HomeMy WebLinkAbout30. Outstanding IssuesDate of Initial
Request
Affected
Department(s) (If
Applicable)
Title of Directive Current Status
Date of Next
Status
Report/Update
Other Notes
1/1/2018 Facilities-OPD-OFD Facility Studies Fire Department Facility Study is underway. Due to be completed by April 1,
2022 4/12/2022
1/22/2019 Finance/DPW Fee to replace Special Assessments for Street Improvements Staff is working with RA Smith to proceed to next steps of process toward
utility creation. May be held up by legislation.4/12/2022
11/12/2019 Finance & Public
Works
Study the feasibility of creating "Lifeline" rates for base level
utility usage "Lifeline" rate option to be considered in next rate application.4/12/2022
Next steps will be
determined by next
rate case
4/28/2020 Community
Development Assistance for Landlords and Tenants during COVID Emergency Staff approved funding for assistance for tenants and landlords for Advocap
as part of the multiple funding rounds from HUD's CDBG program. 4/12/2022
6/9/2020 City Manager Community Conversations to address racism City Manager seeking contacts to initiate discussions with community leaders
to identify next steps.4/12/2022 Delayed due to COVID
pandemic
1/1/2021 City Manager Identify and pursue a strategy for the city to provide support for
short and long-term solutions to reduce and end homelessness.
Staff continues to work with Day By Day Warming Shelter and OACF on year
round permanent facility location option. Staff is working with the Oshkosh
Kid's Foundation on their Tiny Home project. Staff continues to review grant
opportunities as they become available that would support solutions to
reduce homelessness.
4/12/2022
1/1/2021 City Manager
Continue incorporating equity and inclusion into the day-to-day
operations and structures of the Oshkosh city government by
doing the following: (a) Create employee DEI committee and
begin reporting on approved DEI measures; and (b) Support DEI
Committee and its consultant to create the DEI Committee
Strategic Plan.
Consultant is currently conducting DEI training with staff. DEI Committee
provided suggestions to staff on possible DEI measures.4/12/2022
1/1/2021 City Manager
Present funding options to begin implementation of ADA
improvements as recommended by SRF / Accessibility Audit of
Oshkosh Public Buildings and Facilities Report.
Next steps with facility study TBD.4/12/2022
1/1/2021 City Manager
Continue participating in State multi-organizational committee
on Local Government Funding (LGFC) to address Oshkosh’s
shortfall in state-local funding, with particular attention to
Municipal Services Payment (MSP) program, Shared Revenue,
and Transportation Aids.
Staff continues to collaborate with other cities on legislative options outside
of budget process. City Manager is a member of statewide committee to
investigate local sources of revenue.
4/12/2022
8/24/2021 Community
Development Convention and Visitors Bureau (CVB) Tourism Assessment
City staff will continue to work with the CVB on moving forward with
recommendations. CVB staff and city staff are working with a consultant to
start the rebranding process and are discussing the feasibility of a downtown
plaza. The City and the BID continue to work on recommendations from the
study to improve the downtown.
5/10/2022
03.08.22
City of Oshkosh Status of Outstanding Issues
Council Meeting
print date: 3/4/2022