HomeMy WebLinkAboutChange Order No. 1 Contract 18-13 PTS Contractors City
f
Oshkosh
June 26, 2020
Casey Ashman
PTS Contractors, Inc.
4075 Eaton Road
Green Bay, WI 54311
RE: Change Order No. 1 (Final)
Contract 18-13
Dear Casey:
Enclosed is an executed copy of Change Order No. 1 (Final) between the City of
Oshkosh and PTS Contractors, Inc. regarding the abovementioned project. •
If you have any questions, please call our office at(920)236-5065.
Sincerely,
J es Rabe, P.E., CPESC
Director of Public Works
JER/tit
Enclosure: Change Order No. 1 (Final)
cc: Pam Ubrig, City Clerk (w/original)
Jennifer Messerschmidt, Assistant Finance Director (w/copy)
File (w/original)
I:\Engineering\2018 CONTRACTS\18-13 San Swr Relay\Project_Information\Contract Info\Change
Orders\18-13 Executed CO ill(Final)Ltr_6-26-2!).do, Page 1 of 1
City Hall,215 Church Avenue P.O.Box 1 130 Oshkosh,WI 54903-1130 http://www.ci.oshkosh.wi.us
TO: PTS CONTRACTORS, INC. CHANGE ORDER#1 FINAL(REVISED)
4075 EATON ROAD DATE APRIL 16, 2020
GREEN BAY,WI 54311
Your present contract with the City of Oshkosh, Contract No. 18-13, awarded June 12,2018, is hereby amended
and changed as follows:
NET INCREASE TO SECTION I: $109,835.70
NET DECREASE TO SECTION I: ($78,064.75)
NET INCREASE TO CONTRACT $31,770.95
SECTION I TOTALS
BID TOTAL $3,895,768.30 $3,895,768.30
CO#1 $31,770.95 $31,770.95
CONTRACT TOTAL $3,927,539.25 $3,927,539.25
CITY OF OSHKOSH
BY:
City Manage
iMnn
City Clerk
1
Approve?and accepted:
1
rn•% -- 7 I .r
Contractor
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh,Wisconsin,
under the within Change Order.
7/:— l'‘‘‘' 7"/
Comet oiler
Approved a a form: '
c .21t. A di -•
...al‘-- a tg..e.
City Alto •-
•
RECEIVED
JUN302020
•
CITY CLERK'S OFFICE
CONTRACT 18-13 CHANGE ORDER#1 FINAL(REVISED)
18-13
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Removing pavement; Square
1100 complete as specified Yards 16,420.00 16,245.91 -174.09 $2.30 ($400.41)
Removing concrete and
asphalt sidewalk and
driveway; complete as Square
1120 specified Feet 10,200.00 9,785.39 -414.61 $0.75 ($310.96)
Unclassified excavation; Cubic
1200 complete as specified Yards 4,150.00 4,995.95 845.95 $18.90 $15,988.46
7"concrete pavement
removal and replacement;
including sawing; pavement
ties;dowel bars; bond
breaker; integral curb and
fine grading;turf restoration;
and traffic control; complete Square
1308 as specified Yards 1,850.00 2,017.10 167.10 $60.50 $10,109.55
8"concrete pavement HES
removal and replacement;
including sawing; pavement
ties; dowel bars; bond
breaker; integral curb and
fine grading;turf restoration;
and traffic control;complete Square
1319 as specified Yards 1,225.00 1,435.80 210.80 $71.30 $15,030.04
Adjust manholes and inlets;
1360 complete as specified Each 84.00 88.00 4.00 $360.00 $1,440.00
Turf restoration on Buchanan
Avenue;complete as Square
1370A specified Yards 131.00 433.03 302.03 $11.30 $3,412.94
Turf restoration on North
Eagle Street;complete as Square
1370B specified Yards 286.00 420.90 134.90 $10.25 $1,382.73
Turf restoration on Fox Square
1370C Street;complete as specified Yards 394.00 386.02 -7.98 $9.75 ($77.81)
Turf restoration on Graham
Avenue; complete as Square
1370D specified Yards 1,232.00 1,439.51 207.51 $9.20 $1,909.09
Turf restoration on Hawk Square
1370E Street;complete as specified Yards 503.00 556.83 53.83 $9.20 $495.24
Turf restoration on Maple
Avenue; complete as Square
1370F specified Yards 147.00 401.30 254.30 $11.30 $2,873.59,
Turf restoration on Punhoqua Square
1370G Street;complete as specified Yards 2,800.00 3,157.58 357.58 $9.20 $3,289.74,
Turf restoration on Vine
Street outfall; complete as Square
1370H specified Yards 27.00 240.11 213.11 $15.40 $3,281.89
Restore gravel driveway/ Square
1372 apron; complete as specified Yards 15.00 0.00 -15.00 $20.50 ($307.50)
Cold weather covering
(concrete pavement)-single
visquine;complete as Square
1380 specified Yards 264.00 82.00 -182.00 $5.20 ($946.40)
Page 1 of 8
CONTRACT 18-13 CHANGE ORDER#1 FINAL(REVISED)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Up-charge for late season
cold weather concrete
pavement; complete as Cubic
1390 specified Yards 54.00 105.00 51.00 S10.25 $522.75
12"radius curb with 6"CABC
and grading; complete as Linear
1410 specified Feet 115.00 178.88 63.88 $11.30 $721.84
18"concrete curb and gutter
removal and replacement;
including sawing; pavement
ties;dowel bars; bond
breaker; integral curb and
fine grading;turf restoration;
and traffic control;complete Linear
1428 as specified Feet 50.00 21.21 -28.79 $43.00 ($1,237.97)
4"concrete sidewalk with 3"
CABC and grading;complete Square
1500 as specified Feet 6,300.00 6,657.21 357.21 $6.90 $2,464.75
6"concrete sidewalk/
driveway/ramp with 3"CABC
and grading; complete as Square
1510 specified Feet 1,560.00 3,017.00 1457.00 $7.65 $11,146.05
6"concrete step; complete as Square
1530 specified Feet 20.00 76.03 56.03 $41.00 $2,297.23
Curb ramp detectable
warning field(natural/non-
painted);complete as Square
1540 specified Feet 168.00 240.00 72.00 $36.00 $2,592.00,
No. 4 reinforcing rods-
deformed;epoxy-coated; Linear
1550 complete as specified Feet 2,025.00 2,144.73 119.73 $0.85 $101.77
Drilled No.4 sidewalk tie bars
-deformed; epoxy-coated;
1560 complete as specified Each 338.00 370.00 32.00 $6.20 $198.40
Sawing existing pavement; Linear
1700 complete as specified Feet 6,000.00 2,881.23 -3,118.77 $2.10 ($6,549.42)
Base aggregate dense; 3/4";
1800 complete as specified Tons 770.00 540.70 -229.30 $18.00 (S4,127.40)
Tack coat;complete as
1900 specified Gallons 2,160.00 1,160.00 -1,000.00 $2.90 ($2,900.00)
HMA Pavement MT;
1902 complete as specified Tons 2,400.00 2,128.20 -271.80 $60.20 ($16,362.35)
HMA cold weather paving;
1903 complete as specified Tons 300.00 0.00 -300.00 $64.00 ($19,200.00)
5"asphaltic pavement MT
with 10"CABC and grading; Square
1905 complete as specified Yards 12.00 28.03 16.03 $64.00 $1,025.92
4"asphaltic pavement LT
with 10"CABC and grading; Square
1906 complete as specified Yards 15,750.00 18,198.54 2448.54 $23.60 $57,785.54
4"asphaltic surface LT with
6"CABC and grading; Square
1916 complete as specified Yards 284.00 326.78 42.78 $32.75 $1,401.05
Asphaltic cold weather Square
1918 paving;complete as specified Yards 788.00 11,841.70 11053.70 $1.00 S11,053.70
Asphaltic base patching; Square
1920 complete as specified Yards 1,300.00 0.00 -1,300.00 $17.00 ($22,100.00)
Page 2 of 8
CONTRACT 18-13 CHANGE ORDER#1 FINAL(REVISED)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Asphaltic pavement milling; Square
1950 complete as specified Yards 7,900.00 8,048.90 148.90 $1.70 S253.13
Prepare foundation for
asphaltic paving on Hughes Lump
1960F Street;complete as specified Sum 1.00 1.00 $54,000.00
Furnish and install 6"storm Linear
2000 sewer:complete as specified Feet 10.00 0.00 -10.00 $102.00 ($1,020.00)
Furnish and install 8"storm Linear
2001 sewer; complete as specified Feet 40.00 144.50 104.50 $102.00 $10,659.00
Furnish and install 10"storm Linear
2002 sewer; complete as specified Feet 20.00 17.50 -2.50 $106.00 ($265.00)
Furnish and install 12"storm Linear
2003 sewer;complete as specified Feet 20.00 50.00 30.00 $108.00 $3,240.00
Furnish and install 15"storm Linear
2006 sewer;complete as specified Feet 8.00 41.00 33.00 $112.00 $3,696.00
Furnish and install 27"storm Linear
2018 sewer;complete as specified Feet 5.00 8.00 3.00 $393.00 $1,179.00
Furnish and install 30"RCP
Class V storm sewer; Linear
2023 complete as specified Feet 8.00 0.00 -8.00 $265.00 ($2,120.00)
Furnish and install 48"storm Linear
2030 sewer;complete as specified Feet 270.00 267.00 -3.00 $165.00 ($495.00)
Furnish and install 54"storm Linear
2033 sewer;complete as specified Feet 425.00 402.00 -23.00 $220.00 ($5,060.00)
Furnish and install 38"x 60" Linear
2120 CMP; complete as specified Feet 16.00 0.00 -16.00 $265.00 ($4,240.00)
Class III apron endwall with
joint ties; complete as
2150 specified Each 1.00 0.00 -1.00 $18,000.00 ($18,000.00)
Furnish and install standard
storm sewer inlet manhole(8'
diameter);complete as Vertical
2217 specified Feet 31.00 29.50 -1.50 $1,240.00 ($1,860.00)
Furnish and install Type 1
inlet(with 18"sump);
2235 complete as specified Each 7.00 9.00 2.00 $2,500.00 $5,000.00
Rebuild existing manhole; Lump
2270 complete as specified Sum 1.00 1.00 $6,630.00
Furnish and install 6"storm
sewer lateral;complete as Linear
2400 specified Feet 24.00 88.00 64.00 $115.00 $7,360.00
Furnish and install storm
sewer marker balls; complete
2404 as specified Each 2.00 6.00 4.00 $140.00 $560.00
Furnish and install storm
sewer clay dams;complete
2406 as specified Each 1.00 3.00 2.00 $240.00 $480.00
Furnish and install storm
sewer lateral inlet;complete
2408 as specified Each 1.00 2.00 1.00 $555.00 $555.00
Storm lateral inlet
adjustments;complete as
2414 specified Each 1.00 0.00 -1.00 $577.00 ($577.00)
Page 3 of 8
' CONTRACT 18-13 CHANGE ORDER#1 FINAL(REVISED)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Furnish; install;maintain; and
remove Type D modified inlet
protection; complete as
2508 specified Each 69.00 68.00 -1.00 $72.00 ($72.00)
Sediment removal-Type D
modified inlet protection;
2510 complete as specified Each 69.00 4.00 -65.00 $5.20 ($338.00)
Furnish; install; maintain; and
remove stone tracking pad;
2512 complete as specified Each 1.00 0.00 -1.00 $2,100.00 ($2,100.00)
Furnish; install; maintain; and
remove silt fence; complete Linear
2514 as specified Feet 15.00 0.00 -15.00 $4.10 ($61.50)
Furnish; install; maintain; and
remove stone bag; complete
2516 as specified Each 25.00 11.00 -14.00 $10.25 ($143.50)
Furnish; install;maintain; and
remove 12"diameter
sediment logs;complete as Linear
2518 specified Feet 130.00 100.00 -30.00 $10.25 ($307.50)
Furnish; install;maintain; and
remove ditch check;
2522 complete as specified Each 5.00 0.00 -5.00 $82.00 ($410.00)
Furnish; install; maintain;and
remove dewatering tank
system; complete as
2524 specified Each 2.00 1.00 -1.00 $2,000.00 ($2,000.00)
Furnish; install; maintain;and
remove turbidity barrier;
2526 complete as specified Each 1.00 0.00 -1.00 $3,200.00 ($3,200.00)
Furnish and install topsoil 6" Square
2600 depth;complete as specified Yards 300.00 0.00 -300.00 $7.70 ($2,310.00)
Furnish and install no-mow Square
2622 fescue; complete as specified Yards 300.00 0.00 -300.00 $0.60 ($180.00)
Furnish and install Class I;
Urban;Type A erosion
control mat;complete as Square
2632 specified Yards 300.00 206.00 -94.00 $2.30 ($216.20)
Connect to existing storm
sewer main;complete as
2850 specified Each 13.00 19.00 6.00 $1,280.00 $7,680.00
Storm sewer utility line
opening (ULO);complete as
2914 specified Each 1.00 1.00 $1,280.00
Excavation special(storm);
2950 complete as specified Tons 560.00 590.28 30.28 $26.00 $787.28
Salvage and replace existing Linear
2956 fence;complete as specified Feet 420.00 395.00 -25.00 $46.00 ($1,150.00)
Furnish and install 8"sanitary
sewer(relay); complete as Linear
3000 specified Feet 5,067.30 4,922.75 -144.55 $208.00 (S30,066.40)
Furnish and install 8"sanitary
sewer spot repair;complete Linear
3001 as specified Feet 10.00 4.00 -6.00 $1,000.00 (S6,000.00)
Furnish and install 10"
sanitary sewer(relay); Linear
3002 complete as specified Feet 952.10 903.96 -48.14 $220.00 ($10,590.80)
Page 4 of 8
CONTRACT 18-13 CHANGE ORDER#1 FINAL(REVISED)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
' Furnish and install 12"
sanitary sewer(relay); Linear
3004 complete as specified Feet 5.00 12.00 7.00 $210.00 $1,470.00
Furnish and install 8"sanitary
sewer drop; complete as Vertical
3060 specified Feet 106.00 96.17 -9.83 $363.00 ($3,568.28)
Furnish and install 10"
sanitary sewer drop; Vertical
3062 complete as specified Feet 10.00 13.30 3.30 $395.00 $1,303.50
Furnish and install standard
sanitary sewer manhole(4'
diameter);complete as Vertical
3100 specified Feet 495.00 491.51 -3.49 $280.00 ($977.20)
Furnish and install external
sanitary sewer manhole
chimney seal;complete as
3114 specified Each 40.00 39.00 -1.00 $510.00 ($510.00)
Furnish and install external
sanitary sewer manhole
chimney seal extension;
3116 complete as specified Each 2.00 0.00 -2.00 $510.00 ($1,020.00)
Furnish and install internal
sanitary sewer manhole
chimney seal;complete as
3118 specified Each 2.00 0.00 -2.00 $410.00 ($820.00)
Furnish and install internal
sanitary sewer manhole
chimney seal extension;
3120 complete as specified Each 2.00 0.00 -2.00 $390.00 ($780.00)
Reconstruct sanitary sewer
manhole(4'diameter); Vertical
3122 complete as specified Feet 6.00 0.00 -6.00 $840.00 ($5,040.00)
Furnish and install 8"x 6"
sanitary sewer factory wyes
or tees;complete as
3210 specified Each 60.00 62.00 2.00 $146.00 $292.00
Furnish and install 10"x 6"
sanitary sewer factory wyes
or tees;complete as
3212 specified Each 15.00 13.00 -2.00 $230.00 ($460.00)
Furnish and install 4"/6"
sanitary sewer lateral(relay); Linear
3234 complete as specified Feet 2,714.00 2,476.00 -238.00 S140.00 ($33,320.00)
Furnish and install 4"/6"
sanitary sewer riser(relay); Linear
3235 complete as specified Feet 525.00 542.00 17.00 $140.00 $2,380.00
Furnish and install sanitary
sewer lateral marker balls;
3236 complete as specified Each 148.00 152.00 4.00 $42.00 $168.00
Furnish and install clay
3238 dams;complete as specified Each 75.00 72.00 -3.00 $180.00 ($540.00)
Furnish and install
connection to existing 8"
sanitary sewer mains;
3300 complete as specified Each 11.00 13.00 2.00 $715.00 $1,430.00
Furnish and install
connection to existing 10"
sanitary sewer mains;
3302 complete as specified Each 5.00 5.00 $870.00
Page 5 of 8
CONTRACT 18-13 CHANGE ORDER#1 FINAL(REVISED)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Furnish and install
connection to existing 12"
sanitary sewer mains;
3304 complete as specified Each 2.00 1.00 -1.00 $1,111.00 ($1,111.00)
Furnish and install sanitary
sewer concrete collars;
3330 complete as specified Each 1.00 0.00 -1.00 $910.00 ($910.00)
Core into existing manhole;
3332 complete as specified Each 3.00 3.00 $2,700.00
Rock excavation;complete Cubic
3600 as specified Yards 50.00 0.00 -50.00 $0.01 ($0.50)
Closed circuit televising; Linear
3700 complete as specified Feet 6,015.00 5,846.75 -168.25 $2.50 ($420.63)
Closed circuit televising-
using push camera;complete
3710 as specified Each 6.00 4.00 -2.00 $450.00 ($900.00)
Abandon sanitary sewer
manholes; complete as
3800 specified Each 18.00 16.00 -2.00 $890.00 ($1,780.00)
Abandon 6"sanitary sewer; Linear
3801 complete as specified Feet 525.00 492.00 -33.00 $14.00 ($462.00)
Abandon 8"sanitary sewer; Linear
3802 complete as specified Feet 2,038.00 1,361.50 -676.50 $14.00 ($9,471.00)
Abandon 10"sanitary sewer; Linear
3804 complete as specified Feet 1,625.00 1,422.10 -202.90 $18.00 ($3,652.20)
Abandon 12"sanitary sewer; Linear
3806 complete as specified Feet 470.00 166.00 -304.00 $18.00 ($5,472.00)
Remove sanitary sewer
manholes;complete as
3852 specified Each 8.00 7.00 -1.00 $1,300.00 ($1,300.00)
Remove sanitary sewer; Linear
3854 complete as specified Feet 296.00 236.00 -60.00 $85.00 ($5,100.00)
Abandon sanitary sewer lift Linear
3860 station;complete as specified Feet 1.00 1.00 $15,000.00
Sanitary sewer utility line
opening(ULO);complete as
3890 specified Each 2.00 0.00 -2.00 $1,540.00 ($3,080.00)
Excavation special(sanitary);
3892 complete as specified Tons 30.50 0.00 -30.50 $26.00 ($793.00)
Furnish and install 6"ductile
iron water main(relay)with
polywrap; complete as Linear
4002 specified Feet 104.00 131.00 27.00 $160.00 $4,320.00
Furnish and install 12"ductile
iron water main (relay)with
polywrap;complete as Linear
4008 specified Feet 50.00 117.00 67.00 $260.00 $17,420.00
Furnish and install 1"water
service(relay); complete as Linear
4036 specified Feet 1,550.00 1,196.50 -353.50 $106.00 ($37,471.00)
Furnish and install 1"
corporation and stop box;
4048 complete as specified Each 45.00 44.00 -1.00 $660.00 ($660.00)
Furnish and install water
service clay dams; complete
4055 as specified Each 45.00 46.00 1.00 $180.00 $180.00
Page 6 of 8
CONTRACT 18-13 CHANGE ORDER#1 FINAL(REVISED)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Furnish and install
connections to existing 6"
water main;complete as
4058 specified Each 4.00 2.00 -2.00 $2,800.00 ($5,600.00)
Furnish and install
connections to existing 12"
water main; complete as
4064 specified Each 2.00 2.00 $4,880.00
Furnish and install 6"x 6"
water main cross;complete
4181 as specified Each 1.00 1.00 $530.00
Furnish and install 6"45
degree water main bend;
4236 complete as specified Each 8.00 8.00 $255.00
Furnish and install 12"45
degree water main bend;
4239 complete as specified Each 4.00 4.00 $700.00
Furnish and install 6"water
main gate valve;complete as
4401 specified Each 3.00 3.00 $1,200.00
Furnish and install 12"water
main gate valve;complete as
4404 specified Each 2.00 0.00 -2.00 $2,630.00 ($5,260.00)
Jack and bore 24"steel water
main casing pipe;complete Linear
4702 as specified Feet 30.00 39.00 9.00 $370.00 $3,330.00
Abandon water main on
Sawyer Street;complete as Lump
4900 specified Sum 1.00 0.00 -1.00 $2,000.00 ($2,000.00)
Remove water main; Lump
4920 complete as specified Sum 30.00 0.00 -30.00 $85.00 ($2,550.00)
SECTION (BID ITEMS 1100-4920)-SUBTOTAL: $224,267.18 ($302,331.93)
NET DECREASE TO SECTION I: ($78,064.75)
ADDITIONAL WORK REQUIRED:
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Wedge and mill temporary
asphalt street structures; Lump
10000 complete as specified Sum 0.00 1.00 1.00 $4,462.50 $4,462.50
Binder base patch repair Square
10001 areas;complete as specified Yards 0.00 301.00 301.00 $11.55 $3,476.55
Excavation asphalt&
pavement base repair; Lump
10002 complerte as specified Sum 0.00 1.00 1.00 $1,597.05 $1,597.05
Extra traffic control; complete Lump
10003 as specified Sum 0.00 1.00 1.00 $918.75 $918.75
Remove and replace 4'
diameter storm manhole Lump
20000 G1A; complete as specified Sum 0.00 1.00 1.00 $2,810.26 $2,810.26
Remove and replace 4'
diameter storm manhole F- Lump
20002 101; complete as specified Sum 0.00 1.00 1.00 $11,946.81 $11,946.81
Page 7 of 8
CONTRACT 18-13 CHANGE ORDER#1 FINAL(REVISED)
J
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE/N
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Remove and replace 4'
diameter storm manhole and
storm sewer multiple; Lump
20003 complete as specified Sum 0.00 1.00, 1.00 $6,475.59 $6,475.59
Remove and replace 4'
diameter manhole and storm
sewer multiple; complete as Lump
20004 specified Sum 0.00 1.00 1.00 $1,728.05 S1,728.05
Abandon 6"storm sewer; Lump
20005 complete as specified Sum 0.00 1.00 1.00 $1,000.00 $1,000.00
Install City supplied Type I Lump
20006 inlet;complete as specified Sum 0.00 1.00 1.00 $2,311.46 $2,311.46
15"furnish and install storm Linear
20007 sewer;complete as specified Feet 0.00 156.00 156.00 S10.00 $1,560.00
Remove existing inlet; install
City supplied Type III inlet; Lump
20008 complete as specified Sum 0.00 1.00 1.00 $2,786.97 $2,786.97
Vine Street outfall extra work; Lump
20009 complete as specified Sum 0.00 1.00 1.00 S55,840.52 $55,840.52
Existing 8"sanitary sewer
repair PTS supplied parts; Lump
30001 complete as specified Sum 0.00 1.00 1.00 $2,033.62 $2,033.62
Remove sanitary sewer vault: Lump
30002 complete as specified Sum 0.00 1.00 1.00 $3,202.05 $3,202.05
Rebuild existing sanitary
sewer manholes; complete Lump
30003 as specified Sum 0.00 1.00 1.00 $4,710.15 $4,710.15
Water main repair; City
supplied sleeve;complete as Lump
40000 specified Sum 0.00 1.00 1.00 S796.91 $796.91
Hydrant assemby,valve and
water service replacement; Lump
40001 complete as specified Sum 0.00 1.00 1.00 $2,178.46 $2,178.46
ADDITIONAL WORK REQUIRED: BID ITEMS 10000-40001 SUBTOTAL: $109,835.70 $0.00
NET INCREASE TO SECTION I: $109,835.70
NET INCREASE TO SECTION I: $109,835.70
NET DECREASE TO SECTION I: ($78,064.75)
NET INCREASE TO CONTRACT: $31,770.95
Page 8 of 8