HomeMy WebLinkAbout07. 21-109 PURPOSE: APPROVE CIP BUDGET AMENDMENTS AND CHANGE ORDER NO. 1 FOR PUBLIC WORKS NO. 21-04 WEST 9TH AVENUE RECONSTRUCTION / DORNER, INC. (+$423,591.00) INITIATED BY: PUBLIC WORKS DEPARTMENT WHEREAS, it is necessary to extend sanitary sewer and water main to a planned residential development near the intersection of Clairville Road and West 9th Avenue; and WHEREAS, the Common Council has adopted the 2021 Capital Improvements Budget (CIP), which is on file in the Office of the City Clerk and available for public inspection; and WHEREAS, it is necessary to amend the 2021 CIP Budget to transfer funds to fund sanitary sewer and water main to be installed in West 9th Avenue from Pauls Place to 750 west of Pauls Place to service the planned residential development; and WHEREAS, the extension of sanitary and water main and laterals may be most effectively and efficiently done by the contractor performing the West 9 th Avenue reconstruction from South Oakwood to Linden Oaks Drive and in connection with that work as a part of Contract No. 21-04; and WHEREAS, it is necessary to amend Contract No. 21-04 for this purpose. NOW, THEREFORE, BE IT THEREFORE RESOLVED, by the Common Council of the City of Oshkosh that the 2021 Capital Improvements Budget, on file in the City Clerk’s Office, is hereby amended as follows:  To transfer $274,833.28 from Account No. 03210410-6802-04805 (Contract Control- Sanitary Sewer-Second Local Street Concrete Paving) to Account No. 03210410-6802- 04104 (Contract Control-Sanitary Sewer-21-04 West 9th Avenue Reconst). MARCH 9, 2021 21-109 RESOLUTION (CARRIED__6-0___ LOST _______ LAID OVER _______ WITHDRAWN _______) MARCH 9, 2021 21-109 RESOLUTION CONT’D  To transfer $185,100 from Account No. 03210410-6803-04907 (Contract Control-Water Main-Water Main & Lateral Relay) to Account No. 03210410-6803-04104 (Contract Control-Water Main-21-04 West 9th Avenue Reconst). BE IT FURTHER RESOLVED by the Common Council of the City of Oshkosh that the following change Order, a copy of which is attached, is hereby approved: DORNER, INC. PO Box 129 Luxemburg, WI 54217 Net Increase to Contract: $423,591.00 PURPOSE: See attached Change Order. Money for this purpose is hereby appropriated from: Acct. Nos. 03210410-6802-04805 Contract Control-Sanitary Sewer-Second Local Street Concrete Paving 03210410-6803-04907 Contract Control-Water Main-Water Main & Lateral Relay 03210410-6802-04104 Contract Control-Sanitary Sewer-21-04 West 9th Avenue Reconst 03210410-6803-04104 Contract Control-Water Main-21-04 West 9th Avenue Reconst C:\Users\dianem\AppData\Local\Temp\43e9-b551-2518-fc74.docx Page 1 of 2 TO: Honorable Mayor and Members of the Common Council FROM: Justin Gierach, Engineering Division Manager / City Engineer DATE: March 4, 2021 RE: Approve Change Order No. 1 for Public Works Contract No. 21-04 West 9th Avenue Reconstruction / Dorner, Inc. (+$423,591) BACKGROUND Change Order No. 1 for Contract 21-04 is scheduled for consideration by the Common Council at the March 9, 2021 meeting. The Contract was originally awarded to Dorner, Inc. in January of 2021. A developer recently approached the City regarding a new residential development near the intersection of Clairville Road and West 9th Avenue. According to the Cooperative Plan between the City of Oshkosh and the Town of Algoma, this area (Zone C) is scheduled to attach to the City in March 2023. This developer hopes to develop this new residential development in 2021 and/or 2022 and would attach to the City prior to dates specified in the Cooperative Plan. With this potential development, it was determined the sanitary sewer and water main could be most effectively installed by the contractor performing the West 9th Avenue reconstruction work from South Oakwood Road to Linden Oaks Drive. ANALYSIS Following is a summary of the significant changes to each section of the CIP:  Sanitary Sewer – This change order is for additional sanitary sewer and associated asphalt paving work on West 9th Avenue, from Pauls Place to 750’ west of Pauls Place, to accommodate a future development. New sanitary sewer main and laterals will be installed, as needed, prior to replacing asphalt pavement.  Water Main – This change order is for additional water main and associated asphalt paving work on West 9th Avenue, from Pauls Place to 750’ west of Pauls Place, to accommodate a future development. New water main and laterals will be installed, as needed, prior to replacing asphalt pavement. C:\Users\dianem\AppData\Local\Temp\43e9-b551-2518-fc74.docx Page 2 of 2 FISCAL IMPACT Contract Section Change Order Amount Estimated Total Construction Costs CIP Budget Amount Street $0.00 $1,735,187.37 $3,184,700 Storm Sewer $0.00 $1,221,484.44 $2,007,000 Sanitary Sewer $260,967.80 $1,470,746.53 $1,547,333 Water Main $162,623.20 $809,394.30 $850,000 Sidewalk $0.00 $202,935.49 $205,000 Traffic $0.00 $309,739.75 $500,000 Total $423,591.00 $5,749,487.88 $8,294,033 Funding for the sanitary sewer and water main portions of this Change Order is available from CIP projects which have come in under budget:  $274,833.28 will be transferred from Account No. 03210410-6802-04805 (Contract Control- Sanitary Sewer-Second Local Street Concrete Paving) and transferred to Account No. 03210410-6802-04104 (Contract Control-Sanitary Sewer-21-04 West 9th Avenue Reconst).  $185,100 will be transferred from Account No. 03210410-6803-04907 (Contract Control-Water Main-Water Main & Lateral Relay) and transferred to Account No. 03210410-6803-04104 (Contract Control-Water Main-21-04 West 9th Avenue Reconst). RECOMMENDATIONS I recommend approval of Change Order No. 1 to Contact No. 21-04 in the amount of +$423,591 to Dorner, Inc. Approved: Mark A. Rohloff City Manager JLG/tlt