HomeMy WebLinkAbout15. 22-103MARCH 8, 2022 22-103 RESOLUTION
(CARRIED___7-0____LOST_______LAID OVER_______WITHDRAWN_______)
PURPOSE: REJECT BID COMMUNITY DEVELOPMENT CONTRACT NO.
22-10 FOR WILLIAM WATERS PLAZA GAZEBO
CONSTRUCTION
INITIATED BY: COMMUNITY DEVELOPMENT
WHEREAS, the City of Oshkosh advertised for bids for William Waters Plaza
Gazebo construction; and
WHEREAS, the Community Foundation secured private donations totaling
$293,000.00 for construction of the William Waters Plaza Gazebo; and
WHEREAS, the City received one bid for construction of the William Waters Plaza
Gazebo in the amount of $404,800.00; and
WHEREAS, Section 62.15 (5) allows the City to reject bids; and
WHEREAS, it is in the best interests of the City to reject the bid as the Community
Foundation is unable to provide sufficient funding for the $404,800.00 project at this time.
NOW, THEREFORE, BE IT RESOLVED by the Common Council of the City of
Oshkosh that the Common Council finds that accepting the bid received for construction
of the William Waters Plaza Gazebo would be against the best interests of the City and
that the appropriate City officials are hereby authorized to reject the bid received.
City Hall, 215 Church Avenue P.O. Box 1130 Oshkosh, WI 54903-1130 920.236.5000 http://www.ci.oshkosh.wi.us
TO: Honorable Mayor and Members of the Common Council
FROM: Mark Lyons, Planning Services Manager
DATE: March 3, 2022
RE: Reject Bid Community Development Contract 22-10 for William Waters Plaza
Gazebo Construction
BACKGROUND
In 2019, the River East Neighborhood Association proposed and received approval for the
implementation of the William Waters Plaza Master Plan as an approved Great Neighborhoods
project. City staff, along with the Oshkosh Area Community Foundation, worked to secure
private donors to cover the anticipated construction costs of the project.
The City worked with MSA Professional Services, Inc. on the design, bid documents, and cost
estimates for the construction of a new gazebo as part of the ongoing renovations of William
Waters Plaza. Community Development staff worked with the Public Works staff and sought
bids for the construction of the gazebo.
ANALYSIS
A total of $293,000 was raised to cover the anticipated cost of construction. The City received
only one (1) bid for the project, totaling $404,800. Insufficient funding exists at this time to award
the bid.
RECOMMENDATION
The Common Council rejects the bid for Community Development contract 22-10 for William
Waters Plaza Gazebo Construction.
Respectfully Submitted, Approved:
Mark Lyons John Fitzpatrick
Planning Services Manager Assistant City Manager / Director of
Administrative Services
Contract 22-10 Williams Waters Gazebo Construction (#8087977)Owner: Oshkosh WI, City ofSolicitor: MSA Professional Services, Inc.Bid Opening: 01/17/2022 01:00 PM CSTSection TitleItem CodeItem DescriptionUofMQuantityUnit PriceExtensionSection 1$404,800.001Construction of a 290-sf outdoor cast-stone gazebo with associated site work; complete as specified Lump Sum 1.00 $404,800.00 $404,800.00Bid Total:$404,800.00Capelle Bros. & Diedrich, Inc.PO Box 1274Fond du Lac, WI 54935C:\Users\tracyt\Downloads\BidWorksheet_8087977_EvalPage 1 of 11/17/2022
1
Lyons, Mark
From:Naudziunas, Alexa
Sent:Thursday, February 24, 2022 10:33 AM
To:Lyons, Mark
Subject:WWPlaza
Oshkosh Area Community Foundation - William Waters Plaza
Date Description Gift amount
12/31/2021 Credit Card $ 500.00
2/3/2021 '' $ 30,000.00
5/12/2020 Stock $ 252,113.48
6/30/2018 '' $ 8,000.00
4/25/2018 Cash $ 2,500.00
4/17/2018 Check $ 150.00
3/21/2018 '' $ 500.00
Total Funds Available $ 293,763.48
Alexa Naudziunas
Associate Planner, Community Development
City of Oshkosh