INTERGOVERNMENTAL AGREEMENT
BETWEEN WINNEBAGO COUNTY AND CITY OF OSHKOSH
1. PARTIES: This Intergovernmental Agreement is made and entered into by and
between Winnebago County and the City of Oshkosh.
2. PURPOSE: The County is undertaking at its expense some shoreline rehabilitation
at the end of the Broad Street right-of-way. The City has future plans to construct a
storm water outfall pipe in the same shoreline area that the County will be
rehabilitating. The parties have agreed that it would be beneficial to both for the
County's engineering consultant that is designing the shoreline rehabilitation to
also review and incorporate the City's future outfall design plans into the County's
shoreline plans. The County and City wish to make it clear that the additional
amounts the County is billed by its engineering consultant for work related to the
City's future outfall project will be reimbursed by the City.
3. LOCATION: The location of the shoreline rehabilitation project is at the end of and
within the Broad Street public right-of-way at the shoreline of the Fox River. The
County's shoreline rehabilitation project is adjacent to and nearby a boathouse that
has been used by the County Sheriff's Department for Decades. Ownership of the
boathouse was conveyed from the City to the County through a Bill of Sale signed
on June 02, 2021. The area in the right-of-way underneath that boathouse was
leased by the City to the County through a long term lease. The Lease allows the
County to perform certain shoreline work necessary to protect and enhance the
boathouse structure.
4. PROJECT: The City has consulted with both the County and the County's
engineering consultant regarding the City's engineering and design needs. The
County's consultant, MartinRiley, has provided a proposal that encompasses the
City's project needs. The proposal is attached to this Agreement as Exhibit A.
5. PAYMENT: MartinRiley will bill the County for, among other costs, the amount
identified in Exhibit A. The County will pay MartinRiley for these expenses. The
City, in return, promises and agrees to promptly reimburse the County for the
costs that it has paid MartinRiley that are related to the work described in Exhibit
A that benefits the City. The MartinRiley costs to be reimbursed by the City will be
strictly pass through costs, and there shall be no administrative, handling, or other
fees or costs added to the reimbursement requests. Reimbursements to the County
is expected within thirty (30) days after the City receives the reimbursement
request.
October 14, 2021 1
6. CHANGES: In the event changes are made to the work described in Exhibit A, the
City similarly agrees to reimburse the County for those additional costs as long as
the City has been notified of and approved those changes in writing,in advance.
7. FUTURE AGREEMENTS: This purpose of this intergovernmental agreement is
solely related to design elements of the project and explicitly does not include
reimbursement for any construction work. It is anticipated that after the project
design is complete and the project is bid out, a second Intergovernmental
Agreement will be entered into between the County and City related to
reimbursement and other matters related to that phase of the overall project.
8. NOTICES: It is expected that both parties will work together in good faith during
this project, with each promptly responding to informal questions or requests.
Formal notices or requests are expected to be sent in writing either through hand
delivery, or through USPS certified mail, return receipt requested, to the following
addresses:
a. For the County:
Winnebago County
c/o Director of Facilities
1221 Knapp Street
Oshkosh,WI 54902
b. For the City
City of Oshkosh
c/o Director of Public Works
PO Box 1130
Oshkosh, WI 54903-1130
9. TERMINATION: This Agreement may be terminated with or without cause by
either party after thirty (30) day notice. However, costs incurred related to the
City's part of the project that have been incurred by MartinRiley and/or the County
through the date of termination shall be reimbursed by the City.
10. AUTHORITY: Both parties agree and acknowledge that all of the necessary
boards, committees, and elected officials have approved and authorized this
Agreement.
SIGNATURE PAGE FOLLOWS
October 14,2021 2
Dated: a VA / 9)1 ?O? )
CITY OF OSHKOSH:
By: a--,(- 1- /
Mark A. Rohloff, City Manager
By: __ fluM
Pamela R. Ubrig, City Clerk
App7ved as to form:
I
Lynn A. orenson, torney
WIN A O COUN
By: I
an oemel, County Executive
By: 2,49 t
Sue Ertmer, County Clerk
Ap to for .
Mary A r9
M lie , orl ounsel
October 14, 2021 3
MARTINRILEY
arohlt.ecto-engtnsars
Approval of Additional Fee
PROJECT: Winnebago County Sheriff's Boathouse
MARTINRILEY PROJECT NUMBER: 021062
WINNEBAGO COUNTY: RFP#SH05-01
WINNEBAGO COUNTY PURCHASE ORDER: 20210405
REASON FOR AND DESCRIPTION OF ADDITIONAL FEE:
Additional Design and Engineering Services of MartinRiley and its consultant, Larson
Engineering to coordinate and incorporate into the boathouse bid documents the
installation of the City of Oshkosh's planned storm sewer from the river to the first
existing manhole (approximately 75-100 linear feet). New outfall for the City of
Oshkosh is to be located directly east of the Winnebago County Sheriff's boathouse
making its incorporation into the boathouse project necessary and desired by both the
City of Oshkosh and Winnebago County. City to reimburse County for amount listed.
SCOPE OF WORK
MartinRiley through its consultant shall:
• Coordinate with the City of Oshkosh the inclusion of the City's proposed new
storm sewer outfall in the construction documents for the Sheriff's boathouse.
• The City of Oshkosh is responsible for the design of the new outfall including:
pipe sizing, invert elevation at the river, pipe slope, and all pertinent design
calculations needed for permitting.
• MartinRiley/Larson Engineering will discuss with the DNR the inclusion of the
outfall in the permitting for the boathouse, if the DNR will allow the permit to
include the outfall.
ADDITIONAL FEE: Four thousand one hundred and forty and no hundredths ($4,140)
I hereby approve the expenditure listed above as an additional reimbursable expense
for this project.
Mike Elder Date
Director of Facilities a Property Management
Winnebago County
Z:12021 Projects1021062 Winnebago Co Sheriffs Boathouse\AIA Documents\Agreements\LARSON\SheriffsBoathouse-
StormSewerOutfaU.doc
404 N. Main Street, Suite 601, Oshkosh, WI 54901 1920.267,3600 I www.martin-riley.com
EXHIBIT A (1 of 1)