Pages. Page 23 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 22    Page 24 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 23    Page 25 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 24    SECTION 8: Detailed List of Estimated Project Costs The following list identifies the Project Costs that the City currently expects to incur in implementing the District’s Plan. All projects identified and related costs reflect the best estimates available as of the date of preparation of this Plan. All costs are preliminary estimates and may increase or decrease. Certain Project Costs listed may become unnecessary, and other Project Costs not currently identified may need to be made. (Section 6 details the general categories of eligible Project Costs). Changes in Project Cost totals or the types of Project Costs to be incurred will not require that this Plan be amended. This Plan is not meant to be a budget nor an appropriation of funds for specific Project Costs, but a framework within which to manage Project Costs. Page 26 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 25    SECTION 9: Economic Feasibility Study, Description of the Methods of Financing Estimated Project Costs and the Time When Related Costs or Monetary Obligations are to be Incurred This Section includes a forecast of the valuation increases expected within the District, the associated tax increment collections, a summary of how Project Costs would be financed, and a projected cash flow demonstrating that the District is economically feasible. Key Assumptions The Project Costs the City plans to make are expected to create $10 million in incremental value by January 1, 2024. Estimated valuations and timing for construction of the Project are included in Table 1. Assuming the City’s current equalized TID Interim tax rate of $24.41 per thousand of equalized value, and no economic appreciation or depreciation, the Project would generate $6,383,007 in incremental tax revenue over the 27-year term of the District as shown in Table 2. Page 27 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 26    Table 1 – Development Assumptions Page 28 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 27    Table 2 – Tax Increment Projection Worksheet Page 29 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 28    Financing and Implementation The City anticipates making total expenditures of approximately $2,467,000 including $2,250,000 in development incentives, $122,000 for public infrastructure, $2,678 in interest expense related to projected advances, and $92,060 for District administrative costs related to its creation and ongoing administration. Development incentive payments will be paid from tax increments as they are collected on a “pay as you go” basis. Infrastructure improvements will also be paid from cash as it is available. Administrative expenses will be paid from tax increments collected, or from advances from other funds to the extent those costs exceed cash amounts available. The City will recover any amounts advanced to the District as cash flows permit. Based on the cash flow exhibit (Table 3), the City anticipates that the District will generate enough tax increment to pay all Project Costs by the year 2034, reflecting 11 years of tax increment collections, and 13 years of total elapsed time. If necessary, the District would be permitted to remain open for up to 29 years, allowing for up to a total of 27 years of tax increment collection. The projected closure is based on the various assumptions noted in this Plan and will vary dependent on actual Project Costs incurred and the actual amount of tax increments collected. Page 30  Tax Incremental District No. 40 Project Plan  City of Oshkosh Prepared by Ehlers  Page | 29  Table 3 – Cash Flow Page 31   Tax Incremental District No. 40 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 30  SECTION 10: Annexed Property A tax incremental district cannot include annexed territory unless at least three years have elapsed since the annexation, or certain other requirements are met. None of the property within the proposed District boundary was annexed during the past three years. SECTION 11: Estimate of Property to Be Devoted to Retail Business Pursuant to Wis. Stat. § 66.1105(5)(b), the City estimates that none of the territory within the District will be devoted to retail business at the end of the District’s maximum expenditure period. SECTION 12: Proposed Changes of Zoning Ordinances, Master Plan, Map, Building Codes and City Ordinances Zoning Ordinances Current zoning is Urban Mixed Use with a Planned Development overlay (UMU- PD). The proposed Plan is in general conformance with the City’s current zoning ordinances. Master (Comprehensive) Plan and Map The proposed Plan is in general conformance with the City’s Comprehensive Plan identifying the area as appropriate for multi-family development. Building Codes and Ordinances Development within the District will be required to conform to State Building Codes and will be subject to the City's permitting and inspection procedures. The proposed Plan conforms to all relevant State and local ordinances, plans, and codes. No changes to the existing regulations are proposed or needed. Page 32 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 31    SECTION 13: Statement of the Proposed Method for the Relocation of any Persons to be Displaced Should implementation of this Plan require relocation of individuals or business operations, relocations will be handled in compliance with Wis. Stat. Chapter 32 and Wis. Admin. Code ADM 92. SECTION 14: How Creation of the Tax Incremental District Promotes the Orderly Development of the City Creation of the District and the implementation of the projects in its Plan will promote the orderly development of the City by eliminating blighted areas, providing necessary public infrastructure improvements and providing appropriate financial incentives for private development projects. Through use of tax increment financing, the City can attract new investment that results in increased tax base. Development will occur in an orderly fashion in accordance with approved plans so that the Projects will be compatible with adjacent land uses. Development of new uses in the District will add to the tax base and will generate positive secondary impacts in the community such as creation of market rate multi-family housing to meet market demand, and provision of employment and commercial opportunities related to the construction and operation of the Project Page 33 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 32    SECTION 15: List of Estimated Non-Project Costs Non-project costs are public works projects which only partly benefit the District. Costs incurred that do not benefit the District may not be paid with tax increments. Examples of non-project costs are:  A public improvement made within the District that also benefits property outside the District. That portion of the total Project Costs allocable to properties outside of the District would be a non-project cost.  A public improvement made outside the District that only partially benefits property within the District. That portion of the total Project Costs allocable to properties outside of the District would be a non- project cost.  Projects undertaken within the District as part of the implementation of this Project Plan, the costs of which are paid fully or in part by impact fees, grants, special assessments, or revenues other than tax increments. No improvements to be made within the District will benefit property outside the District. Installation of the cul-de-sac on Dawes Street may provide benefit to areas outside the District. The current estimate of that benefit is $30,500, which is a Non-Project Cost. The total cost of the Dawes Street cul-de-sac is included in this Plan as the City will make a final determination of the benefits to areas outside the District at the time the cul-de-sac is completed, and the allocation may vary. Page 34 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 33    SECTION 16: Legal Opinion Advising Whether the Plan is Complete and Complies with Wis. Stat. § 66.1105(4)(f) Legal Opinion Found on Following Page. Page 35 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 34    Page 36 Tax Incremental District No. 42 Project Plan  City of Oshkosh  Prepared by Ehlers  Page | 35    SECTION 17: Calculation of the Share of Projected Tax Increments Estimated to be Paid by the Owners of Property in the Overlying Taxing Jurisdictions The following projection is provided to meet the requirements of Wis. Stat. § 66.1105(4)(i)4. Page 37