TO: Honorable Mayor and Members of the Common Council,
Mark Rohloff, City Manager
FROM: Russ Van Gompel, Director of Finance
DATE: July 1, 2020
RE: Manager Recommended Capital Improvement Plan
BACKGROUND
In 2015 the City Council adopted the attached Capital Improvement Program (CIP) Policy.
For 2021 — 2025 CIP staff is utilizing a new software program, Plan -It, and a new process. The
first Council Workshop on July 81h will focus on the Capital Improvement Plan. To assist with
the review on July 81h I have prepared and included four schedules. They include a
"Department Summary", a list of "Projects by Department", a "Funding Source Summary",
and a list of "Projects by Funding Source".
ANALYSIS
While the workshop will be held to review and answer questions on the entire five year plan, I
would like the Council to focus on improvements planned for 2021. The biggest decision point
to reach consensus on is the number of projects planned for 2021 and the ability to fund the
desired projects.
For 2021, over $64.5 million in capital projects are being recommended. The recommended
projects is an increase of over $3 million more than the amount approved in 2020 ($61,278,900).
In the 2020 CIP, 2021 projects listed totaled $49,131,100.
One of the major additions for 2021 is the inclusion of a new facility for the Parks Department.
This facility has been discussed in previous years and never included in the final CIP. The
facility was constructed in the 1960's and was a former technical college building. The City
undertook a facilities assessment and this building was identified as the top priority need. The
building was never designed for municipal operations so it is not efficient and lacks necessary
storage capacity. Construction could begin in 2021 and continue into 2022 as would the
phased borrowing for the project.
Finance Department
City Hall, 215 Church Avenue P.O. Box 1 130 Oshkosh, WI 54903-1 130 920.236.5005 http://www.ci.oshkosh.wi.us
The major streets and utility work panned for 2021 include; W 91' Ave reconstruction, Ceape
Avenue reconstruction, Omro Road reconstruction, and Oregon Street Interceptor. Staff will
provide an update on these projects at the Workshop.
Community Development projects include Riverwalk expansion, improvements to the South
Shore and Sawdust Districts, other blight removal and gateway improvements.
A majority of the Transit Improvements will be funded by additional CARES act funding.
And the City continues to face pressure of maintaining other general buildings and
equipment.
FISCAL IMPACT
In 2020 and by past Council consideration, the City was willing to take on about $12,500,000 in
new General Obligation debt. By the time you look at 2021 projects and considering the need
to finance some special assessments, I would like the Council to consider issuing $15,000,000 in
2021. I will provide additional information of the impact of issuing $15,000,000 the night of the
workshop. In addition, $1,100,000 worth of projects is proposed to be financed by tax levy, a
similar amount that was financed by levy in 2020.
RECOMMENDATION
The 2021 Budget Preparation Calendar identifies that after the Workshop, the CIP will be
reviewed by the Plan Commission on August 18, 2020. I would like the Council to consider
adoption of the 2021 CIP at the August 25 City Council meeting. It is my recommendation that
the 2021 projects would then be included with the Operating Budget, which is scheduled to be
adopted on November 10, 2020. Please let me know if you have any questions that might
require additional research prior to the Workshop.
Respectfully Submitted,
(//— 4z'—�
Russ Van Gompel
Director of Finance
Finance Department
City Hall, 215 Church Avenue P.O. Box 1 130 Oshkosh, WI 54903-1 130 920.236.5005 http://www.ci.oshkosh.wi.us
CITY OF OSHKOSH
Capital Improvement Program (CIP) Policy
Policy Statement
The establishment of a formal policy governing the purpose and acceptable parameters of a Capital Improvement
Program (CIP) is an effective contribution to the financial management practices of the City of Oshkosh. A
formally adopted policy will provide a decision making process based on evaluation, selection, and multi -year
scheduling of capital projects.
Purpose
The purpose of this policy is to manage and plan capital spending for multiple years and maintain adequate debt
service capacity for current and future needs. This will also ensure the city is able to deliver services for citizens,
and maintain and improve adequate infrastructure. In addition it is important to minimize tax spikes and avoid
large rate increases related to capital spending while maintaining a reliable infrastructure for our citizens and
employees.
Strategic Plan
The City of Oshkosh adopts a new Strategic Plan every two years that provides a "roadmap" for the City's future.
Depending on internal and external circumstances, the Strategic Plan contains several priority goals for the City to
undertake. Each goal is intended to support the larger vision for the City and to point the way of progress toward
that vision. The goals of the Strategic Plan are incorporated in the annual Capital Improvement Program
development process, providing City staff the framework in which to allocate resources to meet the goals.
Definitions
Capital Outlay — Individual items with minimum value of at least $5,000 and life greater than one year (Included
in operations budget).
Capital Project Individual items with minimum value of at least $10,000 and has expected life of at least ten
years. (Not included in operations budget).
Capital Improvement Program (CIP) A comprehensive schedule of approved capital improvement projects. The
program shall be for a five-year period. The program shall be annually revised and shall meet borrowing
guidelines provided by the Common Council for the first two years of the program. The remaining three years
will provide an estimate of the financial resources needed to complete the program.
Useful Life Policy
All City assets will be assigned a useful life as a means to plan for capital project expenditures, as well as meet
Governmental Accounting Standards Board's (GASB) Statement 34 which requires State and Local governments
to depreciate their exhaustible capital assets, including infrastructure. The term "useful life" will be determined
by either accepted standards & practices and/or best estimate based on industry or prior experience(s).
Recommended estimates for "useful life" are as follows:
Buildings and Building Improvements
Buildings Foundation/Frame/Structure 40 years
Building Improvements 20 years
Infrastructure
Roads & Highways (includes curb & gutter)
Sealcoats
3 years
Asphalt (Cold -Mixed)
5 years
Asphalt (Hot -Mixed)
12 years
Concrete Pavement
25 years
Sewer Mains, Lift Stations
50 years
Sanitary Mains
50 years
Storm Mains
40 years
Sidewalks
20 years
Street Lights
30 years
Water Mains
75 years
Water System
40 years
Wells & Pump Houses
30 years
Land/Land Improvements
Land
No Depreciation
Athletic Fields, Bleachers
15 years
Benches, Tables, Grills
5 years
Fencing, Gates
20 years
Landscaping, Ball Park
25 years
Outdoor Equipment
20 years
Outdoor Lighting
20 years
Parking Lots
25 years
Paths and Trails
25 years
Retaining Walls
20 years
Tennis & Basketball Courts
20 years
Machinery and Equipment
Business/Office Equipment
8 years
Custodial Equipment
5 years
Fire Department Equipment
7 years
Furniture
15 years
Grounds Equipment — Mowers
7 years
Kitchen Equipment Appliances
10 years
Mounted Equip w/Truck Chassis
8 years
Outdoor Equipment — Playgrounds
20 years
Plazas and Pavilions
40 years
Radio Communications
7 years
Water Meters
20 years
Vehicles
Squad Cars
4 years
Transit Buses
10 years
Cars, Light Trucks & Vans
10 years
Heavy trucks (more than 13,OOOlbs)
10 years
Fire Trucks
15 years
Heavy Equipment -Loaders, Graders
10 years
CIP Development Process
The Capital Improvement Program will be developed on an annual basis and follow the process below as much as
possible.
Major Milestones
Time Frame
Process Step
Deliverable/Output
Participants
Review of CIP Policy
January
Long Range Finance
Possible recommendation to Council
Analysis of available and
February to March
Director of Finance
Established parameters for borrowing
acceptable funding levels for
Long Range Finance
levels and expected expenditure limit for
projects in the CIP.
CIP.
Major Milestones
Time Frame
Process Step
Deliverable/Output
Participants
Submission of project requests
Month of April
Department Heads
All requests sent to CIP document
covering five-year period by
Staff Members
developer.
department director on CIP
request form and scoring sheet
Preliminary CIP document
Month of June
Dept. of Public Works
Draft CIP document.
created
Finance Department
Department directors review of
Mid June
City Manager
Preliminary CIP document.
project requests with City
Director of Finance
Manager and Finance Director.
Department Heads and
Staff
City Manager evaluation of
July
City Manager
Recommended CIP document.
projects based on review criteria
Director of Finance
and borrowing limits.
Presentation of the proposed
August
City Manager
Completed review ensuring alignment
five-year CIP to the Plan
Planning Department
with Comprehensive Plan.
Commission for consideration.
Presentation of the proposed
Month of October
City Manager
Receive comments and direction from
five-year CIP to Common
Director of Finance
Common Council regarding projects for
Council for consideration.
Department Heads and
final recommendation.
Staff
Recommendation to the
November
City Manager
Adopted five-year CTP
Common Council for final
adoption.
CIP Ranking Process
Thirteen evaluation criteria have been developed to assist with prioritizing initial project requests. Each project
included in the CIP will be evaluated against this criterion. This ensures the most objective process possible and
leads to consistent decision making. The scoring which is derived from the tools below will assist the City
Manager in prioritizing and preparing the final CIP plan. Every project is evaluated against each criterion and
assigned points on a scale of 15, 10, 5, or 0. The project review criterion consists of the following categories:
Conformity to Approved City Strategic Plan
or Department Plan(s)
Financial Commitments and Leverage of
Outside Funding
• Mandates
• Public Health and Safety
• Implementation Feasibility
• Operating Budget Impact
• Percentage of Population Served
• Project/Item Life
• Estimated Frequency of Use (Average Per
Year)
• Service Level
• Linkages to Other CIP Projects or Other
Organization Projects
• Infrastructure Investment/ Protection
• Encouragement of Economic Development
The City Manager also reserves the right to assess an extra 5 points per project.
City of Oshkosh, Wisconsin
Manager Recommended Capital Improvement Plan
2021 tbm 2025
DEPARTMENT SUMMARY
Department 2021 2022 2023 2024 2025 Total
201 -Senior Center
10,000
30,000
40,000
202 - Community Development
3,635,300
8,110,000
9,475,000
3,775,000
1,700,000
26,695,300
211-Recycling
205,000
300,000
300,000
250,000
1,055,000
212-Sanitation
600,000
335,000
200,000
200,000
200,000
1,535,000
215 - Police
350,000
350,000
235-Fire
216,900
1,085,670
4,570,920
72,584
18,458
5,964,532
239 - Library
40,600
186,600
105,100
117,300
449,600
241 - Museum
100,000
585,000
2,575,000
300,000
3,560,000
311 -Sidewalks
988,000
988,000
988,000
988,000
988,000
4,940,000
315-Streets
698,000
2,694,400
1,228,000
1,625,000
1,075,000
7,320,400
321 -Utility Infrastructure
16,652,200
22,303,100
17,414,200
16,181,800
14,495,600
87,046,900
323 - Gen Building & Equipment
1,241,000
2,728,500
1,813,500
1,531,000
1,764,000
9,078,000
325 - Parks Improvement
4,050,000
3,890,000
3,555,000
4,800,000
3,715,000
20,010,000
326 - Parks Equipment
88,000
320,000
300,000
170,000
165,000
1,043,000
400-Traffic
680,000
875,000
590,000
790,000
590,000
3,525,000
501- Grand Opera House
110,000
75,000
40,000
50,000
160,000
435,000
503 - Convention Center
200,000
40,000
240,000
511 -Transit
5,345,000
110,000
10,000
10,000
2,110,000
7,585,000
541-Water
15,468,600
12,780,000
12,200,000
1,960,000
6,334,000
48,742,600
551-Sewer
10,462,700
8,368,100
5,777,000
5,932,000
2,031,000
32,570,800
561-Storm Water
3,585,000
6,389,000
7,508,000
5,229,000
6,134,000
28,845,000
TOTAL 64,511,300 72,038,370 68,719,720 43,731,684 42,030,058 291,031,132
Produced Using the Plan -It Capital Planning Sofhvare Page I Wednesday, Judy 1, 2020
City of Oshkosh, Wisconsin
Manager Recommended Capital Improvement Plan
2021 thru 2025
PROJECTS BY DEPARTMENT
Department
Project # Priority
2021
2022
2023
2024 2025
Total
201 - Senior Center
GS: Seniors Center (North) Front Desk Replacement
210SC FDESK
3
10,000
10,000
GS: Seniors Center Flooring Replacement
23 OSC FLOOR
4
30,000
30,000
201 - Senior Center Total
10,000
30,000
40,000
202 - Community Development
CD: 9th Avenue Extension East to Main Street
00 9TH AVE
3
3,000,000
3,500,000
6,500,000
CD: Bicycle and Pedestrian Infrastructure
00 BKE N PED
3
50,000
50,000
50,000
50,000 50,000
250,000
CD: Blight Removal Scattered Sites
00 BLGT REM1
2
250,000
250,000
500,000
500,000 500,000
2,000,000
CD: Gateway Blight Elimination
00 BLGT REM2
2
250,000
250,000
250,000
250,000 250,000
1,250,000
CD: Great Neighborhoods Initiative
00 G NHOODS
2
175,000
175,000
200,000
250,000 250,000
1,050,000
CD: Gateway Improvements
00 GATE IMPR
2
50,000
50,000
100,000
100,000 200,000
500,000
CD: Grove Street Infrastructure
00 GRV INFRA
3
200,000
200,000
400,000
CD: Riverway Drive Trail to Riverwalk
00 RVR WY TR
5
175,000
175,000
350,000
CD: Riverwalk on Pioneer Island and Marina
00 RW PIONER
3
2,000,000
4,000,000
2,000,000
8,000,000
CD: Riverwalk Signage and Banners
00 RW SIGNS
3
25,000
25,000
50,000
50,000 50,000
200,000
CD: South Main Acquisition
00 S MAIN AQ
1
250,000
500,000
250,000
1,000,000
CD: South Shore & Sawdust Dist Redevelopment Sites
00 SS SD RED
2
400,000
400,000
400,000
400,000 400,000
2,000,000
CD: Industrial Park Signs
21 IND SIGNS
3
40,000
40,000
CD: Jackson St Corridor SftyStdy ImplementationPH1
21 JSC PHI
2
60,000
60,000
CD: Multimodal Trail Rainbow Park
21 MM TRL RB
2
585,300
585,300
CD: Riverwalk Construction S. Main St to RR Tracks
21 RW CONSTI
1
1,100,000
1,100,000
CD: Riverwalk East of RR Tracks along Pioneer Dr
21 RW CONST2
2
1,000,000
1,000,000
CD: Former Sanitation Garage Demo
21 SANI DEMO
3
200,000
200,000
CD: Jackson St Corridor SftyStdy ImplementationPH2
22 JSC PH2
3
210,000
210,000
202 - Community Development Total
3,635,300
8,110,000
9,475,000
3,775,000 1,700,000
26,695,300
211 - Recycling
REC: #221, Hook -Lift Roll -Off Container Truck
22 RECYVEH1
n/a
150,000
150,000
REC: #202, 1-Ton 4WD Pickup Truck
22 RECY VEH2
n/a
55,000
55,000
REC: #210, Automated Side -Load Refuse Truck
23 RECY VEH1
n/a
300,000
300,000
REC: #209, Automated Side -Load Refuse Truck
24 RECY VEH1
n/a
300,000
300,000
REC: #111, Articulated Loader
25 RECY VEHI
n/a
250,000
250,000
211 - Recycling Total
205,000
300,000
300,000 250,000
1,055,000
212 - Sanitation
SAN: #218, Automated Side -Load Refuse Truck
21 SANI VEH1
n/a
300,000
300,000
SAN: #217, Automated Side -Load Refuse Truck
21 SANI VEH2
n/a
300,000
300,000
SAN: #219, Automated-Sideload Refuse Truck
22 SANI VEH1
n/a
300,000
300,000
SAN: #201, 4WD Supervisor's Pickup Truck
22 SANI VEH2
n/a
35,000
35,000
SAN: #206, Rear -Load Refuse Truck
23 SANI VEH1
nla
200,000
200,000
SAN: #207, Rear -Load Refuse Truck
24 SANI VEH1
n/a
200,000
200,000
SAN: #212, Rear -Load Refuse Truck
25 SANI VEH1
n/a
200,000
200,000
Produced Using the Plan -It Capital Planning Sofnvare Page 1 Wednesday, July 1, 2020
Department Project # Priority 2021 2022 2023 2024 2025 Total
212 - Sanitation Total
215 - Police
Police: Renovations to Vacant Ofc Space North End
21 PD RENO 2
Police: SWAT Team Truck Replacement
21 PD SWT TR 1
215 - Police Total
235 - Fire Li
Fire: Turn Out Gear Pants & Coats
00 FIRE GEAR 1
Fire: Turn Out Gear Helmets
00 FIRE HELM 1
Fire: Parking Lot Program Station 18
00 PRKG LT18 1
Fire: Turn Out Gear Boots
21 FIRE BTS 1
Fire: Replace'94 Ford Expl with 1 Ton pickup
21 FIRE VEH1 3
Fire: Replacement of'99 Chevrolet Suburban
21 FIRE VEH2 3
Fire: Replacement of Generator at Fire Station 16
21 GEN ST16 2
Fire: Turn Out Gear Hi -Visibility Jackets
21 HI VISIB 1
Fire: New Hose to Replace Obsolete Hose
21 HOSE REPL 1
Fire: Fire Training Center
21 TRNG CTR 1
Fire: Replacing 3 Ambulances from'12
22 FIRE VEH2 1
Fire: Replacement for'06 Fire Engine
23 FIRE ENG1 1
Fire: Replacing '98 Chevy 3500
23 FIRE VEH1 2
235 - Fire Total
1239 - Library I
Library: Replace Emergency Electric Generator Sys
21 LIB GENER
2
Library: Fire Alarm System
22 LIB ALARM
2
Library: Elevator#1 Modernization Upgrades
22 LIB ELEV1
3
Library: Elevator#2 Modernization Upgrades
23 LIB ELEV2
3
Library: Elevator #3 Modernization Upgrades
24 LIB ELEV3
3
239 - Library Total
241 - Museum
Museum: Deep Roots, Growing City Exhibition
00 DP ROOTS
2
Museum: Replace Security Camera Systems
22 CAMERAS
3
Museum: Elevator Modernization
22 ELEVATOR
3
Museum: Masonry Overhaul
22 MASONRY
3
Museum: Exterior Painting
22 PAINTING
4
Museum: Building Modifications
23 BLDG MODS
3
Museum: Creation of Access Doors
23 DBL DOORS
2
Museum: Memories Dreams Gallery Refurbishment
23 MEMORIES
2
Museum: Parking Lot Improvements
23 MUSM LOTS
3
Museum: Implement Landscape Plan
25 LANDSCAPE
3
241 - Museum Total
311 - Sidewalks
Sidewalks: New Walk Ordered In
00 NEW WALKS
n/a
Sidewalks: Rehabilitation & Reconstruction Program
00 REHAB
n/a
Sidewalks: Subdivision Agreements
00 SUBDIVNS
n/a
311 - Sidewalks Total
1315 - Streets I
600,000 335,000 200,000 200,000 200,000 1,535,000
150,000 150,000
200,000 200,000
350,000 350,000
40,000
32,100
12,800
24,325
109,225
5,000
0
1,740
4,659
18,458 29,857
0
83,600
43,600
127,200
49,500
49,500
44,300
44,300
45,700
45,700
60,000
60,000
32,400
32,400
66,570
66,570
3,798,780
3,798,780
927,000
927,000
627,000
627,000
47,000
47,000
216,900
1,085,670
4,570,920
72,584
18,458 5,964,532
40,600
40,600
71,100
71,100
115,500
115,500
105,100
105,100
117,300
117,300
40,600
186,600
105,100
117,300
449,600
100,000
100,000
800,000
1,000,000
85,000
85,000
125,000
125,000
200,000
200,000
75,000
75,000
800,000
800,000
75,000
75,000
300,000
300,000
600,000
600,000
300,000
300,000
100,000
585,000
2,575,000
300,000
3,560,000
70,000
70,000
70,000
70,000
70,000
350,000
888,000
888,000
888,000
888,000
888,000
4,440,000
30,000
30,000
30,000
30,000
30,000
150,000
988,000
988,000
988,000
988,000
988,000
4,940,000
Produced Using the Plan -It Capital Planning Sofhvare Page 2 Wednesday, July 1, 2020
Department Project # Priority 2021 2022 2023 2024 2025 Total
ENG: Asphalt Program (Annual)
00 ASPHALT
n/a
475,000 475,000 475,000
1,425,000
ENG: Bradley Street Asphalt Paving
00 BRADLEY
n/a
100,000
1,794,400
1,894,400
ENG: Concrete Pavement Repairs (Annual)
00 CONCRETE
n/a
233,000
235,000
285,000 235,000 235,000
1,223,000
ENG: Up -Front Engineering Services
00 ENG SRVCS
n/a
365,000
365,000
365,000 365,000 365,000
1,825,000
ENG: West 9th Ave Gateway Corridor Improvements
00 W 9TH IMP
n/a
300,000
550,000
850,000
ENG: Mockingbird Way Traffic Calming
23 MOCKBIRD
n/a
103,000
103,000
315 - Streets Total
698,000
2,694,400
1,228,000 1,625,000 1,075,000
7,320,400
321 - Utility Infrastructure
Oregon Street Interceptor Sewer
00 OREGON ST
n/a
3,100,600
4,030,700
3,372,900
10,504,200
Ceape Avenue Reconstruction
21 CEAPE AVE
n/a
6,040,500
6,040,500
Omro Road Reconstruction
21 OMRO RD
n/a
300,000
300,000
West 9th Avenue Reconstruction
21 WEST 9TH
n/a
7,211,100
7,211,100
Algoma Boulevard Reconstruction
22 ALGOMA
n/a
9,766,700
9,766,700
East Lincoln Avenue Reconstruction
22 E LINCOLN
n/a
3,249,800
3,249,800
Grand Street Reconstruction
22 GRAND ST
n/a
2,223,300
2,223,300
Rosalia St. Water Main Replacement/Asphalt Paving
22 ROSALIA
n/a
3,032,600
3,032,600
McKinley Street Reconstruction
23 MCKINLEY
n/a
1,087,400
1,087,400
South Main Street Reconstruction
23 S MAIN
n/a
9,275,300
9,275,300
West Lincoln Avenue Reconstruction
23 W LINCOLN
n/a
3,678,600
3,678,600
Central Street Reconstruction
24 CENTRAL
n/a
3,709,200
3,709,200
Cherry Street Reconstruction
24 CHERRY
n/a
5,456,300
5,456,300
Mill Street Reconstruction
24 MILL ST
n/a
1,265,200
1,265,200
Waugoo Avenue Reconstruction
24WAUG00
n/a
5,751,100
5,751,100
ArthurAvenue Reconstruction
25ARTHUR
n/a
2,303,400
2,303,400
Bay Shore Drive Reconstruction
25 BAYSHORE
n/a
2,168,000
2,168,000
Bowen Street Reconstruction
25 BOWEN ST
n/a
2,860,700
2,860, 700
Ripon Lane Utility Installation & Asphalt Patching
25 RIPON LN
n/a
903,100
903,100
West 15th Avenue Reconstruction
25 WEST 15TH
n/a
6,260,400
6,260,400
321 - Utility Infrastructure Total
16,652,200
22,303,100
17,414,200 16,181,800 14,495,600
87,046,900
323 - Gen Building & Equipment
GS: Office Furniture Replacement
00 FURN REPL
2
10,000
10,000
10,000 10,000 10,000
50,000
GS: HVAC/Roofing Replacement Program
00 HVAC/ROOF
1
500,000
500,000
500,000 500,000 500,000
2,500,000
GS: Complete ADA Audit of all City buildings
21 ADA AUDIT
2
60,000
60,000
GS: City Hall Security Improvements
21 CTYHALSEC
1
75,000
75,000
ENG: #389, 4-Wheel Drive 1/2-Ton Pickup Truck
21 ENG VEH1
n/a
37,000
37,000
STR: #67, Tandem -Axle Plow Truck
21 STR VEH1
n/a
225,000
225,000
STR: #24, Flat Bed Truck
21 STR VEH10
n/a
100,000
100,000
STR: #104, Concrete Breaker
21 STR VEH11
n/a
100,000
100,000
STR: #33, 3/4-Ton 4WD Pickup Truck
21 STR VEH2
n/a
40,000
40,000
STR: #50 Single -Axle Plow Truck
21 STR VEH3
n/a
204,000
204,000
STR: #140, Motor Grader
21 STR VEH4
n/a
210,000
210,000
STR: #122, Skid Steer and Router
21 STR VEH5
n/a
80,000
80,000
STR: #262, Walk -Behind Router
21 STR VEH6
n/a
25,000
25,000
STR: #22, 1-Ton 4WD Pickup Truck
21 STR VEH7
n/a
44,000
44,000
STR: #68, Tandem -Axle Plow Truck
21 STR VEH8
n/a
225,000
225,000
STR: #238, Single -Axle Trailer
21 STR VEH9
n/a
10,000
10,000
GS: Safety Building Elevator 1-2 Modernizations
22 SB ELEVS
1
250,000
250,000
STR: #256, Rock Drill
22 STR EQP1
n/a
10,000
10,000
STR: #69, Tandem -Axle Plow Truck
22 STR VEH1
n/a
235,000
235,000
STR: #244, Leaf Blower
22 STR VEH2
n/a
65,000
65,000
STR: #34, 1-Ton 4WD Crew Cab Pickup Truck
22 STR VEH3
n/a
45,000
45,000
STR: #53, Single -Axle Plow Truck
22 STR VEH4
n/a
204,000
204,000
STR: #106, Rubber -Tire Backhoe
22 STR VEH5
n/a
160,000
160,000
Produced Using the Plan -It Capital Planning Sofmare Page 3 Wednesday, July 1, 2020
Department Project # Priority 2021 2022 2023 2024 2025 Total
STR: #110, Sidewalk Tractor
22 STR VEH6
n/a
135,500
135,500
STR: #70, Tandem -Axle Plow Truck
22 STR VEH7
n/a
225,000
225,000
STR: #93, Semi -Tractor
22 STR VEH8
n/a
100,000
100,000
STR: #239 and #246, Stainless Tanker Semi -Trailer
22 STR VEH9
n/a
85,000
85,000
GS: City Hall 2nd Floor Hallway Tile Replacement
23 CTYHAL2ND
4
20,000
20,000
GS: 3/4 Ton Van (repl #003'97 GMC)
23 FAC VEH1
1
35,000
35,000
STR: #200, Road Saw
23 STR EQP1
n/a
30,000
30,000
STR: #71, Tandem -Axle Plow Truck
23 STR VEH1
n/a
225,000
225,000
STR: #40, Single -Axle Area Plow Truck
23 STR VEH2
n/a
204,000
204,000
STR: #26, 1-Ton 4WD Dump Truck
23 STR VEH3
n/a
90,000
90,000
STR: #260, Crack Filler
23 STR VEH4
n/a
50,000
50,000
STR: #264, Tar Kettle Trailer Unit
23 STR VEH5
n/a
40,000
40,000
STR: #32, 3/4-Ton 4WD Pickup Truck
23 STR VEH6
n/a
42,500
42,500
STR: #163, Asphalt Roller
23 STR VEH7
nla
52,000
52,000
STR: #116, Articulated Loader
23 STR VEH8
n/a
295,000
295,000
STR: #54 and #20, Hook Lift Trucks
23 STR VEH9
n/a
220,000
220,000
ENG: #386, 4-Wheel Drive 1/2-Ton Pickup Truck
24 ENG VEH1
n/a
37,000
37,000
STR: #108, Floor Scrubber
24 STR EQP1
n/a
65,000
65,000
STR: #218, Trailered Air Compressor
24 STR EQP2
n/a
30,000
30,000
STR: #72, Tandem -Axle Dump Truck
24 STR VEH1
n/a
225,000
225,000
STR: #41, Single -Axle Area Plow Truck
24 STR VEH2
n/a
204,000
204,000
STR: #92, Semi -Tractor
24 STR VEH3
n/a
105,000
105,000
STR: #230, 5-Ton Tandem -Axle Trailer
24 STR VEH4
n/a
10,000
10,000
STR: #36, 4WD Single -Axle Truck
24 STR VEH5
n/a
120,000
120,000
STR: #174, Utility Tractor
24 STR VEH6
n/a
215,000
215,000
STR: #105, Zero -Turn Mower
24 STR VEH7
n/a
10,000
10,000
GS: 3/4 Ton Pickup (repl #002 '08 Ford)
25 FAC VEH1
3
45,000
45,000
STR: #73, Tandem -Axle Plow Truck
25 STR VEH1
n/a
235,000
235,000
STR: #241, Leaf Blower
25 STR VEH2
n/a
65,000
65,000
STR: #44, Single -Axle Area Plow Truck
25 STR VEH3
n/a
204,000
204,000
STR: #172, 114" Snow Blower
25 STR VEH4
n/a
180,000
180,000
STR: #117, Articulated Loader
25 STR VEH5
n/a
295,000
295,000
STR: #168, Paver
25 STR VEH6
n/a
175,000
175,000
STR: #240, Tandem -Axle Equipment Trailer
25 STR VEH7
n/a
20,000
20,000
STR: #37, Supervisor's Pickup Truck
25 STR VEH8
n/a
35,000
35,000
323 - Gen Building & Equipment Total
1,241,000 2,728,500
1,813,500
1,531,000 1,764,000
9,078,000
325 - Parks Improvement
Parks: Lakeshore Park Phase 1 b Development
00 LAKESHORE
3
500,000
500,000
1,000,000
Parks: Menominee Prk Prkg Lot & Reetz Fids -Design
00 MP LOT DS
3
350,000
3,000,000
3,350,000
Parks: Menominee Park Road Reconstruction
00 MP RD CON
2
500,000
500,000
1,000,000
Parks: New Building Construction
00 PRKS BLDG
2
3,400,000 3,000,000
6,400,000
Parks: Riverside Cemetery Roads Repaving
00 R CEM RDS
3
25,000
25,000
25,000
75,000
Parks: Rainbow Memorial Park Improvements
00 RB PRK IP
4
400,000 2,750,000
3,150,000
Parks: Menominee Park Zoo Improvements
21 M PRK ZOO
3
100,000
100,000
Parks: Menominee Park Trail Improvements/drainage
21 MP TRL IM
3
75,000
75,000
Parks: Roe Park Play Equipment Replacement
21 ROE EQUIP
2
200,000
200,000
Parks: Riverwalk Light Bollards Replacement
21 RW BOLRDS
2
25,000
25,000
Parks: South Park Tennis Court Reconstruction
21 SP TEN CT
2
325,000
325,000
Parks: Westhaven Circle Prk Play Equip & Surfacing
21 WCRL EQUP
2
200,000
200,000
Parks: Westhaven Circle Park Lighting Replacement
21 WCRL LGTS
3
30,000
30,000
Parks: 44th Parallel Park Play Equip & Surfacing
22 44P EQUIP
2
200,000
200,000
Parks: 44th Parallel Park Lighting Replacement
22 44P LGHTS
3
30,000
30,000
Parks: Abbey Park Play Equipment & Surfacing
22 ABY EQUIP
2
200,000
200,000
Parks: Fugleberg Park Lighting Replacement
22 FGL LGHTS
3
30,000
30,000
Parks: Rainbow Mem Prk Play Equipment & Surfacing
22 RB EQUIP
2
200,000
200,000
Produced Using the Plan -It Capital Planning Sofhnare Page 4 Wednesday, July 1, 2020
Department Project # Priority 2021 2022 2023 2024 2025 Total
Parks: Stevens Park Lighting Replacement
22 SP LGHTS
3
30,000
30,000
Parks: Quarry Park Restroom/Shelter Building Reno
23 QRYBLDG
3
150,000
150,000
Parks: Rusch Park Development
23 RUSCH DEV
n/a
200,000
200,000
Parks: Stevens Park Play Equipment and Surfacing
23 SP EQUIP
3
200,000
200,000
Parks: Site A Development - Ripple & Oregon
23 STE A DEV
3
300,000
300,000
Parks: Site B Development - 9th and Clairville
23 STE B DEV
3
300,000
300,000
Parks: Stoegbauer Park Restrooms/Shelter Constr
23 STGBR BLD
3
200,000
200,000
Parks: Teichmiller Park Tennis Court Reconstruct
23 TEIC TNIS
n/a
200,000
200,000
Parks: 44th Parallel Park Tennis Court Reconst
24 44P TENIS
3
200,000
200,000
Parks: Abe Rochlin Park Play Equipment & Surfacing
24 ABE EQUIP
3
200,000
200,000
Parks: Stevens Park Tennis Court Reconstruction
24 SP TENNIS
3
100,000
100,000
Parks: West Algoma Park Play Equipment & Surfacing
24 W ALG EQP
3
200,000
200,000
Parks: Westhaven Circle Prk Tennis Crt Reconstuct
24 WHCRL TNS
3
200,000
200,000
Parks: Red Arrow Park Play Equipment
25 ARW EQUIP
3
200,000
200,000
Parks: Red Arrow Park Lighting Replacement
25 ARW LGHTS
3
40,000
40,000
Parks: Menominee Park Lighting Replacement
25 MP LIGHTS
3
50,000
50,000
Parks: Menominee Park Tennis Court Lights
25 MP TC LTS
4
150,000
150,000
Parks: Quarry Park Dog Park Development
25 QURY DOG
4
100,000
100,000
Parks: Westhaven Circle Park - Splash Pad
25 WHCRL PAD
4
400,000
400,000
325 - Parks Improvement Total
4,050,000 3,890,000
3,555,000
4,800,000 3,715,000
20,010,000
326 - Parks Equipment
Parks: Replace'01 Ford Workhorse Step Van #401
21 PRKS VEH1
1
60,000
60,000
Parks: Replace'06 Vermeer BC 1000 XL Chipper #471
21 PRKS VEH2
2
60,000
60,000
Parks: Replace'07 Ford F-250 #418
21 PRKS VEH3
3
40,000
40,000
Parks: Replace'89 Topsoil Screener
21 PRKS VEH4
3
28,000
28,000
Parks: Replace'07 Dodge Ram 35001 Tn #492
22 PRKS VEH1
3
50,000
50,000
Parks: Replace'l2 Toro 7200 Gmdmstr Zero Tm #455
22 PRKS VEH2
2
60,000
60,000
Parks: Replace'09 Ford F450 #481
22 PRKS VEH3
2
110,000
110,000
Parks: Replace'11 John Deere Gator#499
23 PRKS VEH1
3
30,000
30,000
Parks: Replace'13 Toro 7200 Gmdmstr Zero Tm #454
23 PRKS VEH2
2
65,000
65,000
Parks: Replace'08 Ford F-250 #493
23 PRKS VEH3
3
45,000
45,000
Parks: Replace'09 Chevrolet 3500 HD #486
23 PRKS VEH4
3
50,000
50,000
Parks: Replace'08 Ford Econoline Van #409
23 PRKS VEH5
3
30,000
30,000
Parks: Replace'07 Ford Ranger Ext Cab #417
23 PRKS VEH6
3
40,000
40,000
Parks: Replace'08 Ford F-350 1 Ton Truck#416
23 PRKS VEH7
4
40,000
40,000
Parks: Replace'14 Toro 7200 Gmdmstr Zero Tm #456
24 PRKS VEH1
2
65,000
65,000
Parks: Replace'12 CNG Dump Truck #412
24 PRKS VEH2
n/a
75,000
75,000
Parks: Replace'09 Leaf PickerNacuum #031
24 PRKS VEH3
nla
30,000
30,000
Parks: Replace Enclosed Trailer #428
25 PRKS TRLR
2
12,000
12,000
Parks: Replace'15 Toro 7200 Gmdmstr Zero Tm #457
25 PRKS VEH1
2
70,000
70,000
Parks: Replace'12 Smithco Athletic Field Grmr P12
25 PRKS VEH2
2
23,000
23,000
Parks: Replace'14 Skag Zero Turn Mower#1
25 TRN MOWR1
2
15,000
15,000
Parks: Replace'14 Skag Zero Turn Mower #2
25 TRN MOWR2
2
15,000
15,000
Parks: Replace'14 Skag Zero Turn Mower#3
25 TRN MOWR3
2
15,000
15,000
Parks: Replace'14 Skag Zero Turn Mower#4
25 TRN MOWR4
2
15,000
15,000
326 - Parks Equipment Total
88,000 320,000
300,000
170,000 165,000
1,043,000
400 - Traffic
TR: Parking Lot Improvements
00 LOT IMRPV
2
500,000 500,000
500,000
500,000 500,000
2,500,000
TR: LED Traffic Signal Head Equipment
00 SGNL HEAD
3
10,000 10,000
10,000
10,000 10,000
50,000
TR: LED Streetlighting Upgrades
00 STR LGHTS
3
10,000 10,000
10,000
10,000 10,000
50,000
TR: Purchase Streetlighting Poles
00 STR POLES
3
25,000 25,000
25,000
25,000 25,000
125,000
TR: Traffic Signal Equipment
00 TRF SGNL
3
45,000 45,000
45,000
45,000 45,000
225,000
TR: Electric Div Service Truck (rep[ 2008)
21 VEH ELECT
3
60,000
60,000
Produced Using the Plan -It Capital Planning Sofhilare Page 5 Wednesday, July 1, 2020
Department Project # Priority 2021 2022 2023 2024 2025 Total
TR: Sign Service Truck 1 to 1 1/2 Tn (repl 2004)
21 VEH SIGN1
2
90,000
90,000
TR: Traffic Signal Westhaven Dr & 9th Avenue
22 TRSIGNAL1
3
175,000
175,000
TR: Electrical Supervisor Truck (repl 2008)
22 VEH ELEC1
3
50,000
50,000
TR: Electric Division Truck (repl 2003)
24 VEH ELEC1
3
200,000
200,000
400 - Traffic Total
680,000
875,000
590,000 790,000 590,000
3,525,000
501 - Grand Opera House
GS: Grand Opera House Seat Replacement Program
00 GOH SEATS
2
50,000 50,000
100,000
GS: Grand Opera House Signage Updates
21 GOH SIGNS
3
75,000
75,000
GS: Grand Opera House Stage Floor Replacement
21 GOH STAGE
2
35,000
35,000
GS: Grand Opera House Dimmer Rack Replacement
22 GOH DIMMR
2
75,000
75,000
GS: Grand Opera House Wheelchair Lift Replacement
23 GOH CH LF
1
40,000
40,000
GS: Grand Opera House Plumbing Improvements
25 GOH PLUMB
1
65,000
65,000
GS: Grand Opera House Fire Pump Controller Rapt
25 GOH PUMP
1
25,000
25,000
GS: Grand Opera House Wallpaper Replacement Frog
25 GOH WALL
3
20,000
20,000
501 - Grand Opera House Total
110,000
75,000
40,000 50,000 160,000
435,000
503 - Convention Center
GS: OCC Air Handler Unit (Mezzanine) Replacement
21 OCC AHU
1
200,000
200,000
GS: OCC Moveable Walls Wallpaper Replacement
23 OCC WALLS
3
40,000
40,000
503 - Convention Center Total
200,000
40,000
240,000
511 - Transit
TR: Transit Stop Improvements
00 TR STP IM
3
10,000
10,000
10,000 10,000 10,000
50,000
TR: Automated Wheelchair Securement Sys 12 buses
21 AUT WHLCH
2
180,000
180,000
TR: 2 hybrid & 2 clean diesel buses (repl 2010's)
21 TR BUSES
1
2,600,000
2,600,000
TR: Forklift (repl 1993 Komatsu FD 25VT-11 Diesel)
21 TR FRKLFT
3
35,000
35,000
TR: Electronic Fare Readers/Farebox for Buses
21 TRAN FARE
1
200,000
200,000
TR: Downtown Transit Center
21 TRANS CTR
1
2,320,000
2,320,000
TR: Riding Lawnmower (repl 2005 Toro Z Master)
22 LAWNMOWER
3
20,000
20,000
TR: Supervisor Pickup Truck (repl 2012)
22 TRAN VEH1
3
40,000
40,000
TR: Driver Shuffle Vehicle (repl 2011 Honda Civic)
22 TRAN VEH2
3
40,000
40,000
TR: 2 Elec Buses (rep] 2013's) & 1 Charging Infras
25 2ELEC BUS
1
2,000,000
2,000,000
TR: Replace Go Transit Hoist in maintenance garage
25 TR HOIST
2
100,000
100,000
511 - Transit Total
5,345,000
110,000
10,000 10,000 2,110,000
7,585,000
541 - Water
ENG: Misc. Utility -Owned Lead Service Repl.
00 ENG LEAD
n/a
100,000
100,000
100,000 100,000 100,000
500,000
WD: Heated Storage Building
00 WD ST BDG
n/a
90,000
350,000
440,000
WFP: Clearwell Replacement
00WFCLRWLL
n/a
10,000,000
8,000,000
4,000,000
22,000,000
WFP: Re -Paint Femau Water Tower and Add Mixing
00 WF FER TW
n/a
75,000
1,125,000
1,200,000
WFP: Repl Granulated Activated Carbon Filter Media
00 WF GAC FT
n/a
300,000 3,145,000
3,445,000
WFP: Replace Ozone Generators
00 WF GENER
n/a
400,000
4,100,000
4,500,000
WFP: 36" Intake Miller's Bay Bypass
00 WF M BAY
n/a
300,000
2,000,000
2,300,000
WFP: Dual Media Filter Repairs/Replacements
00 WF MEDIA
n/a
65,000
1,200,000 1,200,000
2,465,000
WFP: Replace Ozone Liquid Oxygen System
00 WF OZONE
n/a
130,000
1,420,000
1,550,000
WFP: Chloramine System/Rep[ Booster Station Pumps
00 WF PUMP
n/a
135,000 2,000,000
2,135,000
ENG: Knapp Street Area Water Main Replacements
21 ENG KNAPP
nla
3,709,600
3,709,600
WD: #830, 3/4-Ton CNG Full -Size Van
21 WD VEH1
n/a
44,000
44,000
WD: New Step Service Van
21 WD VEH2
n/a
150,000
150,000
WFP: #891, 3/4-Ton 44 Pickup Truck
21 WF VEH1
n/a
50,000
50,000
WFP: Re -Paint Washburn Water Tower and Add Mixing
21 WF WSH TIN
n/a
1,100,000
1,100,000
WD: #815, Backhoe/Front End Loader
22 WD VEH1
n/a
150,000
150,000
Produced Using the Plan -It Capital Planning Sofhi,are Page 6 Wednesday, July 1, 2020
Department Project # Priority 2021 2022 2023 2024 2025 Total
WD: #819, Mini Dump Truck
22 WD VEH2
n/a
85,000
85,000
WFP: Water Filtration Plant Membrane Roof Repl.
22 WF ROOF
n/a
225,000
225,000
WD: #801, 3/4-Ton CNG 44 Pickup Truck
23 WD VEH1
nla
49,000
49,000
WD: #821, 3/4-Ton Pickup Truck
23 WD VEH2
n/a
60,000
60,000
WFP: Replace Low -Lift Pumps and Related Equipment
23 WF LL PMP
n/a
1,271,000
1,271,000
WD: #835, Replace with Tri-Axle Dump Truck
24 WD VEH1
n/a
205,000
205,000
WFP: Replace Floor Cleaner
24 WF F CLNR
n/a
20,000
20,000
WD: #809, Trailer -Mounted Dewatering Pump
25 WD VEH1
nla
50,000
50,000
WD: #829, 3/4-Ton Van
25 WD VEH2
n/a
40,000
40,000
WD: #817, Mini Dump Truck
25 WD VEH3
n/a
85,000
85,000
WD: #827, 3/4-Ton Pickup Truck
25 WD VEH4
n/a
60,000
60,000
WFP: Ammonia Gas Scrubber
25 WFA SCBR
n/a
451,000
451,000
WFP: Chlorine Gas Scrubber
25 WF C SCBR
n/a
383,000
383,000
WFP: Replace SCADA Computers
25 WF SCADA
n/a
20,000
20,000
541 - Water Total
15,468,600 12,780,000 12,200,000 1,960,000 6,334,000
48,742,600
551 - Sewer
ENG: Inflow/Infiltration Removal
00 ENG LEAKS
n/a
1,000,000 1,000,000 1,000,000 1,500,000 1,500,000
6,000,000
WW: Bowen Street Pump Station Upgrades
00 WW BOWEN
n/a
100,000 650,000
750,000
WW: Replace WWTP Chlorinators and Piping
00 WW CHL PP
n/a
50,000 192,000
242,000
WW: Clean Digesters
00 WW CL DIG
n/a
95,000 95,000 95,000
285,000
WW: Clarifiers #1, #2, #3, & #4 Floor Replacement
00 WW CLRFRS
We
450,000 450,000
900,000
WW: Replace Electrical Unit Substations
00 WW EUSS
n/a
890,000 2,593,500 4,182,000
7,665,500
WW: Collection System Inspections
00 WW INSPEC
nla
100,000 1,400,000
1,500,000
WW: Replace Polymer Mixing System
00 WW PM SYS
nla
50,000 370,000
420,000
WW: Replace Shorewood Lift Station Piping & Valves
00 WW SHORE
n/a
45,000 185,000
230,000
ENG: Fond du Lac Sanitary Sewer
21 ENG FDL
n/a
5,400,400
5,400,400
WW: Assessment of WWTP Piping Condition
21 WW ASSESS
n/a
30,000
30,000
WW: Repl Broad St Pump Station Make-up Air Unit #1
21 WW BR PSI
n/a
15,000
15,000
WW: Chlorine Feed System Upgrade
21 WW CF SYS
n/a
555,000
555,000
WW: WWTP Concrete Condition Assessment
21 WW CONCRT
n/a
23,000
23,000
WW: Update/Relocation of Dump Site
21 WW DUMP
n/a
2,000,000
2,000,000
WW: Add Ladder Access in WWTP Pump Room
21 WW LADDR
n/a
13,000
13,000
WW: Replace Computers and Related Equipment
21 WW PUTERS
nla
25,000
25,000
WW: #172, Zero-Tum Lawn Mower
21 WW VEH1
n/a
11,300
11,300
ENG: Bowen Street Interceptor Sewer
22 ENG BOWEN
nla
3,744,600
3,744,600
WW: Repl Dry Weather VFD at Broad St. Pump Station
22 WW BR VFD
nla
35,000
35,000
WW: #970, Pickup Truck
22 WW VEH1
n/a
45,000
45,000
WW: WWTP Pump Room Repairs
22 WW WTP PR
n/a
175,000
175,000
WW: Replace Effluent Strainers
23 WW EFF ST
n/a
205,000
205,000
WW: Replace WWTP Influent Bar Screens
24 WW BAR SC
n/a
1,900,000
1,900,000
WW: Replace Digester Area HVAC
24 WW D HVAC
n/a
150,000
150,000
WW: Replace Wastewater Facility HVAC
25 WW HVAC
n/a
112,000
112,000
WW: Repl S Main St Pump Station Generator & Equip
25 WW S MAIN
n/a
130,000
130,000
WW: #173, Zero-Tum Lawn Mower
25 WW VEH1
n/a
9,000
9,000
551 - Sewer Total
10,462,700 8,368,100 5,777,000 5,932,000 2,031,000
32,570,800
561 - Storm Water
ENG: Femau Watershed Detention Basin (Hoffmaster)
00 ENG FRNAU
n/a
50,000 350,000 5,000,000
5,400,000
ENG: Glatz Cr/Gallups-Memtts/Johnson Av Wtrsheds
00 ENG GALMR
n/a
500,000 3,000,000 185,000
3,685,000
ENG: Mini Storm Sewers/Storm Laterals
00 ENG MINI
n/a
675,000 675,000 675,000 675,000 675,000
3,375,000
ENG: Anchorage Watershed RR-Libbey Storm Sewer
00 ENG RR LI
n/a
100,000 2,179,000 993,000
3,272,000
ENG: Sawyer Creek Watershed Detention Basin
00 ENG SAWYR
n/a
1,500,000 300,000 5,000,000
6,800,000
ENG: Stringham Watershed Box Culvert -Phase 2
00 ENG STRHM
n/a
400,000 4,019,000
4,419,000
ENG: Vegetation Planting
00 ENG VEGET
n/a
95,000 169,000
264,000
Produced Using the Plan -It Capital Planning Sofhvare Page 7 Wednesday, July 1, 2020
Department Project # Priority 2021 2022 2023 2024 2025 Total
ENG: Westowne Area Detention Basin
SW: #100, Zero-Tum Mower
SW: #228, Trailered Water Pump
SW: #157, Street Sweeper
SW: #159, Street Sweeper
561 - Storm Water Total
GRAND TOTAL
00 ENG WSTWN
n/a 800,000 185,000
21 SW VEH1
n/a 10,000
22 SW VEH1
n/a 50,000
23 SW VEH1
n/a
25 SW VEH1
n/a
295,000
290,000
985,000
10,000
50,000
295,000
290,000
3,585,000 6,389,000 7,508,000 5,229,000 6,134,000 28,845,000
64,511,300 72,038,370 68,719,720 43,731,684 42,030,058 291,031,132
Produced Using the Plan -It Capital Planning Software Page 8 Wednesday, July 1, 2020
City of Oshkosh, Wisconsin
Manager Recommended Capital Improvement Plan
2021 thru 2025
FUNDING SOURCE SUMMARY
Source 2021 2022 2023 2024 2025 Total
Assessment
21947,400
3,680,600
3,146,100
3,327,200
3,217,900
16,319,200
Cash - Fund Balance
200,000
200,000
400,000
Debt
12,909,161
20,627,100
24,254,780
13,723,700
11,402,100
82,916,841
Debt State Trust Fund Loan
830,000
540,000
250,000
250,000
250,000
2,120,000
Donations
85,000
86,000
Grant
5,810,300
1,384,000
800,000
800,000
1,880,000
10,674,300
Levy
1,100,000
1,464,170
1,707,140
1,535,084
1,584,958
7,391,352
Operations
100,000
292,000
1,075,000
290,000
230,000
1,987,000
Prior Year Funding
456,339
8,000
40,000
504,339
Safe Drinking Water Loan
10,000,000
8,530,000
9,520,000
28,050,000
Sewer Revenue Bonds
13,735,200
13,792,400
10,416,000
7,835,900
3,733,300
49,512,600
Sewer Utility Fund
816,000
715,000
810,000
810,000
818,150
3,969,150
Storm Revenue Bonds
6,990,000
10,704,500
9,435,000
7,175,000
7,702,000
42,006,500
Storm Water Utility Fund
790,000
790,000
790,000
1,140,000
790,000
4,300,000
TID #14 Cash
200,000
200,000
400,000
TID #19 Cash
20,000
20,000
TID Cash
400,000
400,000
400,000
400,000
400,000
2,000,000
Trade -In
73,000
175,000
129,500
105,500
134,350
617,350
Transit Fund
10,000
10,000
10,000
10,000
10,000
50,000
Water Revenue Bonds
5,809,900
7,405,600
5,771,200
5,779,300
9,512,300
34,278,300
Water Utility Fund
1,429,000
1,505,000
165,000
165,000
165,000
3,429,000
GRAND TOTAL
64,511,300
72,223,370
68,719,720
43,546,684
42,030,058
291,031,132
Produced Using the Plan -It Capital Planning Software Page 1 Wednesday, July 1, 2020
City of Oshkosh, Wisconsin
Manager Recommended Capital Improvement Plan
2021 thru 2025
PROJECTS BY FUNDING SOURCE
Source Project # Priority 2021 2022 2023 2024 2025 Total
Assessment
ENG: Asphalt Program (Annual)
00 ASPHALT
n/a
150,000
150,000
150,000
450,000
ENG: Bradley Street Asphalt Paving
00 BRADLEY
n/a
333,400
333,400
ENG: Mini Storm Sewers/Storm Laterals
00 ENG MINI
n/a
25,000
25,000
25,000
25,000
25,000
125,000
ENG: Stringham Watershed Box Culvert -Phase 2
00 ENG STRHM
n/a
39,000
39,000
Sidewalks: New Walk Ordered In
00 NEW WALKS
n/a
65,000
65,000
65,000
65,000
65,000
325,000
Sidewalks: Rehabilitation & Reconstruction Program
00 REHAB
n/a
588,000
588,000
588,000
588,000
588,000
2,940,000
Sidewalks: Subdivision Agreements
00 SUBDIVNS
n/a
27,500
27,500
27,500
27,500
27,500
137,500
Ceape Avenue Reconstruction
210EAPEAVE
n/a
956,800
956,800
ENG: Fond du Lac Sanitary Sewer
21 ENG FDL
n/a
23,000
23,000
Omro Road Reconstruction
21 OMRO RD
n/a
268,600
268,600
West 9th Avenue Reconstruction
21 WEST 9TH
n/a
993,500
993,500
Algoma Boulevard Reconstruction
22 ALGOMA
n/a
1,520,700
1,520,700
East Lincoln Avenue Reconstruction
22 ELINCOLN
n/a
572,100
572,100
Grand Street Reconstruction
22 GRAND ST
n/a
339,400
339,400
Rosalia St. Water Main Replacement/Asphalt Paving
22 ROSALIA
n/a
209,500
209,500
McKinley Street Reconstruction
23 MCKINLEY
n/a
139,800
139,800
South Main Street Reconstruction
23 S MAIN
n/a
1,621,500
1,621,500
West Lincoln Avenue Reconstruction
23 W LINCOLN
n/a
529,300
529,300
Central Street Reconstruction
24 CENTRAL
n/a
540,000
540,000
Cherry Street Reconstruction
24 CHERRY
n/a
768,900
768,900
Mill Street Reconstruction
24 MILL ST
n/a
156,500
156,500
Waugoo Avenue Reconstruction
24 WAUGOO
n/a
967,300
967,300
Arthur Avenue Reconstruction
25 ARTHUR
n/a
387,400
387,400
Bay Shore Drive Reconstruction
25 BAY SHORE
n/a
393,000
393,000
Bowen Street Reconstruction
25 BOWEN ST
n/a
392,100
392,100
Ripon Lane Utility Installation & Asphalt Patching
25 RIPON LN
n/a
186,800
186,800
West 15th Avenue Reconstruction
25 WEST 15TH
n/a
1,003,100
1,003,100
Assessment Total 2,947,400 3,680,600 3,146,100 3,327,200 3,217,900 16,319,200
Cash - Fund Balance
Parks: Menominee Prk Prkg Lot & Reetz Fids -Design 00 MP LOT DS 3 200,000 200,000
Parks: Rainbow Memorial Park Improvements 00 RB PRK IP 4 200,000 200,000
Cash - Fund Balance Total 200,000 200,000 400,000
Debt
CD: 9th Avenue Extension East to Main Street
00 9TH AVE
3
3,000,000
3,500,000
6,500,000
ENG: Asphalt Program (Annual)
00 ASPHALT
n/a
150,000
150,000
150,000 450,000
ENG: Bradley Street Asphalt Paving
00 BRADLEY
n/a
226,000
226,000
GS: HVAC/Roofing Replacement Program
00 HVACIROOF
1 500,000
500,000
500,000
500,000
500,000 2,500,000
Parks: Lakeshore Park Phase 1b Development
00 LAKESHORE
3
500,000
500,000
1,000,000
TR: Parking Lot Improvements
00 LOT IMRPV
2 500,000
500,000
500,000
500,000
500,000 2,500,000
Parks: Menominee Prk Prkg Lot & Reetz Fids -Design
00 MP LOT DS
3
350,000
2,800,000
3,150,000
Produced Using the Plan -It Capital Planning Sofhvare
Page I
WVednesday, July 1, 2020
Source Project # Priority 2021 2022 2023 2024 2025 Total
Parks: Menominee Park Road Reconstruction
00 MP RD CON
2
500,000
500,000 1,000,000
Oregon Street Interceptor Sewer
00 OREGON ST
n/a
250,000
250,000
Parks: New Building Construction
00 PRKS BLDG
2
3,400,000
3,000,000
6,400,000
Parks: Rainbow Memorial Park Improvements
00 RB PRK IP
4
400,000 2,550,000 2,950,000
Sidewalks: Rehabilitation & Reconstruction Program
00 REHAB
nla
300,000
300,000
300,000
300,000 300,000 1,500,000
CD: Riverwalk on Pioneer Island and Marina
00 RW PIONER
3
1,200,000
3,200,000
1,200,000 5,600,000
CD: South Main Acquisition
00 S MAINAQ
1
250,000
500,000
250,000
1,000,000
ENG: West 9th Ave Gateway Corridor Improvements
00 IN9TH IMP
n/a
300,000
550,000 850,000
Ceape Avenue Reconstruction
21 CEAPE AVE
n/a
1,530,400
1,530,400
ENG: #389, 4-Wheel Drive 1/2-Ton Pickup Truck
21 ENG VEHI
n/a
36,500
36,500
Fire: Replace'94 Ford Expl with 1 Ton pickup
21 FIRE VEHI
3
44,300
44,300
Fire: Replacement of'99 Chevrolet Suburban
21 FIRE VEH2
3
45,200
45,200
CD: Jackson St Corridor SftyStdy ImplementationPH1
21 JSC PHI
2
60,000
60,000
Library: Replace Emergency Electric Generator Sys
21 LIB GENER
2
40,600
40,600
Parks: Menominee Park Zoo Improvements
21 M PRK ZOO
3
100,000
100,000
CD: Multimodal Trail Rainbow Park
21 MM TRL RB
2
330,000
330,000
Parks: Menominee Park Trail Improvements/drainage
21 MP TRL IM
3
75,000
75,000
Omro Road Reconstruction
21 OMRO RD
n/a
31,400
31,400
Police: Renovations to Vacant Ofc Space North End
21 PD RENO
2
150,000
150,000
Police: SWAT Team Truck Replacement
21 PD SWT TR
1
200,000
200,000
Parks: Replace'01 Ford Workhorse Step Van #401
21 PRKS VEHI
1
57,500
57,500
Parks: Replace'07 Ford F-250 #418
21 PRKS VEH3
3
37,000
37,000
Parks: Replace'89 Topsoil Screener
21 PRKS VEH4
3
27,500
27,500
Parks: Roe Park Play Equipment Replacement
21 ROE EQUIP
2
200,000
200,000
CD: Riverwalk Construction S. Main St to RR Tracks
21 RW CONSTI
1
600,000
600,000
CD: Riverwalk East of RR Tracks along Pioneer Dr
21 RW CONST2
2
500,000
500,000
CD: Former Sanitation Garage Demo
21 SANI DEMO
3
200,000
200,000
Parks: South Park Tennis Court Reconstruction
21 SP TEN CT
2
325,000
325,000
STR: #67, Tandem -Axle Plow Truck
21 STR VEHI
n/a
210,000
210,000
STR: #24, Flat Bed Truck
21 STR VEHIO
n/a
95,000
95,000
STR: #104, Concrete Breaker
21 STR VEHII
n/a
95,000
95,000
STR: #33, 3/4-Ton 4WD Pickup Truck
21 STR VEH2
n/a
37,500
37,500
STR: #50 Single -Axle Plow Truck
21 STR VEH3
n/a
189,000
189,000
STR: #140, Motor Grader
21 STR VEH4
n/a
195,000
195,000
STR: #122, Skid Steer and Router
21 STR VEH5
n/a
73,000
73,000
STR: #262, Walk -Behind Router
21 STR VEH6
n/a
24,500
24,500
STR: #22, 1-Ton 4WD Pickup Truck
21 STR VEH7
n/a
41,500
41,500
STR: #68, Tandem -Axle Plow Truck
21 STR VEH8
n/a
210,000
210,000
TR: 2 hybrid & 2 clean diesel buses (rep] 2010's)
21 TR BUSES
1
56,061
56,061
Fire: Fire Training Center
21 TRNG CTR
1
3,798,780
3,798,780
TR: Electric Div Service Truck (repl 2008)
21 VEH ELEC1
3
60,000
60,000
TR: Sign Service Truck 1 to 1 1/2 Tn (repl 2004)
21 VEH SIGN1
2
90,000
90,000
Parks: Westhaven Circle Prk Play Equip & Surfacing
21 WCRL EQUP
2
200,000
200,000
Parks: Westhaven Circle Park Lighting Replacement
21 WCRL LGTS
3
30,000
30,000
West 9th Avenue Reconstruction
21 WEST 9TH
n/a
3,028,200
3,028,200
Parks: 44th Parallel Park Play Equip & Surfacing
22 44P EQUIP
2
200,000
200,000
Parks: 44th Parallel Park Lighting Replacement
22 44P LGHTS
3
30,000
30,000
Parks: Abbey Park Play Equipment & Surfacing
22 ABY EQUIP
2
200,000
200,000
Algoma Boulevard Reconstruction
22 ALGOMA
n/a
3,383,900
3,383,900
Museum: Replace Security Camera Systems
22 CAMERAS
3
85,000
85,000
East Lincoln Avenue Reconstruction
22 ELINCOLN
n/a
830,000
830,000
Museum: Elevator Modernization
22 ELEVATOR
3
125,000
125,000
Parks: Fugleberg Park Lighting Replacement
22 FGL LGHTS
3
30,000
30,000
Fire: Replacing 3 Ambulances from'12
22 FIRE VEH2
1
927,000
927,000
Grand Street Reconstruction
22 GRAND ST
n/a
572,700
572,700
Produced Using the Plan -It Capital Planning Software
Page 2
Wednesday, July 1, 2020
Source
Project # Priority 2021
2022
2023 2024 2025
Total
CD: Jackson St Corridor SftyStdy ImplementationPH2
22 JSC PH2
3
210,000
210,000
Library: Fire Alarm System
22 LIB ALARM
2
71,100
71,100
Library: Elevator#1 Modernization Upgrades
22 LIB ELEVI
3
115,500
115,500
Museum: Masonry Overhaul
22 MASONRY
3
200,000
200,000
Museum: Exterior Painting
22 PAINTING
4
75,000
75,000
Parks: Replace'07 Dodge Ram 35001 Tn #492
22 PRKS VEH1
3
49,000
49,000
Parks: Replace'l2 Toro 7200 Grndmstr Zero Tm #455
22 PRKS VEH2
2
56,500
56,500
Parks: Replace'09 Ford F450 #481
22 PRKS VEH3
2
109,000
109,000
Parks: Rainbow Mem Prk Play Equipment & Surfacing
22 RB EQUIP
2
200,000
200,000
Rosalia St. Water Main Replacement/Asphalt Paving
22 ROSALIA
n/a
761,400
761,400
SAN: #201, 4WD Supervisor's Pickup Truck
22 SANI VEH2
n/a
34,000
34,000
Parks: Stevens Park Lighting Replacement
22 SP LGHTS
3
30,000
30,000
STR: #256, Rock Drill
22 STR EQPI
n/a
10,000
10,000
STR: #69, Tandem -Axle Plow Truck
22 STR VEH1
n/a
220,000
220,000
STR: #244, Leaf Blower
22 STR VEH2
n/a
65,000
65,000
STR: #34,1-Ton 4WD Crew Cab Pickup Truck
22 STR VEH3
Na
42,500
42,500
STR: #53, Single -Axle Plow Truck
22 STR VEH4
n/a
189,000
189,000
STR: #106, Rubber -Tire Backhoe
22 STR VEH5
n/a
145,000
145,000
STR: #110, Sidewalk Tractor
22 STR VEH6
n/a
130,500
130,500
STR: #70, Tandem -Axle Plow Truck
22 STR VEH7
n/a
210,000
210,000
STR: #93, Semi -Tractor
22 STR VEHB
n/a
95,000
95,000
STR: #239 and #246, Stainless Tanker Semi -Trailer
22 STR VEH9
n/a
80,000
80,000
TR: Supervisor Pickup Truck (rep[ 2012)
22 TRAN VEH1
3
8,000
8,000
TR: Traffic Signal Westhaven Dr & 9th Avenue
22 TRSIGNALI
3
175,000
175,000
TR: Electrical Supervisor Truck (repl 2008)
22 VEH ELEC1
3
50,000
50,000
Museum: Building Modifications
23 BLDG MODS
3
800,000
800,000
Museum: Creation of Access Doors
23 DBL DOORS
2
75,000
75,000
Fire: Replacement for'06 Fire Engine
23 FIRE ENG1
1
627,000
627,000
Library: Elevator#2 Modernization Upgrades
23 LIB ELEV2
3
105,100
105,100
McKinley Street Reconstruction
23 MCKINLEY
n/a
249,100
249,100
Museum: Memories Dreams Gallery Refurbishment
23 MEMORIES
2
300,000
300,000
ENG: Mockingbird Way Traffic Calming
23 MOCKBIRD
n/a
90,000
90,000
Museum: Parking Lot Improvements
23 MUSM LOTS
3
600,000
600,000
Parks: Replace'l1 John Deere Gator#499
23 PRKS VEHI
3
29,500
29,500
Parks: Replace'l3 Toro 7200 Gmdmstr Zero Tm #454
23 PRKS VEH2
2
61,500
61,500
Parks: Replace'08 Ford F-250 #493
23 PRKS VEH3
3
44,000
44,000
Parks: Replace'09 Chevrolet 3500 HD #486
23 PRKS VEH4
3
49,000
49,000
Parks: Replace'08 Ford Econoline Van #409
23 PRKS VEH5
3
29,000
29,000
Parks: Replace'07 Ford Ranger Ext Cab #417
23 PRKS VEH6
3
39,500
39,500
Parks: Replace'08 Ford F-3501 Ton Truck#416
23 PRKS VEH7
4
38,500
38,500
Parks: Quarry Park Restroom/Shelter Building Reno
23 QRY BLDG
3
150,000
150,000
Parks: Rusch Park Development
23 RUSCH DEV
n/a
200,000
200,000
South Main Street Reconstruction
23 S MAIN
n/a
2,967,000
2,967,000
SAN: #206, Rear -Load Refuse Truck
23 SANI VEH1
n/a
190,000
190,000
Parks: Stevens Park Play Equipment and Surfacing
23 SP EQUIP
3
200,000
200,000
Parks: Site A Development - Ripple & Oregon
23 STE A DEV
3
300,000
300,000
Parks: Site B Development - 9th and Clairville
23 STE B DEV
3
300,000
300,000
Parks: Stoegbauer Park Restrooms/Shelter Constr
23 STGBR BLD
3
200,000
200,000
STR: #200, Road Saw
23 STR EQP1
n/a
29,500
29,500
STR: #71, Tandem -Axle Plow Truck
23 STR VEH1
n/a
210,000
210,000
STR: #40, Single -Axle Area Plow Truck
23 STR VEH2
n/a
189,000
189,000
STR: #26, 1-Ton 4WD Dump Truck
23 STR VEH3
n/a
85,000
85,000
STR: #260, Crack Filler
23 STR VEH4
n/a
45,000
45,000
STR: #264, Tar Kettle Trailer Unit
23 STR VEH5
n/a
39,000
39,000
STR: #32, 3/4-Ton 4WD Pickup Truck
23 STR VEH6
n/a
40,000
40,000
Produced Using the Plan -It Capital Planning Sofhvare Page 3 Wednesday, July 1, 2020
Source Project # Priority 2021 2022 2023 2024 2025 Total
STR: #163, Asphalt Roller
23 STR VEH7
n/a
51,000
51,000
STR: #116, Articulated Loader
23 STR VEH8
n/a
275,000
275,000
STR: #54 and #20, Hook Lift Trucks
23 STR VEH9
n/a
215,000
215,000
Parks: Teichmiller Park Tennis Court Reconstruct
23 TEIC TNIS
n/a
200,000
200,000
West Lincoln Avenue Reconstruction
23 W LINCOLN
n/a
1,053,300
1,053,300
Parks: 44th Parallel Park Tennis Court Reconst
24 44P TENIS
3
200,000
200,000
Parks: Abe Rochlin Park Play Equipment & Surfacing
24 ABE EQUIP
3
200,000
200,000
Central Street Reconstruction
24 CENTRAL
n/a
1,033,000
1,033,000
Cherry Street Reconstruction
24 CHERRY
n/a
1,197,400
1,197,400
ENG: #386, 4-Wheel Drive 1/2-Ton Pickup Truck
24 ENG VEHI
n/a
36,500
36,500
Library: Elevator#3 Modernization Upgrades
24 LIB ELEV3
3
117,300
117,300
Mill Street Reconstruction
24 MILL ST
n/a
424,200
424,200
Parks: Replace'14 Toro 7200 Gmdmstr Zero Tm #456
24 PRKS VEHI
2
61,500
61,500
Parks: Replace'l2 CNG Dump Truck #412
24 PRKS VEH2
n/a
69,000
69,000
Parks: Replace'09 Leaf PickerNacuum #031
24 PRKS VEH3
n/a
29,500
29,500
SAN: #207, Rear -Load Refuse Truck
24 SANI VEHI
n/a
190,000
190,000
Parks: Stevens Park Tennis Court Reconstruction
24 SP TENNIS
3
100,000
100,000
STR: #108, Floor Scrubber
24 STR EQP1
n/a
60,000
60,000
STR: #218, Trailered Air Compressor
24 STR EQP2
n/a
30,000
30,000
STR: #72, Tandem -Axle Dump Truck
24 STR VEHI
n/a
210,000
210,000
STR: #41, Single -Axle Area Plow Truck
24 STR VEH2
n/a
189,000
189,000
STR: #92, Semi -Tractor
24 STR VEH3
Na
100,000
100,000
STR: #230, 5-Ton Tandem -Axle Trailer
24 STR VEH4
n/a
10,000
10,000
STR: #36, 4WD Single -Axle Truck
24 STR VEH5
n/a
110,000
110,000
STR: #174, Utility Tractor
24 STR VEH6
n/a
205,000
205,000
STR: #105, Zero-Tum Mower
24 STR VEH7
n/a
10,000
10,000
TR: Electric Division Truck (repl 2003)
24 VEH ELECT
3
200,000
200,000
Parks: West Algoma Park Play Equipment & Surfacing
24 WALG EQP
3
200,000
200,000
Waugoo Avenue Reconstruction
24 WAUGOO
n/a
1,641,300
1,641,300
Parks: Westhaven Circle Prk Tennis Crt Reconstuct
24 WHCRL TNS
3
200,000
200,000
TR: 2 Elec Buses (repl 2013's) & 1 Charging Infras
25 2ELEC BUS
1
200,000
200,000
Arthur Avenue Reconstruction
25ARTHUR
n/a
607,900
607,900
Parks: Red Arrow Park Play Equipment
25 ARW EQUIP
3
200,000
200,000
Parks: Red Arrow Park Lighting Replacement
25 ARW LGHTS
3
40,000
40,000
Bay Shore Drive Reconstruction
25 BAY SHORE
n/a
634,600
634,600
Bowen Street Reconstruction
25 BOWEN ST
n/a
1,070,600
1,070,600
Museum: Implement Landscape Plan
25 LANDSCAPE
3
300,000
300,000
Parks: Menominee Park Lighting Replacement
25 MP LIGHTS
3
50,000
50,000
Parks: Menominee Park Tennis Court Lights
25 MP TC LTS
4
150,000
150,000
Parks: Replace Enclosed Trailer #428
25 PRKS TRLR
2
11,000
11,000
Parks: Replace'l5 Toro 7200 Gmdmstr Zero Trn #457
25 PRKS VEHI
2
66,500
66,500
Parks: Replace'12 Smithco Athletic Field Grmr P12
25 PRKS VEH2
2
22,500
22,500
Parks: Quarry Park Dog Park Development
25 QURY DOG
4
100,000
100,000
Ripon Lane Utility Installation & Asphalt Patching
25 RIPON LN
n/a
321,200
321,200
SAN: #212, Rear -Load Refuse Truck
25 SANI VEH1
n/a
190,000
190,000
STR: #73, Tandem -Axle Plow Truck
25 STR VEHI
n/a
220,000
220,000
STR: #241, Leaf Blower
25 STR VEH2
n/a
65,000
65,000
STR: #44, Single -Axle Area Plow Truck
25 STR VEH3
n/a
189,000
189,000
STR: #172, 114' Snow Blower
25 STR VEH4
n/a
175,000
175,000
STR: #117, Articulated Loader
25 STR VEH5
n/a
275,000
275,000
STR: #168, Paver
25 STR VEH6
n/a
165,000
165,000
STR: #240, Tandem -Axle Equipment Trailer
25 STR VEH7
n/a
19,000
19,000
STR: #37, Supervisors Pickup Truck
25 STR VEH8
n/a
32,500
32,500
SW: #159, Street Sweeper
25 SW VEHI
n/a
280,000
280,000
TR: Replace Go Transit Hoist in maintenance garage
25 TR HOIST
2
20,000
20,000
Produced Using the Plan -It Capital Planning Sofhvare
Page 4
Wednesday, Judy 1, 2020
Source Project # Priority 2021 2022 2023 2024 2025 Total
Parks: Replace'14 Skag Zero Turn Mower #1
25 TRN MOWR1
2
14,500
14,500
Parks: Replace'14 Skag Zero Turn Mower#2
25 TRN MOWR2
2
14,500
14,500
Parks: Replace'14 Skag Zero Turn Mower #3
25 TRN MOWR3
2
14,500
14,500
Parks: Replace'l4 Skag Zero Turn Mower#4
25 TRN MOWR4
2
14,500
14,500
West 15th Avenue Reconstruction
25 WEST 15TH
nla
1,539,300
1,539,300
Parks: Westhaven Circle Park - Splash Pad
25 WHCRL PAD
4
400,000
400,000
Debt Total
12,909,161
20,627,100
24,254,780 13,723,700
11,402,100
82,916,841
Debt: State Trust Fund Loan
CD: Gateway Blight Elimination
00 BLGT REM2
2
250,000
250,000
250,000 250,000
250,000
1,250,000
SAN: #218, Automated Side -Load Refuse Truck
21 SANI VEH1
nla
290,000
290,000
SAN: #217, Automated Side -Load Refuse Truck
21 SANI VEH2
nla
290,000
290,000
SAN: #219, Automated-Sideload Refuse Truck
22 SANI VEH1
nla
290,000
290,000
Debt: State Trust Fund Loan Total
830,000
540,000
250,000 250,000
250,000
2,120,000
Donations
GS: Grand Opera House Signage Updates
21 GOH SIGNS
3
75,000
75,000
GS: Grand Opera House Stage Floor Replacement
21 GOH STAGE
2
10,000
10,000
Donations Total
85,000
85,000
Grant
CD: Riverwalk on Pioneer Island and Marina
00 RW PIONER
3
800,000
800,000 800,000
2,400,000
TR: Automated Wheelchair Securement Sys 12 buses
21 AUT WHLCH
2
180,000
180,000
CD: Multimodal Trail Rainbow Park
21 MM TRL RB
2
255,300
255,300
CD: Riverwalk Construction S. Main St to RR Tracks
21 RW CONST1
1
500,000
500,000
CD: Riverwalk East of RR Tracks along Pioneer Dr
21 RW CONST2
2
500,000
500,000
TR: 2 hybrid & 2 clean diesel buses (rep] 201 O's)
21 TR BUSES
1
2,360,000
2,360,000
TR: Forklift (repl 1993 Komatsu FD 25VT-11 Diesel)
21 TR FRKLFT
3
35,000
35,000
TR: Electronic Fare ReaderslFarebox for Buses
21 TRAN FARE
1
160,000
160,000
TR: Downtown Transit Center
21 TRANS CTR
1
2,320,000
2,320,000
TR: Riding Lawnmower (rep] 2005 Toro Z Master)
22 LAWNMOWER
3
20,000
20,000
TR: Supervisor Pickup Truck (repl 2012)
22 TRAN VEH1
3
32,000
32,000
TR: Driver Shuttle Vehicle (repl 2011 Honda Civic)
22 TRAN VEH2
3
32,000
32,000
TR: 2 Elec Buses (rep] 2013's) & 1 Charging Infras
25 2ELEC BUS
1
1,800,000
1,800,000
TR: Replace Go Transit Hoist in maintenance garage
25 TR HOIST
2
80,000
80,000
Grant Total
5,810,300
1,384,000
800,000 800,000
1,880,000
10,674,300
Levy
CD: Bicycle and Pedestrian Infrastructure
00 BKE N PED
3
50,000
50,000
50,000 50,000
50,000
250,000
CD: Blight Removal Scattered Sites
00 BLGT REM1
2
250,000
250,000
500,000 500,000
500,000
2,000,000
ENG: Concrete Pavement Repairs (Annual)
00 CONCRETE
nla
128,000
125,000
175,000 125,000
125,000
678,000
ENG: Mini Storm Sewers/Storm Laterals
00 ENG MINI
nla
25,000
25,000
25,000 25,000
25,000
125,000
ENG: Up -Front Engineering Services
00 ENG SRVCS
nla
30,000
30,000
30,000 30,000
30,000
150,000
Fire: Turn Out Gear Pants & Coats
00 FIRE GEAR
1
40,000
32,100
12,800 24,325
109,225
Fire: Turn Out Gear Helmets
00 FIRE HELM
1
5,000
1,740 4,659
18,458
29,857
GS: Office Furniture Replacement
00 FURN REPL
2
10,000
10,000
10,000 10,000
10,000
50,000
CD: Great Neighborhoods Initiative
00 G NHOODS
2
175,000
175,000
200,000 250,000
250,000
1,050,000
CD: Gateway Improvements
00 GATE IMPR
2
50,000
50,000
100,000 100,000
200,000
500,000
GS: Grand Opera House Seat Replacement Program
00 GOH SEATS
2
50,000
50,000
100,000
Produced Using the Plan -It Capital Planning Sofhvare
Page 5
Wednesday, July 1, 2020
Source Project # Priority 2021 2022 2023 2024 2025 Total
Sidewalks: New Walk Ordered In
00 NEW WALKS
n/a
5,000
5,000
5,000
5,000
5,000
25,000
Fire: Parking Lot Program Station 18
00 PRKG LT18
1
0
83,600
43,600
127,200
Parks: Riverside Cemetery Roads Repaving
00 R CEM RDS
3
25,000
25,000
25,000
75,000
CD: Riverway Drive Trail to Riverwalk
00 RVR WY TR
5
175,000
175,000
350,000
CD: Riverwalk Signage and Banners
00 RW SIGNS
3
25,000
25,000
50,000
50,000
50,000
200,000
TR: LED Traffic Signal Head Equipment
00 SGNL HEAD
3
10,000
10,000
10,000
10,000
10,000
50,000
TR: LED Streetlighting Upgrades
00 STR LGHTS
3
10,000
10,000
10,000
10,000
10,000
50,000
TR: Purchase Streetlighting Poles
00 STR POLES
3
25,000
25,000
25,000
25,000
25,000
125,000
Sidewalks: Subdivision Agreements
00 SUBDIVNS
n/a
2,500
2,500
2,500
2,500
2,500
12,500
TR: Traffic Signal Equipment
00 TRF SGNL
3
45,000
45,000
45,000
45,000
45,000
225,000
GS: Complete ADA Audit of all City buildings
21 ADA AUDIT
2
60,000
60,000
GS: City Hall Security Improvements
21 CTYHALSEC
1
75,000
75,000
Fire: Turn Out Gear Boots
21 FIRE BTS
1
49,500
49,500
Fire: Replacement of Generator at Fire Station 16
21 GEN ST16
2
60,000
60,000
GS: Grand Opera House Stage Floor Replacement
21 GOH STAGE
2
25,000
25,000
Fire: New Hose to Replace Obsolete Hose
21 HOSE REPL
1
66,570
66,570
CD: Industrial Park Signs
211ND SIGNS
3
20,000
20,000
GS: Seniors Center (North) Front Desk Replacement
21 OSC FDESK
3
10,000
10,000
Parks: Replace'06 Vermeer BC 1000 XL Chipper#471
21 PRKS VEH2
2
58,000
58,000
Parks: Riverwalk Light Bollards Replacement
21 RW BOLRDS
2
25,000
25,000
STR: #238, Single -Axle Trailer
21 STR VEH9
n/a
10,000
10,000
GS: Grand Opera House Dimmer Rack Replacement
22 GOH DIMMR
2
75,000
75,000
GS: Safety Building Elevator 1-2 Modernizations
22 SB ELEVS
1
250,000
250,000
GS: City Hall 2nd Floor Hallway Tile Replacement
23 CTYHAL2ND
4
20,000
20,000
GS: 3/4 Ton Van (rep] #003'97 GMC)
23 FAC VEH1
1
34,500
34,500
Fire: Replacing'98 Chevy3500
23 FIRE VEHI
2
47,000
47,000
GS: Grand Opera House Wheelchair Lift Replacement
23 GOH CH LF
1
40,000
40,000
GS: Seniors Center Flooring Replacement
23 OSC FLOOR
4
30,000
30,000
GS: 3/4 Ton Pickup (repl #002'08 Ford)
25 FAC VEHI
3
44,000
44,000
GS: Grand Opera House Plumbing Improvements
25 GOH PLUMB
1
65,000
65,000
GS: Grand Opera House Fire Pump Controller Repl
25 GOH PUMP
1
25,000
25,000
GS: Grand Opera House Wallpaper Replacement Prog
25 GOH WALL
3
20,000
20,000
Levy Total
1,100,000
1,464,170
1,707,140 1,535,084 1,584,958
7,391,352
Operations
Museum: Deep Roots, Growing City Exhibition
00 DP ROOTS
2
100,000
100,000
800,000
1,000,000
REC: #221, Hook -Lift Roll -Off Container Truck
22 RECYVEHI
n/a
140,000
140,000
REC: #202, 1-Ton 4WD Pickup Truck
22 RECY VEH2
n/a
52,000
52,000
REC: #210, Automated Side -Load Refuse Truck
23 RECYVEHI
n/a
275,000
275,000
REC: #209, Automated Side -Load Refuse Truck
24 RECYVEHI
n/a
290,000
290,000
REC: #111, Articulated Loader
25 RECYVEHI
nla
230,000
230,000
Operations Total
100,000
292,000
1,075,000 290,000 230,000
1,987,000
Prior Year Funding
Fire: Turn Out Gear Hi -Visibility Jackets
21 HI VISIB
1
32,400
32,400
GS: OCC Air Handler Unit (Mezzanine) Replacement
21 OCCAHU
1
200,000
200,000
TR: 2 hybrid & 2 clean diesel buses (repl 2010's)
21 TR BUSES
1
183,939
183,939
TR: Electronic Fare Readers/Farebox for Buses
21 TRAN FARE
1
40,000
40,000
TR: Driver Shuttle Vehicle (repl 2011 Honda Civic)
22 TRAN VEH2
3
8,000
8,000
GS: OCC Moveable Walls Wallpaper Replacement
23 OCC WALLS
3
40,000
40,000
Prior Year Funding Total
456,339
8,000
40,000
504,339
Produced Using the Plan -It Capital Planning Sofftvare Page 6 Wednesday, July 1, 2020
Source Project # Priority 2021 2022 2023 2024 2025 Total
Safe Drinking Water Loan
WFP: Clearwell Replacement 00 WF CLRWLL n/a 10,000,000 8,000,000 4,000,000
WFP: Replace Ozone Generators 00 WF GENER n/a 400,000 4,100,000
WFP: Replace Ozone Liquid Oxygen System 00 WF OZONE n/a 130,000 1,420,000
Safe Drinking Water Loan Total
Sewer Revenue Bonds
ENG: Asphalt Program (Annual)
00 ASPHALT
We
ENG: Bradley Street Asphalt Paving
00 BRADLEY
n/a
ENG: Inflow/Infiltration Removal
00 ENG LEAKS
n/a
Oregon Street Interceptor Sewer
00 OREGON ST
n/a
WW: Bowen Street Pump Station Upgrades
00 WW BOWEN
n/a
WW: Replace WWTP Chlorinators and Piping
00 WW CHL PP
n/a
WW: Clarifiers #1, #2, #3, & #4 Floor Replacement
00 WW CLRFRS
n/a
WW: Replace Electrical Unit Substations
00 WW EUSS
n/a
WW: Collection System Inspections
00 WW INSPEC
n/a
WW: Replace Polymer Mixing System
00 WW PM SYS
n/a
WW: Replace Shorewood Lift Station Piping & Valves
00 WW SHORE
n/a
Ceape Avenue Reconstruction
21 CEAPE AVE
n/a
ENG: Fond du Lac Sanitary Sewer
21 ENG FDL
We
West 9th Avenue Reconstruction
21 WEST 9TH
We
WW: Chlorine Feed System Upgrade
21 WW CF SYS
n/a
WW: Update/Relocation of Dump Site
21 WW DUMP
We
WW: #172, Zero -Turn Lawn Mower
21 WW VEH1
n/a
Algoma Boulevard Reconstruction
22 ALGOMA
We
East Lincoln Avenue Reconstruction
22 E LINCOLN
n/a
ENG: Bowen Street Interceptor Sewer
22 ENG BOWEN
n/a
Grand Street Reconstruction
22 GRAND ST
n/a
Rosalie St. Water Main ReplacementlAsphalt Paving
22 ROSALIA
n/a
WW: Repl Dry Weather VFD at Broad St. Pump Station
22 WW BR VFD
n/a
WW: WWTP Pump Room Repairs
22 WW WTP PR
n/a
McKinley Street Reconstruction
23 MCKINLEY
n/a
ENG: Mockingbird Way Traffic Calming
23 MOCKBIRD
n/a
South Main Street Reconstruction
23 S MAIN
n/a
West Lincoln Avenue Reconstruction
23 W LINCOLN
n/a
WW: Replace Effluent Strainers
23 WW EFF ST
n/a
Central Street Reconstruction
24 CENTRAL
n/a
Cherry Street Reconstruction
24 CHERRY
n/a
Mill Street Reconstruction
24 MILL ST
We
Waugoo Avenue Reconstruction
24 WAUGOO
n/a
WW: Replace WWTP Influent Bar Screens
24 WW BAR SC
n/a
WW: Replace Digester Area HVAC
24 WW D HVAC
n/a
Arthur Avenue Reconstruction
25 ARTHUR
n/a
Bay Shore Drive Reconstruction
25 BAY SHORE
n/a
Bowen Street Reconstruction
25 BOWEN ST
n/a
Ripon Lane Utility Installation & Asphalt Patching
25 RIPON LN
nla
West 15th Avenue Reconstruction
25 WEST 15TH
n/a
WW: Replace Wastewater Facility HVAC
25 WW HVAC
n/a
WW: Rapt S Main St Pump Station Generator & Equip
25 WW S MAIN
n/a
Sewer Revenue Bonds Total
Sewer Utility Fund
22,000,000
4,500,000
1,550,000
10,000,000
8,530,000
9,520,000
28,050,000
50,000
50,000
50,000
150,000
50,000
50,000
500,000
500,000
500,000
1,000,000
1,000,000
3,500,000
2,775,600
3,955,700
3,297,900
10,029,200
100,000
650,000
750,000
50,000
192,000
242,000
450,000
450,000
900,000
890,000
2,593,500
4,182,000
7,665,500
100,000
1,400,000
1,500,000
50,000
370,000
420,000
45,000
185,000
230,000
1,113,900
1,113,900
5,227,400
5,227,400
1,163,500
1,163,500
555,000
555,000
1,000,000
1,000,000
9,800
9,800
1,160,900
1,160,900
496,300
496,300
3,669,600
3,669,600
286,400
286,400
50,000
50,000
35,000
35,000
175,000
175,000
218,900
218,900
3,000
3,000
1,139,100
1,139,100
570,100
570,100
205,000
205,000
647,500
647,500
874,500
874,500
63,800
63,800
863,100
863,100
1,900,000
1,900,000
150,000
150,000
399,700
399,700
367,800
367,800
458,500
458,500
123,100
123,100
907,200
907,200
112,000
112,000
130,000
130,000
13,735,200
13,792,400
10,416,000
7,835,900
3,733,300
49,512,800
Produced Using the Plan -It Capital Planning Software Page 7 Wednesday, July 1, 2020
Source Project # Priority 2021 2022 2023 2024 2025 Total
ENG: Concrete Pavement Repairs (Annual)
00 CONCRETE
n/a
15,000
20,000
20,000
20,000 20,000
95,000
ENG: Inflow/Infiltration Removal
00 ENG LEAKS
n/a
500,000
500,000
500,000
500,000 500,000
2,500,000
ENG: Up -Front Engineering Services
00 ENG SRVCS
n/a
195,000
195,000
195,000
195,000 195,000
975,000
WW: Clean Digesters
00 WW CL DIG
n/a
95,000
95,000 95,000
285,000
WW: Assessment of WWTP Piping Condition
21 WW ASSESS
n/a
30,000
30,000
WIN: Repl Broad St Pump Station Make-up Air Unit #1
21 WW BR PS1
n/a
15,000
15,000
WW: WWTP Concrete Condition Assessment
21 WW CONCRT
n/a
23,000
23,000
WW: Add Ladder Access in WWTP Pump Room
21 WW LADDR
n/a
13,000
13,000
WIN: Replace Computers and Related Equipment
21 WW PUTERS
n/a
25,000
25,000
WW: #173, Zero -Turn Lawn Mower
25 WW VEH1
n/a
8,150
8,150
Sewer Utility Fund Total
816,000
715,000
810,000
810,000 818,150
3,969,150
Storm Revenue Bonds
ENG: Asphalt Program (Annual)
00 ASPHALT
n/a
75,000
75,000 75,000
225,000
ENG: Bradley Street Asphalt Paving
00 BRADLEY
n/a
100,000
1,150,000
1,250,000
ENG: Femau Watershed Detention Basin (Hoffmaster)
00 ENG FRNAU
n/a
50,000
5,000,000
5,050,000
ENG: Glatz Cr/Gallups-Merdtts/Johnson Av Wtrsheds
00 ENG GALMR
n/a
500,000
3,185,000
3,685,000
ENG: Anchorage Watershed RR-Libbey Storm Sewer
00 ENG RR LI
Na
100,000
2,179,000
993,000
3,272,000
ENG: Sawyer Creek Watershed Detention Basin
00 ENG SAWYR
n/a
1,500,000
300,000
5,000,000
6,800,000
ENG: Stdngham Watershed Box Culvert -Phase 2
00 ENG STRHM
n/a
400,000
3,980,000
4,380,000
ENG: Vegetation Planting
00 ENG VEGET
n/a
95,000
169,000
264,000
ENG: Westowne Area Detention Basin
00 ENG WSTWN
n/a
800,000
185,000
985,000
Oregon Street Interceptor Sewer
00 OREGON ST
n/a
75,000
75,000
75,000
225,000
Ceape Avenue Reconstruction
21 CEAPEAVE
n/a
883,000
883,000
ENG: Fond du Lac Sanitary Sewer
21 ENG FDL
n/a
50,000
50,000
SW: #100, Zero -Turn Mower
21 SW VEH1
n/a
10,000
10,000
West 9th Avenue Reconstruction
21 WEST 9TH
n/a
1,972,000
1,972,000
WW: Update/Relocation of Dump Site
21 WW DUMP
n/a
1,000,000
1,000,000
Algoma Boulevard Reconstruction
22 ALGOMA
n/a
1,978,500
1,978,500
East Lincoln Avenue Reconstruction
22 E LINCOLN
n/a
460,000
460,000
ENG: Bowen Street Interceptor Sewer
22 ENG BOWEN
n/a
75,000
75,000
Grand Street Reconstruction
22 GRAND ST
n/a
536,000
536,000
Rosalia St. Water Main Replacement/Asphalt Paving
22 ROSALIA
n/a
532,000
532,000
SW: #228, Trailered Water Pump
22 SW VEH1
n/a
49,000
49,000
WW: #970, Pickup Truck
22 WW VEH1
n/a
41,000
41,000
McKinley Street Reconstruction
23 MCKINLEY
n/a
148,000
148,000
ENG: Mockingbird Way Traffic Calming
23 MOCKBIRD
n/a
10,000
10,000
South Main Street Reconstruction
23 S MAIN
n/a
1,506,000
1,506,000
SW: #157, Street Sweeper
23 SW VEH1
n/a
290,000
290,000
West Lincoln Avenue Reconstruction
23 W LINCOLN
n/a
752,000
752,000
Central Street Reconstruction
24 CENTRAL
n/a
570,000
570,000
Cherry Street Reconstruction
24 CHERRY
n/a
1,179,000
1,179,000
Mill Street Reconstruction
24 MILL ST
n/a
497,000
497,000
Waugoo Avenue Reconstruction
24 WAUGOO
n/a
874,000
874,000
Arthur Avenue Reconstruction
25ARTHUR
n/a
319,000
319,000
Bay Shore Drive Reconstruction
25 BAY SHORE
n/a
278,000
278,000
Bowen Street Reconstruction
25 BOWEN ST
n/a
319,000
319,000
Ripon Lane Utility Installation & Asphalt Patching
25 RIPON LN
n/a
96,000
96,000
West 15th Avenue Reconstruction
25 WEST 15TH
n/a
1,446,000
1,446,000
Storm Revenue Bonds Total 6,990,000 10,704,500 9,435,000 7,175,000 7,702,000 42,006,500
Storm Water Utility Fund
Produced Using the Plan -It Capital Planning Sofhvare Page 8 Wednesday, July 1, 2020
Source Project # Priority 2021 2022 2023 2024 2025 Total
ENG: Concrete Pavement Repairs (Annual)
00 CONCRETE
n/a
ENG: Femau Watershed Detention Basin (Hoffmaster)
00 ENG FRNAU
nla
ENG: Mini Storm Sewers/Storm Laterals
00 ENG MINI
nla
ENG: Up -Front Engineering Services
00 ENG SRVCS
n/a
Storm Water Utility Fund Total
TID #14 Cash
CD: Grove Street Infrastructure
00 GRV INFRA
3
TID #14 Cash Total
TID #19 Cash
CD: Industrial Park Signs
21 IND SIGNS
3
TID #19 Cash Total
TID Cash
CD: South Shore & Sawdust Dist Redevelopment Sites 00 SS SD RED 2
TID Cash Total
Trade -In
ENG: #389, 4-Wheel Drive 1/2-Ton Pickup Truck
21 ENG VEH1
n/a
Fire: Replacement of'99 Chevrolet Suburban
21 FIRE VEH2
3
Parks: Replace'01 Ford Workhorse Step Van #401
21 PRKS VEH1
1
Parks: Replace'06 Vermeer BC 1000 XL Chipper#471
21 PRKS VEH2
2
Parks: Replace'07 Ford F-250 #418
21 PRKS VEH3
3
Parks: Replace'89 Topsoil Screener
21 PRKS VEH4
3
SAN: #218, Automated Side -Load Refuse Truck
21 SANI VEH1
n/a
SAN: #217, Automated Side -Load Refuse Truck
21 SANI VEH2
n/a
STR: #67, Tandem -Axle Plow Truck
21 STR VEH1
n/a
STR: #24, Flat Bed Truck
21 STR VEH10
n/a
STR: #104, Concrete Breaker
21 STR VEH11
n/a
STR: #33, 3/4-Ton 4WD Pickup Truck
21 STR VEH2
n/a
STR: #50 Single -Axle Plow Truck
21 STR VEH3
n/a
STR: #140, Motor Grader
21 STR VEH4
n/a
STR: #122, Skid Steer and Router
21 STR VEH5
nla
STR: #262, Walk -Behind Router
21 STR VEH6
n/a
STR: #22, 1-Ton 4WD Pickup Truck
21 STR VEH7
n/a
STR: #68, Tandem -Axle Plow Truck
21 STR VEHB
n/a
WD: #830, 314-Ton CNG Full -Size Van
21 WD VEH1
n/a
WFP: #891, 3/4-Ton U4 Pickup Truck
21 WF VEH1
n/a
WW: #172, Zero-Tum Lawn Mower
21 ININVEH1
n/a
Parks: Replace'07 Dodge Ram 3500 1 Tn #492
22 PRKS VEH1
3
Parks: Replace'12 Toro 7200 Gmdmstr Zero Tm #455
22 PRKS VEH2
2
Parks: Replace'09 Ford F450 #481
22 PRKS VEH3
2
REC: #221, Hook -Lift Roll -Off Container Truck
22 RECY VEH1
nla
REC: #202, 1-Ton 4WD Pickup Truck
22 RECY VEH2
n/a
SAN: #219, Automated-Sideload Refuse Truck
22 SANI VEH1
n/a
SAN: #201, 4WD Supervisor's Pickup Truck
22 SANI VEH2
n/a
STR: #69, Tandem -Axle Plow Truck
22 STR VEH1
n/a
STR: #34, 1-Ton 4WD Crew Cab Pickup Truck
22 STR VEH3
nla
75,000
625,000
90,000
75,000
625,000
90,000
75,000
625,000
90,000
75,000
350,000
625,000
90,000
75,000
625,000
90,000
375,000
350,000
3,125,000
450,000
790,000
790,000
790,000
1,140,000
790,000
4,300,000
200,000
200,000
400,000
200,000
200,000
400,000
20,000
20,000
20,000
20,000
400,000
400,000
400,000
400,000
400,000
2,000,000
400,000
400,000
400,000
400,000
400,000
2,000,000
500
500
500
500
2,500
2,500
2,000
2,000
3,000
3,000
500
500
10,000
10,000
10,000
10,000
15,000
15,000
5,000
5,000
5,000
5,000
2,500
2,500
15,000
15,000
15,000
15,000
7,000
7,000
500
500
2,500
Z500
15,000
15,000
2,000
2,000
3,000
3,000
1,500
1,500
1,000
1,000
3,500
3,500
1,000
1,000
10,000
10,000
3,000
3,000
10,000
10,000
1,000
1,000
15,000
15,000
2,500
Z500
Produced Using the Plan -It Capital Planning Sofhnare Page 9 Wednesday, July 1, 2020
Source Project # Priority 2021 2022 2023 2024 2025 Total
STR: #53, Single -Axle Plow Truck
22 STR VEH4
n/a
15,000
15,000
STR: #106, Rubber -Tire Backhoe
22 STR VEH5
n/a
15,000
15,000
STR: #110, Sidewalk Tractor
22 STR VEH6
n/a
5,000
5,000
STR: #70, Tandem -Axle Plow Truck
22 STR VEH7
n/a
15,000
15,000
STR: #93, Semi -Tractor
22 STR VEH8
n/a
5,000
5,000
STR: #239 and #246, Stainless Tanker Semi -Trailer
22 STR VEH9
n/a
5,000
5,000
SW: #228, Trailered Water Pump
22 SW VEHI
n/a
1,000
1,000
WD: #815, Backhoe/Front End Loader
22 WD VEHI
n/a
15,000
15,000
WD: #819, Mini Dump Truck
22 WD VEH2
n/a
7,000
7,000
WW: #970, Pickup Truck
22 WW VEHI
n/a
4,000
4,000
GS: 3/4 Ton Van (repl #003 '97 GMC)
23 FAC VEH1
1
500
500
Parks: Replace'l1 John Deere Gator#499
23 PRKS VEHI
3
500
500
Parks: Replace'13 Toro 7200 Gmdmstr Zero Tm #454
23 PRKS VEH2
2
3,500
3,500
Parks: Replace'08 Ford F-250 #493
23 PRKS VEH3
3
1,000
1,000
Parks: Replace'09 Chevrolet 3500 HD #486
23 PRKS VEH4
3
1,000
1,000
Parks: Replace'08 Ford Econoline Van #409
23 PRKS VEH5
3
1,000
1,000
Parks: Replace'07 Ford Ranger Ext Cab #417
23 PRKS VEH6
3
500
500
Parks: Replace'08 Ford F-3501 Ton Truck #416
23 PRKS VEH7
4
1,500
1,500
REC: #210, Automated Side -Load Refuse Truck
23 RECY VEH1
n/a
25,000
25,000
SAN: #206, Rear -Load Refuse Truck
23 SANI VEHI
nla
10,000
10,000
STR: #200, Road Saw
23 STR EQP1
n/a
500
500
STR: #71, Tandem -Axle Plow Truck
23 STR VEHI
n/a
15,000
15,000
STR: #40, Single -Axle Area Plow Truck
23 STR VEH2
n/a
15,000
15,000
STR: #26, 1-Ton 4WD Dump Truck
23 STR VEH3
n/a
5,000
5,000
STR: #260, Crack Filler
23 STR VEH4
n/a
5,000
5,000
STR: #264, Tar Kettle Trailer Unit
23 STR VEH5
n/a
1,000
1,000
STR: #32, 3/4-Ton 4WD Pickup Truck
23 STR VEH6
n/a
2,500
Z500
STR: #163, Asphalt Roller
23 STR VEH7
n/a
1,000
1,000
STR: #116, Articulated Loader
23 STR VEH8
n/a
20,000
20,000
STR: #54 and #20, Hook Lift Trucks
23 STR VEH9
n/a
5,000
5,000
SW: #157, Street Sweeper
23 SW VEHI
n/a
5,000
5,000
WD: #801, 3/4-Ton CNG 4x4 Pickup Truck
23 WD VEHI
n/a
3,000
3,000
WD: #821, 3/4-Ton Pickup Truck
23 WD VEH2
n/a
3,000
3,000
ENG: #386, 4-Wheel Drive 1/2-Ton Pickup Truck
24 ENG VEHI
n/a
500
500
Parks: Replace'14 Toro 7200 Gmdmstr Zero Tm #456
24 PRKS VEHI
2
3,500
3,500
Parks: Replace'12 CNG Dump Truck #412
24 PRKS VEH2
n/a
6,000
6,000
Parks: Replace'09 Leaf PickerNacuum #031
24 PRKS VEH3
n/a
500
500
REC: #209, Automated Side -Load Refuse Truck
24 RECY VEH1
n/a
10,000
10,000
SAN: #207, Rear -Load Refuse Truck
24 SANI VEH1
n/a
10,000
10,000
STR: #108, Floor Scrubber
24 STR EQP1
n/a
5,000
5,000
STR: #72, Tandem -Axle Dump Truck
24 STR VEH1
n/a
15,000
15,000
STR: #41, Single -Axle Area Plow Truck
24 STR VEH2
n/a
15,000
15,000
STR: #92, Semi -Tractor
24 STR VEH3
n/a
5,000
5,000
STR: #36, 4WD Single -Axle Truck
24 STR VEH5
n/a
10,000
10,000
STR: #174, Utility Tractor
24 STR VEH6
n/a
10,000
10,000
WD: #835, Replace with Td-Axle Dump Truck
24 WD VEHI
n/a
15,000
15,000
GS: 3/4 Ton Pickup (repl #002'08 Ford)
25 FAC VEH1
3
1,000 1,000
Parks: Replace Enclosed Trailer#428
25 PRKS TRLR
2
1,000 1,000
Parks: Replace'l5 Toro 7200 Gmdmstr Zero Tm #457
25 PRKS VEHI
2
3,500 3,500
Parks: Replace'12 Smithco Athletic Field Grmr P12
25 PRKS VEH2
2
500 500
REC: #111, Articulated Loader
25 RECY VEHI
n/a
20,000 20,000
SAN: #212, Rear -Load Refuse Truck
25 SANI VEHI
nla
10,000 10,000
STR: #73, Tandem -Axle Plow Truck
25 STR VEH1
n/a
15,000 15,000
STR: #44, Single -Axle Area Plow Truck
25 STR VEH3
n/a
15,000 15,000
STR: #172, 114" Snow Blower
25 STR VEH4
n/a
5,000 5,000
Produced Using the Plan -It Capital Planning Sofhoare
Page 10
Wednesday, July 1, 2020
Source Project # Priority 2021 2022 2023 2024 2025 Total
STR: #117, Articulated Loader
25 STR VEH5
n/a
20,000
20,000
STR: #168, Paver
25 STR VEH6
n/a
10,000
10,000
STR: #240, Tandem -Axle Equipment Trailer
25 STR VEH7
Na
1,000
1,000
STR: #37, Supervisor's Pickup Truck
25 STR VEH8
n/a
2,500
Z500
SW: #159, Street Sweeper
25 SWVEH1
n/a
10,000
10,000
Parks: Replace'14 Skag Zero Turn Mower#1
25 TRN MOINR1
2
500
500
Parks: Replace'14 Skag Zero Turn Mower#2
25 TRN MOWR2
2
500
500
Parks: Replace'l4 Skag Zero Turn Mower#3
25 TRN MOWR3
2
500
500
Parks: Replace'14 Skag Zero Turn Mower #4
25 TRN MOWR4
2
500
500
WD: #809, Trailer -Mounted Dewatering Pump
25 WD VEH1
n/a
5,000
5,000
WD: #829, 3/4-Ton Van
25 WD VEH2
n/a
2,000
2,000
WD: #817, Mini Dump Truck
25 WD VEH3
nla
7,000
7,000
WD: #827, 3/4-Ton Pickup Truck
25 WD VEH4
n/a
3,000
3,000
WIN: #173, Zero -Turn Lawn Mower
25 WIN VEH1
n/a
850
850
Trade -In Total
73,000 175,000 129,500 105,500 134,350
617,350
Transit Fund
TR: Transit Stop Improvements
00 TR STP IM
3
10,000 10,000 10,000 10,000 10,000
50,000
Transit Fund Total
10,000 10,000 10,000 10,000 10,000
50,000
Water Revenue Bonds
ENG: Asphalt Program (Annual)
00 ASPHALT
n/a
50,000 50,000 50,000
150,000
ENG: Bradley Street Asphalt Paving
00 BRADLEY
n/a
35,000
35,000
WD: Heated Storage Building
00 WD ST BDG
n/a
90,000 350,000
440,000
WFP: Repl Granulated Activated Carbon Filter Media
00 WF GAC FT
n/a
300,000 3,145,000
3,445,000
WFP: 36" Intake Miller's Bay Bypass
00 WF M BAY
n/a
300,000 2,000,000
2,300,000
WFP: Dual Media Filter Repairs/Replacements
00WFMEDIA
n/a
1,200,000 1,200,000
2,400,000
WFP: Chloramine System/Repl Booster Station Pumps
00 WF PUMP
n/a
135,000 2,000,000
2,135,000
Ceape Avenue Reconstruction
21 CEAPEAVE
n/a
1,556,400
1,556,400
ENG: Fond du Lac Sanitary Sewer
21 ENG FDL
n/a
100,000
100,000
ENG: Knapp Street Area Water Main Replacements
21 ENG KNAPP
n/a
3,709,600
3,709,600
West 9th Avenue Reconstruction
21 WEST 9TH
n/a
53,900
53,900
Algoma Boulevard Reconstruction
22 ALGOMA
Na
1,722,700
1,722,700
East Lincoln Avenue Reconstruction
22 E LINCOLN
Na
891,400
891,400
Grand Street Reconstruction
22 GRAND ST
nla
488,800
488,800
Rosalia St. Water Main Replacement/Asphalt Paving
22 ROSALIA
n/a
1,479,700
1,479, 700
WD: #815, Backhoe/Front End Loader
22 WD VEH1
n/a
135,000
135,000
WD: #819, Mini Dump Truck
22 WD VEH2
n/a
78,000
78,000
WFP: Water Filtration Plant Membrane Roof Repl.
22 WF ROOF
n/a
225,000
225,000
McKinley Street Reconstruction
23 MCKINLEY
Na
331,600
331,600
South Main Street Reconstruction
23 S MAIN
n/a
2,041,700
2,041,700
West Lincoln Avenue Reconstruction
23 WLINCOLN
n/a
773,900
773,900
WD: #801, 3/4-Ton CNG 44 Pickup Truck
23 WD VEH1
n/a
46,000
46,000
WD: #821, 3/4-Ton Pickup Truck
23 WD VEH2
n/a
57,000
57,000
WFP: Replace Low -Lift Pumps and Related Equipment
23 WF LL PMP
n/a
1,271,000
1,271,000
Central Street Reconstruction
24 CENTRAL
n/a
918,700
918,700
Cherry Street Reconstruction
24 CHERRY
n/a
1,436,500
1,436,500
Mill Street Reconstruction
24 MILL ST
n/a
123,700
123,700
Waugoo Avenue Reconstruction
24 WAUGOO
n/a
1,405,400
1,405,400
WD: #835, Replace with Tri-Axle Dump Truck
24 WD VEH1
n/a
190,000
190,000
WFP: Replace Floor Cleaner
24 WF F CLNR
n/a
20,000
20,000
Arthur Avenue Reconstruction
25ARTHUR
n/a
589,400
589,400
Produced Using the Plan -It Capital Planning Sofhvare Page 1 I Wednesday, Judy 1, 2020
Source Project # Priority 2021 2022 2023 2024 2025 Total
Bay Shore Drive Reconstruction
25 BAY SHORE
nla
494,600
494,600
Bowen Street Reconstruction
25 BOWEN ST
nla
620,500
620,500
Ripon Lane Utility Installation & Asphalt Patching
25 RIPON LN
nla
176,000
176,000
WD: #809, Trailer -Mounted Dewatering Pump
25 WD VEH1
n/a
45,000
45,000
WD: #829, 3/4-Ton Van
25 WD VEH2
nla
38,000
38,000
WD: #817, Mini Dump Truck
25 WD VEH3
nla
78,000
78,000
WD: #827, 3/4-Ton Pickup Truck
25 WD VEH4
nla
57,000
57,000
West 15th Avenue Reconstruction
25 WEST 15TH
nla
1,364,800
1,364,800
WFP: Ammonia Gas Scrubber
25 WFA SCBR
nla
451,000
451,000
WFP: Chlorine Gas Scrubber
25 WF C SCBR
n/a
383,000
383,000
WFP: Replace SCADA Computers
25 WF SCADA
n/a
20,000
20,000
Water Revenue Bonds Total
5,809,900
7,405,600
5,771,200 5,779,300
9,512,300
34,278,300
Water Utility Fund
ENG: Concrete Pavement Repairs (Annual)
00 CONCRETE
n/a
15,000
15,000
15,000 15,000
15,000
75,000
ENG: Misc. Utility -Owned Lead Service Repl.
00 ENG LEAD
n/a
100,000
100,000
100,000 100,000
100,000
500,000
ENG: Up -Front Engineering Services
00 ENG SRVCS
nla
50,000
50,000
50,000 50,000
50,000
250,000
WFP: Re -Paint Femau Water Tower and Add Mixing
00 WF FER TW
nla
75,000
1,125,000
1,200,000
WFP: Dual Media Filter Repairs/Replacements
00 WF MEDIA
nla
65,000
65,000
WD: #830, 3/4-Ton CNG Full -Size Van
21 WD VEH1
n/a
42,000
42,000
WD: New Step Service Van
21 WD VEH2
n/a
150,000
150,000
WFP: #891, 3/4-Ton 44 Pickup Truck
21 WF VEH1
nla
47,000
47,000
WFP: Re -Paint Washburn Water Tower and Add Mixing
21 WF WSH TW
nla
1,100,000
1,100,000
Water Utility Fund Total
1,429,000
1,505,000
165,000 165,000
165,000
3,429,000
GRAND TOTAL 64,511,300 72,223,370 68,719,720 43,546,684 42,030,058 291,031,132
Produced Using the Plan -It Capital Planning Sofhvare Page 12 Wednesday, July 1, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 BKE N PED
Project Name CD: Bicycle and Pedestrian Infrastructure
Type
Infrastructure - New
Useful Life
10 years
Category
7218 - Road improvements
CTP Proj. Score:
90/200
PASER Rating:
n/a
Data in Year 2021
Department 202 - Community Development
Contact Community Development Direct
Priority 3Important
Division Code 0740
Status Active
Description I Total Project Cost: $250,000
Bike and Pedestrian Infrastructure. Provide designated funds for bicycle and pedestrian infrastructure improvements. Primary improvements will be
bicycle lane stripping and symbol, sharrow installation and bike facility signage for existing and future routes. Funding will allow up to 5 miles
worth of bicycle facilities to be installed annually. With 20 miles of priority bicycle routes yet to be installed, additional funding will complete the
priority facilities in 4 years with additional funding used to install the complete bicycle facility system plan. Route installation will be concurrent
with annual road reconstruction projects and 2019 Bicycle and Pedestrain Master Plan. Designated Funds will be broken into two sections:
Suns—$13,500 and Lane Strinpiniz and/or Symbol—$36,500
Justification
With the completion of the Tribal/WIOUWASH Trial over Lake Butte Des Morts, the ongoing Riverwalk developments and increases in
alternative transportation, we are experiencing an increase in bicycle users that do not have safe designated facilities. With an annual allocation of
fitnds, the City will be able to provide a safe interconnected system of bicycle routes that will connect our key development locations, Riverwalk,
parks, schools and commercial centers. The placement of designated facilities will be consistent with our City of Oshkosh 2018 Comprehensive
Plan, 2019 Bicycle and Pedestrian Master Plan, our continued emphasis on road reconstruction and Riverwalk expansion. Maintenance will be
consistent with our existintz road stripiniz maintenance schedule and situ replacement w711 be on an as needed basis.
Budget Tmpact/Other
Expenditures
2021
2022
2023
2024
2025
Total
Traffic
50,000
50,000
50,000
50,000
50,000
250,000
Funding Sources
Total 50,000
2021
50,000
2022
50,000
2023
50,000
2024
50,000
2025
250,000
Total
Levy
50,000
50,000
50,000
50,000
50,000
250,000
Total 50,000
50,000
50,000
50,000
50,000
250,000
Produced Using the Plena -It Capita[ Planning Software Page 1 Thursday, July Q 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 BLGT REM 1
Project Name CD: Blight Removal Scattered Sites
Data in Year 2021
Type Other Department 202 - Community Development
Useful Life >50 years Contact Community Development Direct
Category 7216 - Land Tmprovements Priority 2 Very Important
CTP Proj. Score: 90/200 Division Code 0740
PASER Rating: n/a
Status Active
Description Total Project Cost: $2,000,000
Blight Removal Scattered Sites. Acquisition, demolition, and remediation with WDNR permitting/site closure. Oshkosh Avenue/Sawyer is one
location planned, funding was used for Buckstaff demo in 2017-2018. These sites would then be resold for private development.
Justification
Implementation of the Healthy Neighborhoods through Acquisition/Demolition. Redevelopment of the sites could include commercial and
residential infill projects. Collaboration with local housing providers such as GO-HNI, Habitat for Humanity and Oshkosh Housing Authority.
Budget Trupact/Other
Expenditures
2021
2022
2023
2024
2025
Total
Planning
250,000
250,000
500,000
500,000
500,000
2,000,000
Funding Sources
Total 250,000
2021
250,000
2022
500,000
2023
500,000
2024
500,000
2025
2,000,000
Total
Levy
250,000
250,000
500,000
500,000
500,000
2,000,000
Total 250,000
250,000
500,000
500,000
500,000
2,000,000
Produced Using the Plena -It Capita[ Planning Software Page 2 Thursday, July Q 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Data in Year 2021
Project # 00 BLGT REM21 I—ltllj I 1 bIl�k!
Project name CD: Gateway Blight Elimination I,- ,I
Type Other Department 202 - Community Development —
Useful Life >50 years Contact Community Development Direct
Category 7216 - Land Tmprovements Priority 2 Very Important
CTP Proj. Score: 65/200 Division Code 0740
i II
PASER Rating: n/a-
Status Active
Description Total Project Cost: $1,250,000
Gateway Blight Elimination. Acquisition and demolition of blighted structures along corridors to the City which include South Park Avenue and
9th Avenue.
Justification
Blight removal is necessary to improve the appearance of these gateway corridors. South Park Avenue, 9th Avenue Corridor Plans and Imagine
Oshkosh indicate blight removal is necessary to improve the gateway corridors.
Budget Trupact/Other
Redevelopment will require private investment and some public incentives
Expenditures
2021
2022
2023
2024
2025
Total
Planning
250,000
250,000
250,000
250,000
250,000
1,250,000
Total
Funding Sources
250,000
2021
250,000
2022
250,000
2023
250,000
2024
250,000
2025
1,250,000
Total
Debt: State Trust Fund Loan
250,000
250,000
250,000
250,000
250,000
1,250,000
Total
250,000
250,000
250,000
250,000
250,000
1,250,000
Produced Using the Plena -It Capita[ Planning Software Page 3 Thursday, July Q 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 G NHOODS
Project Name CD: Great Neighborhoods Initiative
Data in Year 2021
Type Other Department 202 - Community Development
Useful Life >50 years Contact Community Development Direct
Category 7216 - Land Tmprovements Priority 2 Very Important
CTP Proj. Score: 95/200 Division Code 0740
PASER Rating:
Status Active
Description Total Project Cost: $1,050,000
Great Neighborhoods Initiative. Construct or plan neighborhood improvements that support the Healthy Neighborhood Initiative in concert with
Neighborhood Associations and neighborhood improvement partners. Projects are located in the right-of-way or on public property and include
streetscape improvements and signage, pedestrian and bicycle safety improvements, park improvements, safe routes to school improvements, and
others identified and approved by the Common Council. $25,000 Taking Root Program per year
Justification
Implementation of the Healthy Neighborhoods Initiative, the City's Community Development Block Grant Program goals, the Housing Element of
the 2018 Comprehensive Plan, and the City Strategic Plan regarding redevelopment and revitalization of the existing residential neighborhoods.
Budget Tmpact/Other
Neighborhood Fundraising, Oshkosh Area Community Foundation fundraising and other public sources including Oshkosh Area School District
leveraged by Great Neighborhood Funding,
Expenditures
2021
2022
2023
2024
2025
Total
Planning
175,000
175,000
200,000
250,000
250,000
1,050,000
Funding Sources
Total 175,000
2021
175,000
2022
200,000
2023
250,000
2024
250,000
2025
1,050,000
Total
Levy
175,000
175,000
200,000
250,000
250,000
1,050,000
Total 175,000
175,000
200,000
250,000
250,000
1,050,000
Produced Using the Plena -It Capita[ Planning Software Page 4 Thursday, July Q 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Itoject * 00 GATE IMPR
'rojectName CD: Gateway Improvements
Type Infrastructure - Upkeep
Useful Life >50 years
Category 7218 - Road improvements
CTP Proj. Score: 100/200
PASER Rating: n/a
Data in Year 2021
I4`-
71
Status Active
Description Total Project Cost: $1,000,000
Gateway improvements identified in Corridor Plans for 9th Avenue and South Park Avenue that include: Streetscape improvements such as street
markings/crossings, lighting signage, removing or undergrounding overhead utilities, landscaping and other right of way improvements.
Department 202 - Community Development
Contact Community Development Direct
Priority 2 Very Important
Division Code 0740
Justification
Visitors to the Central City would use one of these gateway corridors and public input and comments support improvements to the appearance of
these gateway corridors
Budget Tmpact/Other
Expenditures 2021 2022 2023 2024 2025 Total Future
Planning 50,000 50,000 100,000 100,000 200,000 500,000 500,000
Total 50,000 50,000 100,000 100,000 200,000 500,000 Total
Funding Sources 2021 2022 2023 2024 2025 Total Future
Levy 50,000 50,000 100,000 100,000 200,000 500,000 500,000
Total 50,000 50,000 100,000 1005000 200,000 500,000 Total
Produced Using the Plena -It Capita[ Planning Software Page 5 Thursday, July Q 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 GRV INFRA
Project Name CD: Grove Street Infrastructure
Data in Year 2021
Type Other Department 202 - Community Development
Useful Life >50 years Contact Community Development Direct
Category 7216 - Land Tmprovements Priority 3 Important
CTP Proj. Score: 110/200 Division Code 0740!
PASER Rating: n/a
Status Active
Description Total Project Cost: $400,000
Grove Street Infrastructure. This is a portion of the former Mercy Medical Center site. This block frontage along Grove Street was never
redeveloped by the developer who acquired the site. The City acquired this block from Winnebago County due to foreclosure. The City believes
some or all of the foundations from the former residential/commercial structures may remain under some or all of the property.
Justification
Assist developer with site preparation costs -- storm water management, site preparation / environmental issues. Reimburse developer for eligible
site preparation costs for construction of single family homes and/or twindos.
Budget Tmpact/Other
Redevelopment potential for the site will be enhanced and the property will go from tax exempt to taxable. Parcels to be created will potentially be
owned by developer and then sold to eligible homeowners.
Expenditures
2021
2022 2023
2024 2025 Total
Planning
200,000
200,000
400,000
Funding Sources
Total 200,000
2021
200,000
2022 2023
4003000
2024 2025 Total
TID #14 Cash
200,000
200,000
400,000
Total 200,000
200,000
400,000
Produced Using the Plena -It Capita[ Planning Software Page 6 Thursday, July Q 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 RW SIGNS
Project Name CD: Riverwalk Signage and Banners
Data in Year 2021
Type Asset - New Department 202 - Community Development
Useful Life 10 years Contact Community Development Direct
Category 7216 - Land Tmprovements Priority 3 Important
CTP Proj. Score: 70/200 Division Code 0740
PASER Rating: n/a
Status Active
Description Total Project Cost: $200,000
Purchase and install riverwalk signage and banners, way -finding signage, kiosks, and signs bearing park regulations.
Document/Study/Planning Document: Riverwalk Corridor Design Guidelines
Justification
The Fox River Corridor Riverwalk Plan identified the general design and location of wayfinding signs and kiosks in the riverwalk area. The sign
will direct travelers and boaters to the various businesses and points of interst along the riverwalk.
Budget Tmpact/Other
The City is working with the CVB in developing and placing the signs. The City will be collaborating with the CVB for future years signs and
funding. The City is applying for $25,000 for funding from the CVB in the first year. The City's share could then be reduced to $25,000 for a toal
budget of $50,000.
Expenditures 2021 2022 2023 2024 2025 Total
Other 25,000 25,000 50,000 50,000 50,000 200,000
Total 25,000
Funding Sources 2021
25,000
2022
50,000
2023
50,000
2024
50,000
2025
200,000
Total
Levy 25,000
25,000
50,000
50,000
50,000
200,000
Total 25,000
25,000
50,000
50,000
505000
200,000
Produced Using the Plena -It Capita[ Planning Software Page 7 Thursday, July Q 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 S MAIN AQ
Project name CD: South Main Acquisition
Data in Year 2021
Type Other Department 202 - Community Development
Useful Life >50 years Contact Community Development Direct I
Category 7216 - Land Tmprovements Priority 1 Critical
CTP Proj. Score: 75/200 Division Code 0740
PASER Rating:
Status Active �
Description Total Project Cost: $1,000,000
South Main Acquisitions. Land acquisition, demolition, and remediation of properties along the east side of S. Main Street
Justification
Critical for S. Main St reconstruction in 2023.
i op
Budget Tmpact/Other
RDA owned parcels along the corridor would have a higher likelihood for redevelopment. Other privately owned parcels such as Pioneer Island,
Sadoff and others would have a higher likelihood of redevelopment too.
Expenditures 2021 2022 2023 2024 2025 Total
Planning 250,000
500,000
250,000
1,000,000
Total 250,000
500,000
250,000
1,000,000
Funding Sources 2021
2022
2023 2024
2025 Total
Debt 250,000 500,000 250,000 1,000,000
Total 250,000 500,000 250,000 1,000,000
Produced Using the Plena -It Capita[ Planning Software Page 8 Thursday, July Q 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Data in Year 2021
Project * 00 SS SD RED
Project Name CD: South Shore & Sawdust Dist Redevelopment Sites
Type Other Department 202- Community Development - --
�� � .1
Useful Life >50 years Contact Community Development Direct
Category 7216 - Land Tmprovements Priority 2 Very Important
CTP Proj. Score: 60/200 Division Code 0740
PASER Rating: n/a
Status Active
Description Total Project Cost: $2,000,000
South Shore and Sawdust District Redevelopment Sites. Land acquisition, demolition, and remediation of multiple sites in the South Shore
Redevelopment Area including but not limited to blighted industrial, commercial and residential sites. Examples: Pioneer Drive, Miles Kimball
Site, Boatworks upland sites, Central City Investment Strategy- Southshore redevelopment recommendations such as the Sawdust District.
Justification
Implementation of the river walk plan, redevelopment of the south shore as part of the south shore redevelopment area, and TIF Plan #20 for the
redevelopment and revitalization of the south shore of the Fox River. Departernnt of Public Works demolishes buildings when possible to reduce
cost.
Budget Tmpact/Other
Expenditures
2021
2022
2023
2024
2025
Total
Planning
400,000
400,000
400,000
400,000
400,000
2,000,000
Funding Sources
Total 400,000
2021
400,000
2022
400,000
2023
400,000
2024
400,000
2025
2,000,000
Total
TID Cash
400,000
400,000
400,000
400,000
400,000
2,000,000
Total 400,000
400,000
400,000
400,000
400,000
2,000,000
Produced Using the Plena -It Capita[ Planning Software Page 9 Thursday, July Q 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 IND SIGNS
Project Name CD: Industrial Park Signs
Data in Year 2021
Type
Other
Department 202 - Community Development
Useful Life
>50 years
Contact Community Development Direct
Category
6401 -Contractual Services
Priority 3Important
CTP Proj. Score:
55/200
Division Code 0740
PASER Rating:
n/a
Status Active
Description
Total Project Cost: $40,000
Permanent and temporary signs to identify and market the existing City owned industrial and business parks
Justification
Signs have proven to assist in land marketing and sales for City industrial and business parks.
Budget Tmpact/Other
Attracts more private investment, highlighting; Transload facility, Aviation Business Park, Northwest Industrial Park, Southwest Industrial Park,
Universal Business Park and gateways to the City. TIF funds available for some sites.
Expenditures 2021 2022 2023 2024 2025 Total
Other 40,000 40,000
Total 40,000 40,000
Funding Sources 2021 2022 2023 2024 2025 Total
Levy 20,000 20,000
TID #19 Cash 20,000 20,000
Total 40,000 40,000
Produced Using the Plan -It Capital Planning Software Page 10 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Data in Year 2021
Project# 21 JSC PHI
Project Name CD: Jackson St Corridor SftyStdy ImplementationPH1
Type
Infrastructure - Replacement
Useful Life
25 years
Category
7218 - Road improvements
CTP Proj. Score:
80/200
PASER Rating:
Department 202 - Community Development
Contact Community Development Direct
Priority 2 Very Important
Division Code 0740
Status Active
Description Total Project Cost: $60,000
Jackson Street Corridor Safety Study Implementation. Based on the study completed in 2020, this project is implementing Phase 1 of reccomended
improvements to reduce speeding and increase safety along the Jackson Street corridor. The project cost includes the installation of overhead
support sign structure and dynamic speed feedback sign.
Justification
Engineering and Planning Consultants worked closely with city staff and community groups to analyze and understand unique traffic and
pedestrian needs along the Jackson Corridor. FHWA makes a general statement that speed feedback signs have been effective at reducing speeds
by 3 to 5 mph. More specifically, they have a number of urban studies that found average speeds were reduced between 1 mph and 7 mph and 85th
percentile speeds were reduced between 2 mph and 6 mph, depending on the location of the study.
Budget Tmpact/Other
Expenditures
2021 2022
2023 2024 2025 Total
Traffic
60,000
60,000
Total 60,000
60,000
Funding Sources
2021 2022
2023 2024 2025 Total
Debt
60,000
60,000
Total 60,000
60,000
Produced Using the Plena -It Capita[ Planning Software Page 11 Thursday, July Q 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 MM TRL RB
Project Name CD: Multimodal Trail Rainbow Park
Data in Year 2021
Type
Infrastructure - New
Department 202 - Community Development
}�3r
Useful Life
50 years
Contact Community Development Direct't�`:
Category
7216 - Land Tmprovements
Priority 2 Very Important
7�
CTP Proj. Score:
120/200
Division Code 0740
PASER Rating:
Status Active
Description
Total Project Cost: $585,300
Construct a multimodal trail through Rainbow Park connecting Oshkosh Avenue to the City's rivet -walk west to the Tribal Heritage Crossing Trail
and the Lakeshore Trail.
Justification
The multimodal trail through Rainbow Park will create a looped local trail system that will help connect with the regional Wiouwash Trail system
and Sawyer Street bike lanes.
Budget Trnpact/Other
City has been awarded a grant from the Department of Transporation and the actual match will be closer to 45/55 based on recent riverwalk
construction costs.
Expenditures 2021 2022 2023 2024 2025 Total
Improvements 585,300 585,300
Total 585,300 585,300
Funding Sources 2021 2022 2023 2024 2025 Total
Debt 330,000 330,000
Grant 255,300 255,300
Total 585,300 585,300
Produced Using the Plena -It Capita[ Planning Software Page 12 Thursday, July Q 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Data in Year 2021
Project * 21 RW CONST 1
Project Name CD: Riverwalk Construction S. Main St to RR Tracks
Type hit astructure - New Department 202 - Community Development
Useful Life 50 years Contact Community Development Direct
Category 7216 - Land Tmprovements Priority 1 Critical
CTP Proj. Score: 100/200 Division Code 0740
PASER Rating:
Status Active k _.
Description Total Project Cost: $1,100,000
Riverwalk Construction S. Main St to Railroad Tracks. Build river walk and associated infrastructure necessary for the installation of the trail
including, but not limited to, river walk concrete, boardwalk, dredging, bank stabilization, seawall reconstruction, lighting installation, benches,
and signage. CONSTRUCTION GRANT 2021 ($500,000)
Justification
Project is part of South Shore Redevelopment District Plan and the adopted Riverwalk Plan that calls for development of a rivertront trail on the
south side of the Fox River. Development of a riverfront trail east of S. Main and the removal of street improvements in this area will necessitate
another means of ingress/egress to the Pioneer area east of the railroad tracks, and the extension of E. 9th Avenue will provide for this means of
access. The extension of E. 9th Avenue will also enhance opportunities for new development in areas along the E. 9th Avenue corridor and the
adiacent areas.
Budget Tmpact/Other
Expenditures
Improvements
2021 2022 2023 2024 2025 Total
1,100,000 1,100,000
Total 1,100,000 1,100,000
Funding Sources 2021 2022 2023 2024 2025 Total
Debt 600,000 600,000
Grant 500,000 500,000
Total 1,100,000 1,100,000
Produced Using the Plan -It Capital Planning Software Page 13 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 SANI DEMO
Project Name CD: Former Sanitation Garage Demo
Data in Year 2021
Type Other Department 202 - Community Development
Useful Life >50 years Contact Community Development Direct
Category 7216 - Land Tmprovements Priority 3 Important
CTP Proj. Score: 55/200 Division Code 0740
PASER Rating:
Status Active _
Description Total Project Cost: $200,000
Former Sanitation Garage Demo. 4th Avenue and Michigan Street former City Sanitation Building. Specs, asbestos, demo, and oversight
Justification
Redevelopment of South Shore as part of the south shore redevelopment area and TIF Plan #20 for the redevelopment and revitalization of the
south shore of the Fox River.
Budget Tmpact/Other
The property is adjacent to Boatworks Property available for redevelopment. Redevelopment potential for the site will be enhanced and the
property will go from tax exempt to taxable; owned by a private entity.
Expenditures 2021 2022 2023 2024 2025 Total
Planning 200,000 200,000
Total 200,000 200,000
Funding Sources 2021 2022 2023 2024 2025 Total
Debt 200,000 200,000
Total 200,000 200,000
Produced Using the Plan -It Capital Planning Software Page 14 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 SANI VEH 1
Project Name SAN: #218, Automated Side -Load Refuse Truck
Data in Year 2021
Type
Equipment
Department 212 -Sanitation
Useful Life
10 years
Contact Public Works Director
Category
7210 - Vehicles
Priority n/a
CTP Proj. Score:
n/a
Division Code 0470
PASER Rating:
n/a
Status Active
Description
Total Project Cost: $300,000
This will replace 4218, a 2013 Labrie automated side -load refuse truck
Justification
It has 64,783 miles on it. The dash recently quit working on this unit. The arm chains have no more adjustment and they need to be changed. The
hopper, packer, and gripper are showing signs of wear.
Budget Tmpact/Other
Expenditures 2021 2022 2023 2024 2025 Total
EquipmentNehicles 300,000 300,000
Total 300,000 300,000
Funding Sources 2021 2022 2023 2024 2025 Total
Debt: State Trust Fund Loan 290,000 290,000
Trade -In 10,000 10,000
Total 300,000 300,000
Produced Using the Plena -It Capita[ Planning Software Page 15 Thursday, July Q 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 SANI VEH2
Project Name SAN: #217, Automated Side -Load Refuse Truck
Data in Year 2021
Type
Equipment
Department 212 -Sanitation
Useful Life
10 years
Contact Public Works Director
Category
7210 - Vehicles
Priority n/a
CTP Proj. Score:
n/a
Division Code 0470
PASER Rating:
n/a
Status Active
Description
Total Project Cost: $300,000
This will replace 4217, a 2013 Labrie automated side -load refuse truck
Justification
It has 52,554 miles on it. The speedometer recently quit on this unit. The hopper, packer, and gripper are showing signs of wear.
Budget Tmpact/Other
Expenditures 2021 2022 2023 2024 2025 Total
EquipmentNehicles 300,000 300,000
Total 300,000 300,000
Funding Sources 2021 2022 2023 2024 2025 Total
Debt: State Trust Fund Loan 290,000 290,000
Trade -In 10,000 10,000
Total 300,000 300,000
Produced Using the Plan -It Capital Planning Software Page 16 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Data in Year 2021
Project * 21 PD RENO
Project name Police: Renovations to Vacant Ofc Space North End
Type
Other
Department 215 -Police
Useful Life
15 years
Contact Police Chief
Category
7214 - Buildings
Priority 2 Very Important
CTP Proj. Score:
75/200
Division Code 0211
PASER Rating:
Status Active
Description
Total Project Cost: $150,000
Renovations to vacant office space in the north end of Safety Building
Justification
k
Renovation of the vacant space is necessary to accommodate expansion of the Administrative Bureau (Professional Standards and Support Services
Divisions). This will improve our workflow efficiency and customer service. Preliminary work has already been done by Facilities Maintenance
and Electrical Divisions, and furniture has been procured for the new offices.
Budget Tmpact/Other
$150,000
Expenditures
2021 2022
2023 2024 2025 Total
Improvements
150,000
150,000
Funding Sources
Total 150,000
2021 2022
150,000
2023 2024 2025 Total
Debt
150,000
150,000
Total 150,000
150,000
Produced Using the Plan -It Capital Planning Software Page 17 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 PD SWT TR
Project name Police: SWAT Team Truck Replacement
Type Asset - Replacement Department 215 - Police
Useful Life 20 years Contact Police Chief
Category 7210 - Vehicles Priority 1 Critical
CTP Proj. Score: n/a Division Code 0211
PASER Rating:
Data in Year 2021
Status Active
Description Total Project Cost: $200,000
SWAT Team Truck Replacement: The current SWAT Truck is a 1997 and is 23 years old and now requires more maintenance/repairs.
Justification
The SWAT team uses this vehicle as the primary means of transporting equipment and personnel to the scenes of SWAT operations. SWAT
personnel also operate out of this vehicle from the command post near incident scenes. The SWAT team conducts operation planning and staging
from the SWAT Truck. The SWAT Team stores numerous equipment items that must be easily and quickly accessible during emergency situations
in the SWAT Truck. The SWAT Team Truck was originally purchased in 1996 from LDV Custom Specialty Vehicles (formally Lynch Trucking).
The truck was up fitted with storage compartments and seating by members of the Oshkosh Police Department after the purchase. Over the past
several years the SWAT Team Truck has required numerous repairs and has been towed in for service several times. These repairs are likely a
result of the age of the vehicle and it is probable that the vehicle will continue to require frequent repair and be unreliable in emergency situations.
We have requested this item over the last several years and the need continues.
Budget Impact/Other
$200,000
Expenditures
2021 2022
2023 2024 2025 Total
EquipmentNehicles
200,000
200,000
Funding Sources
Total 200,000
2021 2022
200,000
2023 2024 2025 Total
Debt
200,000
200,000
Total 200,000
200,000
Produced Using the Plena -It Capita[ Planning Software Page 18 Thursday, July Q 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 FIRE GEAR
Project Name Fire: Turn Out Gear Pants & Coats
Data in Year 2021
Type Asset - Replacement Department 235 - Fire
Useful Life 10 years Contact Fire Chief
Category 7204 - Machinery & Equip Priority 1 Critical
CTP Proj. Score: Division Code 0230
PASER Rating:
Status Active
Description Total Project Cost: $109,225
Turnout gear is a firefighter's protective clothing that is comprised of three distinct layers: the thermal liner, the moisture barrier & the outer shell.
Each serves specific multiple functions. The thermal liner is the most critical component in turnout gear because it has the biggest impact on
thermal protection & heat stress reduction. This request is for Firefighting Turnout Gear (Globe bunker pants and jacket). We have created a plan
to replace our existing gear based on expiration date. (See attached schedule) https://globe.msasafety.com/Turnout-Gear/c/119?isLanding=true
Justification
NFPA 18.51 Standard on Selection, Care, and Maintenance of Protective Ensembles for Structural Fire Fighting and Proximity Fire Fighting
requires that structural turnout gear shall be retired when the garment is beyond repair and no longer able to pass an NFPA 1851 Advanced
Inspection, or ten years from date of manufacture, whichever comes first.
Budget Tmpact/Other
Expenditures 2021 2022 2023 2024 2025 Total
Other 40,000 32,100 12,800 24,325 109,225
Total 40,000 32,100 12,800 24,325 109,225
Funding Sources 2021 2022 2023 2024 2025 Total
Levy 40,000 32,100 12,800 24,325 109,225
Total 40,000 32,100 12,800 24,325 109,225
Produced Using the Plan -It Capital Planning Software Page 19 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 FIRE HELM
Project Name Fire: Turn Out Gear Helmets
Type Asset - Replacement Department 235 - Fire
Useful Life 10 years Contact Fire Chief
Category 7204 - Machinery & Equip Priority 1 Critical
CTP Proj. Score: Division Code 0230
PASER Rating:
Status Active
Description Total Project Cost: $29,857
Data in Year 2021
Turnout Gear: Bullard Helmets with shields and nametags. See an example: https://www.bullard.com/fire-helmets
Justification
Over time, heat exposure can impact the fire helmet by blistering, bubbling and general degradation. NFPA 1851, Standard on Selection, Care,
and Maintenance of Protective Ensembles for Structural Fire Fighting and Proximity Fire Fighting, requires that structural turnout gear shall be
retired when the garment is beyond repair and no longer able to pass an NFPA 1851 Advanced Inspection, or ten years from date of manufacture,
whichever comes first. The Fire Department has created a plan to replace helmets based on expiration date. (See attached replacement schedule)
Budget Tmpact/Other
Expenditures 2021 2022 2023 2024 2025 Total
EquipmentNehicles 5,000
1,740
4,659
18,458
29,857
Total 5,000
1,740
4,659
18,458
29,857
Funding Sources 2021 2022
2023
2024
2025
Total
Levy 5,000 1,740 4,659 18,458 29,857
Total 5,000 1,740 4,659 18,458 29,857
Produced Using the Plan -It Capital Planning Software Page 20 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 FIRE BTS
Project Name Fire: Turn Out Gear Boots
Type Asset - Replacement Department 235 - Fire
Useful Life 10 years Contact Fire Chief
Category 6401 - Contractual Services Priority 1 Critical
CTP Proj. Score: Division Code 0230
PASER Rating:
Status Active
Description Total Project Cost: $49,500
Data in Year 2021
This request is for Bunker Boots for 108 firefighters. An example of the boot can be found here: https://globc.msasafety.com/arctic-grip-boots
Justification
Our existing boots are a safety issue. They are past service life and do not provide firefighters with other forms of protection. The NFPA 1851
Standard on Selection, Care, & Maintenance of Protective Ensembles for Structural Fire Fighting & Proximity Fire Fighting requires that structural
turnout gear shall be retired when the garment is beyond repair & is no longer able to pass an NFPA 1851 Advanced Inspection, or ten years from
date of manufacture, whichever comes first.
Budget Tmpact/Other
Expenditures
2021 2022
2023 2024 2025 Total
EquipmentNehicles
49,500
49,500
Funding Sources
Total 49,500
2021 2022
49,500
2023 2024 2025 Total
Levy
49,500
49,500
Total 49,500
49,500
Produced Using the Plan -It Capital Planning Software Page 21 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 FIRE VEH 1
Project Name Fire: Replace'94 Ford Expl with 1 Ton pickup
Type
Asset - Replacement
Useful Life
10 years
Category
7210 - Vehicles
CTP Proj. Score:
n/a
PASER Rating:
n/a
Description
Replacement of 1994 Ford Explorer
Department 235 - Fire
Contact Fire Chief
Priority 3Important
Division Code 0230
Status Active
Total Project Cost: $44,300
Data in Year 2021
Justification
The existing vehicle has reached the end of its service life. We will replace it with a pick up truck that will allow for more versatility. A new
vehicle will be able to tow other OFD assets such as rescue boat, trailers of hazardous material, equipment and the rehab trailer. It could also be
used as a response vehicle in inclement weather. Replacing the vehicle in 2020, the cost is estimated at $43,000. Our budget request is assuming a
3% increase in cost each year.
Budget Tmpact/Other
Expenditures
2021 2022
2023 2024 2025 Total
EquipmentNehicles
44,300
44,300
Funding Sources
Total 44,300
2021 2022
44,300
2023 2024 2025 Total
Debt
44,300
44,300
Total 44,300
44,300
Produced Using the Plan -It Capital Planning Software Page 22 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 FIRE VEH2
Project Name Fire: Replacement of'99 Chevrolet Suburban
Data in Year 2021
Type Asset - Replacement Department 235 - Fire
Useful Life 10 years Contact Fire Chief
Category 7210 - Vehicles Priority 3 Important
CTP Proj. Score: n/a Division Code 0230
PASER Rating: n/a
Status Active
Description Total Project Cost: $45,700
The existing vehicle has reached the end of its service life with close to 95,000 miles (as of 3/31/20). We will replace it with a Suburban pick up
truck that will allow for more versatility. A new vehicle will be able to tow other OFD assets such as rescue boat, trailers of hazardous material,
equipment and the rehab trailer. It could also be used as a response vehicle in inclement weather. Replacing the vehicle in 2020, the cost is
estimated at $43,000. Our budget request is assuming a 3% increase in cost each year.
Justification
Replace 1999 Chevrolet Surburban with 4 door, 1 ton Suburban
Budget Tmpact/Other
Expenditures
2021 2022
2023 2024 2025 Total
EquipmentNehicles
45,700
45,700
Funding Sources
Total 45,700
2021 2022
45,700
2023 2024 2025 Total
Debt
Trade -In
45,200
500
45,200
500
Total 45,700
45,700
Produced Using the Plan -It Capital Planning Software Page 23 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 HI VISIB
Project Name Fire: Turn Out Gear Hi -Visibility Jackets
Type Asset - Replacement Department 235 - Fire
Useful Life 10 years Contact Fire Chief
Category 7204 - Machinery & Equip Priority 1 Critical
CTP Proj. Score: Division Code 0230
PASER Rating:
Status Active
Description Total Project Cost: $32,400
Data in Year 2021
Hi -Visibility Jackets https://www.firsttactical.com/products/mens-tactix-high-vis-parka
Justification
In the first quarter of 2020, 15 firefighters nationwide died as a result of being struck by a vehicle during an emergency response. (Source:
SafetyStandDown.org). Every day firefighters respond to a wide variety of calls and when they step off the rig, their lives are at risk. Nothing is
more important in hazardous conditions than visibility. This request is for 108 ANSI/ISEA 107-2010 approved High Visibility Jackets with 3M®
Scotchlite® reflective trims. The jackets are bright and have a reflective seam -sealed outer shell made of nylon/polyester materials. The jacket is
waterproof, breathable, wind repellent and is resistant to bloodborne pathogens.
Budget Tmpact/Other
Expenditures 2021 2022 2023 2024 2025 Total
EquipmentNehicles 32,400 32,400
Total 32,400 32,400
Funding Sources 2021 2022 2023 2024 2025 Total
Prior Year Funding 32,400 32,400
Total 32,400
32,400
Produced Using the Plan -It Capital Planning Software Page 24 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Data in Year 2021
Project * 21 LIB GENER
Project name Library: Replace Emergency Electric Generator Sys
Type
Facility - Upkeep
Department 239 - Library
Useful Life
20 years
Contact Library Director v
Category
7214 - Buildings
Priority 2 Very Important t
CTP Proj. Score:
70/200
Division Code 1060 4k#y. 1
PASER Rating:
n/a
Status Active
Description
Total Project Cost: $40,600
Replace emergency generator system due to obsolescence / maintenance challenges to the Ford diesel motor that powers the system
Justification
Emergency electrical generation is a safety condition for building occupancy.
Budget Tmpact/Other
Expenditures
2021 2022
2023 2024 2025 Total
Improvements
40,600
40,600
Funding Sources
Total 40,600
2021 2022
40,600
2023 2024 2025 Total
Debt
40,600
40,600
Total 40,600
40,600
Produced Using the Plan -It Capital Planning Software Page 25 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 DP ROOTS
Project name Museum: Deep Roots, Growing City Exhibition
Data in Year 2021
Type
Other
Department 241 -Museum
Useful Life
20 years
Contact Muset n Director
Category
7206 - Capital Construction
Priority 2 Vey Important
CTP Proj. Score:
50/200
Division Code 1070
PASER Rating:
Description
Status Active
Total Project Cost: $1,000,000
This request is for the design development phase (planning) of the next long-term exhibition, called Deep Roots, Growing City. The Museum
would continue to engage Split Rock Studios for the design work and undertake media work with staff. This project is part of a comprehensive plan
(2014) to upgrade all exhibitions to meet current standards and thereby create more flexible space within the Museum. Conceptual planning was
funded in 2017 and the design was developed and adopted that year. Deep Roots, Growing City will be located in the 1,355 square foot Sawyer
home gallery. Deep Roots, Growing City is a complex exhibition that will require a full year to develop, as it is intended to attract visitors in many
ways, including through digital interactive components. The exhibition is designed to engage visitors through fun, educational and ADA compliant
interactive digital elements in each theme area. Desiert development will take most of 2021. It is assumed it would open in late 2022.
Justification
This exhibition is the replacement for Memories & Dreams, which is 22 years old and does not work with K-12 curriculum, uses outdated
interpretive techniques, and does not effectively attract or engage visitors. Deep Roots, Growing City continues the storyline from People of the
Waters and uses state of the art techniques, makes connections to the present, represents a more efficient use of space. This exhibition will be the
hi6licht of the Museum's Centennial (2024).
Budget Tmpact/Other
The fabrication cost is estimated at $800,000 and would be shared 75% City/25% Museum. Creation of Deep Roots, Growing City is a requirement
before the multi -purpose gallery can become a reality.
Expenditures 2021 2022 2023 2024 2025 Total
Planning 100,000 100,000 200,000
Improvements 800,000 800,000
Total 100,000 100,000 800,000 1,000,000
Funding Sources 2021 2022 2023 2024 2025 Total
Operations 100,000 100,000 800,000 1,000,000
Total 100,000 100,000 800,000
1,000,000
Produced Using the Plan -It Capital Planning Software Page 26 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 NEW WALKS
Project Name Sidewalks: New Walk Ordered In
Data in Year 2021
Type Infrastructure - New Department 311 - Sidevvatks
Useful Life 10 years Contact Public Works Director
Category 7206 - Capital Construction Priority n/a
CTP Proj. Score: 85/200 Division Code 0410
PASER Rating: n/a
Status Active
Description Total Project Cost: $700,000
This project installs new sidewalk along street segments without sidewalk
Justification
Selection to be coordinated through Bicycle and Pedestrian Advisory Committee.
Budget Tmpact/Other
Expenditures
2021
2022
2023
2024
2025
Total
Future
Sidewalk
70,000
70,000
70,000
70,000
70,000
350,000
350,000
Funding Sources
Total 70,000
2021
70,000
2022
70,000
2023
70,000
2024
70,000
2025
350,000
Total
Total
Future
Assessment
Levy
65,000
5,000
65,000
5,000
65,000
5,000
65,000
5,000
65,000
5,000
325,000
25,000
350,000
Total
Total 70,000
70,000
70,000
70,000
70,000
350,000
Produced Using the Plan -It Capital Planning Software Page 27 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Data in Year 2021
Project * 00 REHAB
Project Name Sidewalks: Rehabilitation & Reconstruction Program
Type
Infrastructure - Replacement
Department 311 - Sidewalks
Useful Life
10 years
Contact Public Works Director
Category
7206 - Capital Construction
Priority n/a
CTP Proj. Score:
90/200
Division Code 0410
PASER Rating:
n/a
Status Active
Description
Total Project Cost: $8,880,000
This program rotates through the City on a 10-year cycle to repair defective sidewalk squares. This program also includes citizen complaint
locations. Handicap ramps are installed at intersections currently without ramps. Program also fixes deteriorated driveway aprons.
Justification
The program cycles through the City on approximately a 10-year cycle.
Budget Tmpact/Other
Expenditures
2021
2022
2023
2024
2025
Total
Future
Sidewalk
888,000
888,000
888,000
888,000
888,000
4,440,000
4,440,000
Funding Sources
Total 888,000
2021
888,000
2022
888,000
2023
888,000
2024
8883000
2025
4,4403000
Total
Total
Future
Assessment
Debt
588,000
300,000
588,000
300,000
588,000
300,000
588,000
300,000
588,000
300,000
2,940,000
1,500,000
4,440,000
Total
Total 888,000
888,000
888,000
888,000
888,000
4,440,000
Produced Using the Plan -It Capital Planning Software Page 28 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 SUBDIVNS
Project Name Sidewalks: Subdivision Agreements
Data in Year 2021
Type Infrastructure - New Department 311 - Sidewalks
Useful Life 10 years Contact Public Works Director
Category 7206 - Capital Construction Priority n/a
CTP Proj. Score: 75/200 Division Code 0410
PASER Rating: n/a
Status Active
Description Total Project Cost: $300,000
This project installs sidewalks at various locations within newer subdivisions
Justification
Sidewalk needs to be installed in subdivisions with vacant lots. This portion will clean up subdivisions that have gaps in the sidewalk.
Budget Tmpact/Other
Expenditures
2021
2022
2023
2024
2025
Total
Future
Sidewalk
30,000
30,000
30,000
30,000
30,000
150,000
150,000
Funding Sources
Total 30,000
2021
30,000
2022
30,000
2023
30,000
2024
30,000
2025
150,000
Total
Total
Future
Assessment
Levy
27,500
2,500
27,500
2,500
27,500
2,500
27,500
2,500
27,500
2,500
137,500
12,500
150,000
Total
Total 30,000
30,000
30,000
30,000
30,000
150,000
Produced Using the Plan -It Capital Planning Software Page 29 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 BRADLEY
Project Name ENG: Bradley Street Asphalt Paving
Data in Year 2021
Type Infrastructure - Replacement Department 315 - Streets
Useful Life 12+ years Contact Public Works Director
Category 7218 - Road improvements Priority n/a
CTP Proj. Score: 80/200 Division Code 0410
PASER Rating: 2
Status Active
Description Total Project Cost: $1,894,400
In 2022, this project will replace proposed length of 2,050' of asphalt paving on Bradley Street, from West 28th Avenue to West Waukau Avenue.
The culvert will be re -installed. A structure will be constructed to cross Gallups-Merritts Creek. In 2021, the culvert will be designed for this
Justification
Age of Infrastructure:
Sanitary - 1966
Water - 1966
Stone - None Present
Street Pavement - 1977
Budget Tmpact/Other
Expenditures
2021
2022 2023
2024 2025 Total
Street
559,400
559,400
Storm
100,000
1,150,000
1,250,000
Wastewater
50,000
50,000
Water
35,000
35,000
Total
100,000
1,794,400
1,894,400
Funding Sources
2021
2022 2023
2024 2025 Total
Assessment
333,400
333,400
Debt
226,000
226,000
Sewer Revenue Bonds
50,000
50,000
Storm Revenue Bonds
100,000
1,150,000
1,250,000
Water Revenue Bonds
35,000
35,000
Total
100,000
1,794,400
1,894,400
Produced Using the Plan -It Capital Planning Software Page 30 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 CONCRETE
Project name ENG: Concrete Pavement Repairs (Annual)
Data in Year 2021
Type
Other
Department 315 -Streets
Useful Life
30+ years
Contact Public Works Director
Category
7218 - Road Tmprovements
Priority n/a
CTP Proj. Score:
75/200
Division Code 0410
PASER Rating:
Varies
Status Active
Description
Total Project Cost: $2,398,000
Spot repairs to deteriorated panels of concrete pavement will be made on various arterial, collector, and local streets. Some work will be done in
coordination with other construction projects, such as the sanitary manhole rehabilitation project.
Justification
Work for areas of pavement that have deteriorated but full reconstruction is not needed at this time.
Budget Tmpact/Other
Expenditures
2021
2022
2023
2024
2025
Total
Future
Street
128,000
125,000
175,000
125,000
125,000
678,000
1,175,000
Storm
75,000
75,000
75,000
75,000
75,000
375,000
Total
Wastewater
15,000
20,000
20,000
20,000
20,000
95,000
Water
15,000
15,000
15,000
15,000
15,000
75,000
Total
233,000
235,000
285,000
235,000
235,000
1,223,000
Funding Sources
2021
2022
2023
2024
2025
Total
Future
Levy
128,000
125,000
175,000
125,000
125,000
678,000
1,175,000
Sewer Utility Fund
15,000
20,000
20,000
20,000
20,000
95,000
Total
Storm Water Utility Fund
75,000
75,000
75,000
75,000
75,000
375,000
Water Utility Fund
15,000
15,000
15,000
15,000
15,000
75,000
Total
233,000
235,000
285,000
235,000
235,000
1,223,000
Produced Using the Plan -It Capital Planning Software Page 31 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 ENG SRVCS
Project Name ENG: Up -Front Engineering Services
Data in Year 2021
Type
Other
Department 315 -Streets
Useful Life
1 year
Contact Public Works Director
Category
7218 - Road improvements
Priority n/a
CTP Proj. Score:
60/200
Division Code 0410
PASER Rating:
n/a
Status Active
Description
Total Project Cost: $1,825,000
Environmental Assessment, Subsurface Exploration, and Storm and Sanitary Sewer Televising services to help in the design of yearly CIP projects
Justification
Work done to assist in the design of CIP projects.
Budget Tmpact/Other
Expenditures
2021
2022
2023
2024
2025
Total
Street
30,000
30,000
30,000
30,000
30,000
150,000
Storm
90,000
90,000
90,000
90,000
90,000
450,000
Wastewater
195,000
195,000
195,000
195,000
195,000
975,000
Water
50,000
50,000
50,000
50,000
50,000
250,000
Total
365,000
365,000
365,000
365,000
365,000
1,825,000
Funding Sources
2021
2022
2023
2024
2025
Total
Levy
30,000
30,000
30,000
30,000
30,000
150,000
Sewer Utility Fund
195,000
195,000
195,000
195,000
195,000
975,000
Storm Water Utility Fund
90,000
90,000
90,000
90,000
90,000
450,000
Water Utility Fund
50,000
50,000
50,000
50,000
50,000
250,000
Total
365,000
365,000
365,000
365,000
365,000
1,825,000
Produced Using the Plan -It Capital Planning Software Page 32 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 OREGON ST
Project Name Oregon Street Interceptor Sewer
Data in Year 2021
Type Infrastructure - New Department 321 - Utility Infrastructure
Useful Life 75-100 years Contact Public Works Director
Category 7206 - Capital Construction Priority n/a
CTP Proj. Score: 130/200 Division Code 0410
PASER Rating: 4, 5, 6
Status Active
Description Total Project Cost: $10,504,200
No
I
In 2021, 2,000' of 36" interceptor sewer will be constructed on Oregon Street, from West 28th Avenue to West Waukau Avenue. In 2022, 2,900'
of 36" interceptor sewer will be constructed on Oregon Street, from West Waukau Avenue to West 35th Avenue. In 2023, 2,700' of 36"
interceptor sewer will be constructed on Oregon Street, from West 35th Avenue to Ripple Avenue. The 2023 portion of the project will be
performed in construction with Winnebago County's reconstruction of CTH I (Oregon Street).
Justification
This interceptor line construction started in 2018 and, once complete, will service development for the Aviation Industrial Park, as well as
additional development at West Ripple Avenue and Oregon Street. Ultimately, this will also serve development along South Washburn Street,
south of West Waukau Avenue.
Age of infrastructure:
Street Pavement - 1975 and 1993
Document/Study/Planning Document: Sanitary Sewer System 2050 Planning Study (2017)
Budget Impact/Other
Expenditures
2021 2022 2023 2024 2025 Total
Street 250,000 250,000
Storm 75,000 75,000 75,000 225,000
Wastewater 2,775,600 3,955,700 3,297,900 10,029,200
Total 3,100,600 4,030,700 3,372,900 10,504,200
Funding Sources 2021 2022 2023 2024 2025 Total
Debt
Sewer Revenue Bonds
Storm Revenue Bonds
250,000
250,000
2,775,600 3,955,700 3,297,900
10,029,200
75,000 75,000 75,000
225,000
Total 3,100,600 4,030,700 3,372,900
10,504,200
Produced Using the Plan -It Capital Planning Software Page 33 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
'roject * 21 CEAPE AVE
Iroject Name Ceape Avenue Reconstruction
Data in Year 2021
Type Infrastructure - Replacement Department 321 - Utility Infrastructure
Useful Life 30+ years Contact Public Works Director
Category 7206 - Capital Construction Priority n/a
CTP Proj. Score: 105/200 Division Code 0410
PASER Rating: 2,4
Status Active
Description Total Project Cost: $6,040,500
Full reconstruction of the street, including public utilities and laterals, from Bowen Street to Lake Street. Proposed 2,510' length of 32' concrete
pavement in 60' right-of-way. Existing storm sewer from Bowen Street to Lake Street will be upsized. Sidewalk sections will be repaired, as
needed. The Bicycle and Pedestrian Mater Plan 2019 recommends bike route signage on this street.
Justification
Age of Infrastructure:
Sanitary - 1936 and 1938
Water - Pre- 1920's
Stone - 1969 and 1978
Street Pavement - 1979
Document/Study/Planning Document: Bicycle and Pedestrian Master Plan 2019 and Water Distribution System Hydraulic Model and Planning
Study (2013)
Budget Impact/Other
Expenditures
2021 2022
2023 2024 2025 Total
Street
1,619,000
1,619,000
Storm
947,000
947,000
Wastewater
1,402,600
1,402,600
Water
1,556,400
1,556,400
Sidewalk
135,500
135,500
Traffic
380,000
380,000
Total
6,040,500
6,040,500
Funding Sources
2021 2022
2023 2024 2025 Total
Assessment
956,800
956,800
Debt
1,530,400
1,530,400
Sewer Revenue Bonds
1,113,900
1,113,900
Storm Revenue Bonds
883,000
883,000
Water Revenue Bonds
1,556,400
1,556,400
Total
6,040,500
6,040,500
Produced Using the Plan -It Capital Planning Software Page 34 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 OMRO RD
Project Name Omro Road Reconstruction
Data in Year 2021
Type Infrastructure - Replacement Department 321 - Utility Infrastructure
Useful Life 30+ years Contact Public Works Director
Category 7206 - Capital Construction Priority n/a
CTP Proj. Score: 90/200 Division Code 0410
PASER Rating: 7
Status Active 1 k4l
Description Total Project Cost: $300,000
The Town of Algoma and the City are working together to perform a full reconstruction and urbanization of the street, including public utilities and
laterals, from Leonard Point Road to Brooks Lane. The City will be sharing the costs with the Town of Algoma for the southern half of the street,
from 200' west of North Westhaven Drive to Brooks Lane. Proposed 1,680' length of 36' concrete pavement in 66' right-of-way. Sidewalk will be
installed. Bicycle and Pedestrian Master Plan 2019 recommends facility.
Justification
Intergovernmental agreement with the Town of Algoma for costs associated with the properties on this road that are in the City
Age of Infrastructure:
Street Pavement - 2001
Document: Bicycle and Pedestrian Master Plan 2019
Budget Tmpact/Other
Expenditures
2021 2022
2023 2024 2025 Total
Street
Sidewalk
256,400
43,600
256,400
43,600
Funding Sources
Total 300,000
2021 2022
300,000
2023 2024 2025 Total
Assessment
Debt
268,600
31,400
268,600
31,400
Total 300,000
300,000
Produced Using the Plan -It Capital Planning Software Page 35 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 WEST 9TH
Project Name West 9th Avenue Reconstruction
Data in Year 2021
Type Infrastructure - Replacement Department 321 - Utility Infrastructure
Useful Life 30+ years Contact Public Works Director
Category 7206 - Capital Construction Priority n/a
CTP Proj. Score: 85/200 Division Code 0410
PASER Rating: 4
x:
i
Status Active
Description Total Project Cost: $7,211,100
This project includes the reconstruction of West 9th Avenue, from Oakwood Road to Linden Oaks Drive. Proposed 3,370' length of 48' concrete
in 80' right-of-way. New storm sewer will be installed and existing storm sewer from South Oakwood Road to Sawyer Creek will be upsized from
42" to 54". Bicycle and Pedestrian Master Plan 2019 recommends bike lanes on this street. Sidewalk will be installed.
Justification
Age of Infrastructure:
Sanitary - 1990 and 1994
Water - 1990 and 1994
Stone - None present and 1992
Street Pavement - 1980
Document/Study/Plamming Document: Bicycle and Pedestrian Master Plan 2019, Southwest Area Sanitary Sewer Study (2002), and Sanitary
Sewer System 2050 Planning Studv
Impact/Other
Expenditures
2021 2022
2023 2024 2025 Total
Street
3,184,700
3,184,700
Storm
2,007,000
2,007,000
Wastewater
1,272,500
1,272,500
Water
64,900
64,900
Sidewalk
182,000
182,000
Traffic
500,000
500,000
Total
7,211,100
7,211,100
Funding Sources
2021 2022
2023 2024 2025 Total
Assessment
993,500
993,500
Debt
3,028,200
3,028,200
Sewer Revenue Bonds
1,163,500
1,163,500
Storm Revenue Bonds
1,972,000
1,972,000
Water Revenue Bonds
53,900
53,900
Total
7,211,100
7,211,100
Produced Using the Plan -It Capital Planning Software Page 36 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 FURN REPL
Project name GS: Office Furniture Replacement
Data in Year 2021
Type Asset - Replacement Department 323 - Gen Building & Equipmen
Useful Life 15 years Contact General Services Manager
Category 7204 - Machinery & Equip Priority 2 Very Important
CTP Proj. Score: n/a Division Code 0130
PASER Rating: n/a
Status Active
Description Total Project Cost: $50,000
General Services coordinates office furniture replacements for all departments except Utilities and OPL. Replacements of office furniture (chairs,
tables, workstations, file cabinets, etc.) are based on wear and tear and/or for approved office reconfigurations or modifications.
Justification
Professional office areas require durable and ergonomically designed office furniture to promote an efficient, healthy and productive work
environment.
Budget Tmpact/Other
Expenditures 2021 2022 2023 2024 2025 Total
EquipmentNehicles 10,000 10,000 10,000 10,000 10,000 50,000
Total 10,000 10,000 10,000 10,000 10,000 50,000
Funding Sources 2021 2022 2023 2024 2025 Total
Levy 10,000 10,000 10,000 10,000 10,000 50,000
Total 10,000 10,000 10,000 10,000 10,000 50,000
Produced Using the Plan -It Capital Planning Software Page 37 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 HVAC/ROOF
Project name GS: HVAC/Roofing Replacement Program
Data in Year 2021
Type Asset - Replacement Department 323 - Gen Building & Equipmen
Useful Life 20 years Contact General Services Manager
Category 7214 - Buildings Priority 1 Critical
CTP Proj. Score: 65/200 Division Code 0130
PASER Rating: n/a
Status Active
Description Total Project Cost: $2,500,000
General Services coordinates the HVAC/Roofing replacement program schedule for all City buildings (with the exception of Utility buildings)
based on age/condition and service life expectancy. Each year the program prioritizes HVAC/Roofing projects and oversees all
updates/replacements, both planned and unplanned.
Justification
Regular updates/replacements of outdated, inefficient or failing HVAC/roofing will ensure City buildings will extend their service life and allow
operations to properly achieve their missions.
Budget Tmpact/Other
Expenditures
2021
2022
2023
2024
2025
Total
Improvements
500,000
500,000
500,000
500,000
500,000
2,500,000
Funding Sources
Total 500,000
2021
500,000
2022
500,000
2023
500,000
2024
500,000
2025
2,500,000
Total
Debt
500,000
500,000
500,000
500,000
500,000
2,500,000
Total 500,000
500,000
500,000
500,000
500,000
2,500,000
Produced Using the Plan -It Capital Planning Software Page 38 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 ADA AUDIT
Project Name GS: Complete ADA Audit of all City buildings
Data in Year 2021
Type Other Department 323 - Gen Building & Equipm
Useful Life Contact General Services Manager
Category 6401- ContractualServices Priority 2 Very Important
CTP Proj. Score: Division Code 0130
PASER Rating:
Status Active
Description Total Project Cost: $60,000
Complete an ADA audit of all City buildings
Justification
Title II of the ADA prohibits discrimination by government entities, including cities, on the basis of disability. Part of ensuring compliance by the
City is to conduct a facility audit to determine the current level of compliance with ADA standards in City structures, facilities and programs and to
develop a plan to bring the remaining City facilities into compliance.
Budget Tmpact/Other
$60,000
Expenditures
2021 2022
2023 2024 2025 Total
Other
60,000
60,000
Funding Sources
Total 60,000
2021 2022
60,000
2023 2024 2025 Total
Levy
60,000
60,000
Total 60,000
60,000
Produced Using the Plan -It Capital Planning Software Page 39 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 ENG VEH 1
Project name ENG: #389, 4-Wheel Drive 1/2-Ton Pickup Truck
Data in Year 2021
Type
Equipment
Department 323 - Gen Building & Equipmen
Useful Life
10-15 years
Contact Public Works Director
Category
7210 - Vehicles
Priority n/a
CTP Proj. Score:
n/a
Division Code 0420
PASER Rating:
n/a
Status Active
Description
Total Project Cost: $37,000
This will replace 4389, a 1997 GMC Suburban, with a 4-wheel drive, 1/2-ton pickup truck with a cap
Justification
Vehicle #389 currently has 151,706 miles on it. The body is rusting and the engine runs poorly. Once replaced, this truck will become a primary
vehicle, and will move an older truck into a backup role.
Budget Tmpact/Other
Expenditures
2021 2022
2023 2024 2025 Total
EquipmentNehicles
37,000
37,000
Funding Sources
Total 37,000
2021 2022
37,000
2023 2024 2025 Total
Debt
Trade -In
36,500
500
36,500
500
Total 37,000
37,000
Produced Using the Plan -It Capital Planning Software Page 40 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 STR VEH 1
Project name STR: #67, Tandem -Axle Plow Truck
Data in Year 2021
Type
Equipment
■.
Department 323 - Gen Building & Equipmen 127
Useful Life
10 years
Contact Public Works Director Ad
Category
7210 - Vehicles
Priority n/a"
CTP Proj. Score:
n/a
Division Code 0430
PASER Rating:
n/a
Status Active
Description
Total Project Cost: $225,000
This will replace 467, a 2007 International, with a tandem -axle plow truck with stainless steel box, wing, and tailgate spreadet
Justification
It has 102,664 miles on it. The hydraulic tank and engine leak oil. The unit has an older Force plow control system that is obsolete and the unit
does not have salt prewetting capabilities. The new unit will have salt prewet capabilities. The plow and especially the wing are worn and
suffering from metal fatigue.
Budget Tmpact/Other
Expenditures 2021 2022 2023 2024 2025 Total
EquipmentNehicles 225,000 225,000
Total 225,000 225,000
Funding Sources 2021 2022 2023 2024 2025 Total
Debt 210,000 210,000
Trade -In 15,000 15,000
Total 225,000 225,000
Produced Using the Plan -It Capital Planning Software Page 41 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 STR VEH2
Project dame STR: #33, 3/4-Ton 4WD Pickup Truck
Data in Year 2021
Type
Equipment
Department 323 - Gen Building & Equipmen
Useful Life
10 years
Contact Public Works Director
Category
7210 - Vehicles
Priority n/a
CTP Proj. Score:
n/a
Division Code 0430
PASER Rating:
n/a
Status Active
Description
Total Project Cost: $40,000
This will replace 433, a 2005 GMC, with a 3/4-ton 4-wheel drive extended cab pickup truck with lift -ate
Justification
It has 41,898 miles on it. This unit has the mobile refueling tank mounted in it. The dispenser on the fuel tank is getting weak. The body and
undercarriage are rusting. The inside of the cab is showing its age.
Budget Tmpact/Other
Expenditures
2021 2022
2023 2024 2025 Total
EquipmentNehicles
40,000
40,000
Funding Sources
Total 40,000
2021 2022
40,000
2023 2024 2025 Total
Debt
Trade -In
37,500
2,500
37,500
2,500
Total 40,000
40,000
Produced Using the Plan -It Capital Planning Software Page 42 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 STR VEH4
Project name STR: #140, Motor Grader
Data in Year 2021
Type
Equipment
Department 323 - Gen Building & Equipm
Useful Life
10 years
Contact Public Works Director
Category
7210 - Vehicles
Priority n/a
CTP Proj. Score:
n/a
Division Code 0430
PASER Rating:
n/a
Status Active
Description
Total Project Cost: $210,000
This will replace 4140, a 2002 Volvo grader with plow and wing
Justification
It has 5,250 hours on it. The unit has had repeated problems with the moldboard turntable. Recently, it has had issues with the front and rear
drive. The clutch is out on it now and will cost over $10,000 to replace. The engine has been losing power. Cost of repairs to this unit have been
$47,213.34 between 2014 and 2019. Cost of repairs on the other two graders over the same period combined have only been $22,979.49. The unit
would be replaced with a used unit.
Budget Tmpact/Other
Expenditures 2021 2022 2023 2024 2025 Total
EquipmentNehicles 210,000 210,000
Total 210,000 210,000
Funding Sources 2021 2022 2023 2024 2025 Total
Debt 195,000 195,000
Trade -In 15,000 15,000
Total 210,000 210,000
Produced Using the Plan -It Capital Planning Software Page 43 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 STR VEH5
Project Name STR: #122, Skid Steer and Router
Data in Year 2021
Type
Equipment
Department 323 - Gen Building & Equipmen
Useful Life
10 years
Contact Public Works Director
Category
7210 - Vehicles
Priority n/a
CTP Proj. Score:
n/a
Division Code 0430
PASER Rating:
n/a
Status Active
Description
Total Project Cost: $80,000
This will replace 4122, a 2005 Bobcat, with a tubber -tire skid steer with steerable axles, broom, and router
Justification
It has 1,736 hours on it. The glass for the cab is prone to breaking. The bucket and wheels are worn out.
Budget Tmpact/Other
Expenditures
2021 2022
2023 2024 2025 Total
EquipmentNehicles
80,000
80,000
Funding Sources
Total 80,000
2021 2022
80,000
2023 2024 2025 Total
Debt
Trade -In
73,000
7,000
73,000
7,000
Total 80,000
80,000
Produced Using the Plan -It Capital Planning Software Page 44 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 STR VEH6
Project Name STR: #262, Walk -Behind Router
Data in Year 2021
N
Type Equipment Department 323 - Gen Building & Equipmen
Useful Life 10 years Contact Public Works Director
Category 7210 - Vehicles Priority n/a
CTP Proj. Score: n/a Division Code 0430
PASER Rating: n/a
Status Active
Description Total Project Cost: $25,000
This will replace 4262, a 1996 Craftco walk -behind router. This unit is used to clean out the cracks in concrete and asphalt pavement prior to
sealing them.
Justification
It has 5,015 hours on it. Various components of this unit have been rebuilt and replaced to extend its useful life, such as the lifting actuator, wiring
harness, and cutting wheel drive systems. The engine will need replacement soon. The new unit will be self-propelled.
Budget Trnpact/Other
Expenditures
2021 2022
2023 2024 2025 Total
EquipmentNehicles
25,000
25,000
Funding Sources
Total 25,000
2021 2022
25,000
2023 2024 2025 Total
Debt
Trade -In
24,500
500
24,500
500
Total 25,000
25,000
Produced Using the Plan -It Capital Planning Software Page 45 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 STR VEH7
Project name STR: #22, 1-Ton 4WD Pickup Truck
Data in Year 2021
Type
Equipment
Department 323 - Gen Building & Equipmen
Useful Life
10 years
Contact Public Works Director
Category
7210 - Vehicles
Priority n/a
CTP Proj. Score:
n/a
Division Code 0430
PASER Rating:
n/a
Status Active
Description
Total Project Cost: $44,000
This will replace 422, a 2008 Ford, with a 1-ton 4-wheel drive regular cab pickup truck with liftgate
Justification
It has 40,884 miles on it. The undercarriage and liftgate are rusting. The inside of the cab is showing its age.
Budget Tmpact/Other
Expenditures
2021 2022
2023 2024 2025 Total
EquipmentNehicles
44,000
44,000
Funding Sources
Total 44,000
2021 2022
44,000
2023 2024 2025 Total
Debt
Trade -In
41,500
2,500
41,500
2,500
Total 44,000
44,000
Produced Using the Plan -It Capital Planning Software Page 46 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 STR VEH9
Project Name STR: #238, Single -Axle Trailer
Data in Year 2021
Type
Equipment
Department 323 - Gen Building & Equipm
Useful Life
10 years
Contact Public Works Director
Category
7210 - Vehicles
Priority n/a
CTP Proj. Score:
n/a
Division Code 0430
PASER Rating:
n/a
Status Active
Description
Total Project Cost: $10,000
This will replace 4238, a 1999 Loadmaster, with a single -axle trailer
Justification
It is used for hauling the concrete saw. It is showing signs of age. The suspension is wearing out. The metal it is built with is fatigued.
Budget Tmpact/Other
Expenditures
2021 2022
2023 2024 2025 Total
EquipmentNehicles
10,000
10,000
Funding Sources
Total 10,000
2021 2022
10,000
2023 2024 2025 Total
Levy
10,000
10,000
Total 10,000
10,000
Produced Using the Plan -It Capital Planning Software Page 47 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 PRKS BLDG
Project Name Parks: New Building Construction
Type Facility - Replacement
Useful Life 40 years
Category 7214 - Buildings
CTP Proj. Score:
PASER Rating:
Data in Year 2021
Department 325 - Parks Improvement
Contact Parks Director
Priority 2 Very Important
Division Code 0610
Status Active
Description I Total Project Cost: $6,400,000
Parks Department New Building. Begin construction of a new parks administration/operations facility necessary to support current and future Parks
Department operations. Construction would begin in 2021 and continue into 2022 as would the phased borrowing to fund the project. Phase 1
also includes funding to purchase and demo one property directly south of the existing building.
Justification
The existing facility from the 1960s was a former technical college building. The city undertook a facilities assessment and this building was
identified as the top priority for needs. It was not designed for municipal operations so it is not efficient and lacks necessary vehicle storage
capacity. The HVAC, electric and plumbing are all in poor condition. A new facility will compliment neighborhood improvements.
Budget Tmpact/Other
The new facility will improve the efficiency of department operations as it will be designed for municipal operations. All vehicles will be stored
indoors in an organized manner to improve staff time getting out to job sites. The building will centalize department administrative staff that are
currently housed in a varietv of facilities. Ener-*v efficient HVAC, liiihtina and Dlumbina will reduce enerav costs.
Expenditures
2021
2022 2023
2024 2025 Total
Improvements
3,400,000
3,000,000
6,400,000
Funding Sources
Total 3,400,000
2021
3,000,000
2022 2023
6,400,000
2024 2025 Total
Debt
3,400,000
3,000,000
6,400,000
Total 3,400,000
3,000,000
6,400,000
Produced Using the Plan -It Capital Planning Software Page 48 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 R CEM RDS
Project name Parks: Riverside Cemetery Roads Repaving
Data in Year 2021
Type
Infrastructure - Replacement
Department 325 - Parks Improvement
Useful Life
25 years
Contact Parks Director
Category
7216 - Land Tmprovements
Priority 3 Important
CTP Proj. Score:
65/200
Division Code 0610
PASER Rating:
Status Active
Description
Total Project Cost: $75,000
Riverside Cemetery Roads Repaving. Repave deteriorating roads in Riverside Cemetery
Justification
Roads within Riverside Cemetery continue to need repaving. Funds for repaving various portions of the roads is an expense requested by the
Department every other year. These funds pay for the materials and the Streets Division staff complete the paving.
Budget Tmpact/Other
These funds are requested every other year to keep up with cemetery road repairs
Expenditures
2021 2022
2023 2024
2025
Total
Improvements
25,000
25,000
25,000
75,000
Funding Sources
Total 25,000
2021 2022
25,000
2023 2024
25,000
2025
75,000
Total
Levy
25,000
25,000
25,000
75,000
Total 25,000
25,000
25,000
75,000
Produced Using the Plan -It Capital Planning Software Page 49 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Data in Year 2021
Project * 21 MP TRL IM
Project Name Parks: Menominee Park Trail Improvements/drainage
Type Infrastructure - New Department 325 - Parks Improvement
Useful Life 25 years Contact Parks Director
Category 7216 - Land Tmprovements Priority 3 Important
CTP Proj. Score: 70/200 Division Code 0610
PASER Rating: n/a
Status Active
Description Total Project Cost: $75,000
Menominee Park Trail Improvements/drainage. Improve the drainage in the park in select areas between Melvin Avenue and Nevada Avenue to
alleviate ponding of water on the park trail sections. Working with engineering and storm water staff, a drainage system will be installed to divert
the water so it does not flow onto and across the trail.
Justification
Due to poor drainage in the park in this area, water tends to pond on the trail throughout the year making it unuseable at times. This has been a
concern of trail and park users for some time.
Budget Tmpact/Other
Project is necessary to improve conditions and use of the trail.
Expenditures
2021 2022
2023 2024 2025 Total
Improvements
75,000
75,000
Funding Sources
Total 75,000
2021 2022
75,000
2023 2024 2025 Total
Debt
75,000
75,000
Total 75,000
75,000
Produced Using the Plan -It Capital Planning Software Page 50 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Data in Year 2021
Type
Asset - Replacement
Department 325 - Parks Improvement
Useful Life
10 years
Contact Parks Director
Category
6452 - Street Lighting
Priority 2 Very Important
CTP Proj. Score:
70/200
Division Code 0610
PASER Rating:
Status Active kr
Description
Total Project Cost: $25,000
Riverwalk Light Bollards Replacement. Replacement and inventory of light bollards along the Fox River Riverwalk
Justification
With the oldest section of the riverwalk being over 10 years old, the light bollards in various sections have started to fail or get vandalized. There
is currently not an inventory of bollards to replace the ones currently not working nor for any that will fail or be damaged in the near future.
Budget Tmpact/Other
As the segments of the riverwalk are completed, the maintenance and associated costs become part of the Parks Department budget including
electric.
Expenditures
2021 2022
2023 2024 2025 Total
Improvements
25,000
25,000
Funding Sources
Total 25,000
2021 2022
25,000
2023 2024 2025 Total
Levy
25,000
25,000
Total 25,000
25,000
Produced Using the Plena -It Capita[ Planning Software Page 51 Thursday, July Q 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 SP TEN CT
Project Name Parks: South Park Tennis Court Reconstruction
Data in Year 2021
Type Asset - Replacement Department 325 - Parks Improvement
Useful Life 20 years Contact Parks Director
Category 7216 - Land Tmprovements Priority 2 Very Important
CTP Proj. Score: 65/200 Division Code 0610
PASER Rating: n/a
Status Active
Description Total Project Cost: $325,000
South Park Tennis Court Reconstruction. A component of the South Park Master Plan is to reconstruct the existing tennis courts and replace the
fencing. These courts are heavily used by the community and the Recreation Department summer tennis program.
Justification
The courts are due for resurfacing due to the age and use. Numerous cracks are present and the court lines are severely faded. With the increased
popularity of pickleball, more pickleball courts are needed in the city. This project will include construction of 4 pickleball courts and 2 tennis
courts (a reduction of one tennis court).
Budget Tmpact/Other
New courts will reduce the cost of crack filling.
Expenditures
2021 2022
2023 2024 2025 Total
Improvements
325,000
325,000
Funding Sources
Total 325,000
2021 2022
325,000
2023 2024 2025 Total
Debt
325,000
325,000
Total 325,000
325,000
Produced Using the Plan -It Capital Planning Software Page 52 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Data in Year 2021
Project# 21 WCRL EQUP
Project name Parks: Westhaven Circle Prk Play Equip & Surfacing
Type Asset - Replacement Department 325 - Parks Improvement
Useful Life 20 years Contact Parks Director
Category 7204 - Machinery & Equip Priority 2 Very Important
CTP Proj. Score: 65/200 Division Code 0610
PASER Rating: n/a
Status Active
Description Total Project Cost: $200,000
Westhaven Circle Park Play equipment and surfacing. The project will include new play equipment, installation of poured -in -place rubberized
surfacing that is safer, more accessible, durable and less maintenance than the existing wood fiber used in the playgrounds and a concrete
accessible perimeter walk.
Justification
With this equipment being some of the oldest in the park system, the need to replace it with safer and more accessible equipment is ranked high in
the priorities for the park. The CORP for the city recommends the replacement of the equipment at Westhaven Circle Park. The equipment was
installed in 2001.
Budget Tmpact/Other
Reduces the need for adding wood fiber surfacing regularly and the rubber surfacing reduces the amount of staff time on maintenance.
Expenditures
2021 2022
2023 2024 2025 Total
Improvements
200,000
200,000
Funding Sources
Total 200,000
2021 2022
200,000
2023 2024 2025 Total
Debt
200,000
200,000
Total 200,000
200,000
Produced Using the Plan -It Capital Planning Software Page 53 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Data in Year 2021
Project# 21 PRKS VEH1
Project Name Parks: Replace'01 Ford Workhorse Step Van #401
Type
Asset - Replacement
Department 326 - Parks Equipment
Useful Life
10 years
Contact Parks Director
Category
7210 - Vehicles
Priority 1 Critical
CTP Proj. Score:
n/a
Division Code 0610
PASER Rating:
n/a
Status Active
Description
Total Project Cost: $60,000
Replace 2001 Ford Workhouse Step Van. #401 equipment number
Justification
This unit provides efficient operations in our fleet by housing tools and providing work space while on the job site. The vehicle is utilized by staff
throughout all seasons. Current unit has 39,000 miles and faulty mechanicals along with chasis deterioration justifies the need for replacement.
Budget Tmpact/Other
Depreciation of vehicle and increased maintenance costs justify replacement
Expenditures
2021 2022
2023 2024 2025 Total
EquipmentNehicles
60,000
60,000
Funding Sources
Total 60,000
2021 2022
60,000
2023 2024 2025 Total
Debt
Trade -In
57,500
2,500
57,500
2,500
Total 60,000
60,000
Produced Using the Plan -It Capital Planning Software Page 54 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 PRKS VEH4
Project Name Parks: Replace'89 Topsoil Screener
Data in Year 2021
Type
Asset - Replacement
Department 326 - Parks Equipment
Useful Life
15 years
Contact Parks Director
Category
7210 - Vehicles
Priority 3 Important
CTP Proj. Score:
n/a
Division Code 0610
PASER Rating:
n/a
Status Active
Description
Total Project Cost: $28,000
Replace 1989 Topsoil Screener with 1,224 hours
Justification
The Topsoil Screener is used frequently to process soil for department projects, grave restoration at cemeteries and stump grinding restoration. The
current unit has been used extensively by several departments and is in poor condition. It is well beyond its useful life.
Budget Tmpact/Other
The unit is beyond repair and a replacement unit would reduce the amount of topsoil the city would need to purchase from outside sources
Expenditures
2021 2022
2023 2024 2025 Total
EquipmentNehicles
28,000
28,000
Funding Sources
Total 28,000
2021 2022
28,000
2023 2024 2025 Total
Debt
Trade -In
27,500
500
27,500
500
Total 28,000
28,000
Produced Using the Plan -It Capital Planning Software Page 55 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 LOT IMRPV
Project name TR: Parking Lot Improvements
Data in Year 2021
Type
Infrastructure - Replacement
Department 400 - Traffic
Useful Life
20 years
Contact Transit Director
Category
7216 - Land Tmprovements
Priority 2 Very Important
CTP Proj. Score:
105/200
Division Code 1717
PASER Rating:
n/a
Status Active
Description
Total Project Cost: $2,500,000
This is an annual amount budgeted to fund the reconstruction of municipal parking lots. Projects are prioritized using the Assessment of municipal
parking lots study performed by Jewell and Associates. The study was updated in 2020.
Justification
Municipal parking lots are an asset to the city that must be maintained. Adequate parking is vital to encourage and accommodate visitors to the
city including downtown. Adequate parking is also needed for employees and guests of city facilities. The parking lot is one of the first
experiences visitors have.
Budget Tmpact/Other
Reconstruction of new parking lots help minimize ongoing maintenance and repair costs
Expenditures
2021
2022
2023
2024
2025
Total
Improvements
500,000
500,000
500,000
500,000
500,000
2,500,000
Funding Sources
Total 500,000
2021
500,000
2022
500,000
2023
500,000
2024
500,000
2025
2,500,000
Total
Debt
500,000
500,000
500,000
500,000
500,000
2,500,000
Total 500,000
500,000
500,000
500,000
500,000
2,500,000
Produced Using the Plan -It Capital Planning Software Page 56 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 SGNL HEAD
Project Name TR: LED Traffic Signal Head Equipment
Data in Year 2021
Type
Infrastructure - Replacement
Department 400 - Traffic
Useful Life
10 years
Contact Transit Director
Category
7206 - Capital Construction
Priority 3 Important
CTP Proj. Score:
60/200
Division Code 0801
PASER Rating:
n/a
Status Active
Description
Total Project Cost: $50,000
This will involve the continual replacement of LED signal heads at city maintained traffic signals to maintain a state of good repait
Justification
LED signal heads offer substantial savings in maintenance and energy consumption compared to conventional incandescent lamp signal heads.
The city switched to LED several years ago and the early generation LEDs are in need of replacement. It is critical that the LED signal heads
maintain sufficient brightness for traffic safety. The LEDs last approximately 10 years.
Budget Tmpact/Other
It is important to maintain the signals and inventory to prevent emergeny purchases and shipments
Expenditures 2021 2022 2023 2024 2025 Total
Traffic 10,000
10,000
10,000
10,000
10,000
50,000
Total 10,000
10,000
10,000
10,000
10,000
50,000
Funding Sources 2021
2022
2023
2024
2025
Total
Levy 10,000 10,000 10,000 10,000 10,000 50,000
Total 10,000 10,000 10,000 10,000 10,000 50,000
Produced Using the Plan -It Capital Planning Software Page 57 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 STR LGHTS
Project Name TR: LED Streetlighting Upgrades
Data in Year 2021
Type Infrastructure - Replacement
Department 400 - Traffic
Useful Life 20 years
Contact Transit Director
Category 7206 - Capital Construction
Priority 3 Important
CTP Proj. Score: 70/200
Division Code 0460
PASER Rating: n/a
Status Active
Description
Total Project Cost: $50,000
This project would replace LED retrofit kits that are at the end of their useful life with LED fixtures. The first wave of LED street lights were
installed with retrofit kits instead of actual LED fixtures as a first step. LED fixtures are now more affordable and reliable and therefore the retrofit
kits need to be replaced.
Justification
Newer LED lights need less maintenance and last longer reducing ongoing costs. They also have better light performance
Budget Tmpact/Other
Vewer LED lights need less maintenance and last longer, reducing ongoing costs.
Expenditures
2021
2022
2023
2024
2025
Total
Traffic
10,000
10,000
10,000
10,000
10,000
50,000
Funding Sources
Total 10,000
2021
10,000
2022
10,000
2023
10,000
2024
10,000
2025
50,000
Total
Levy
10,000
10,000
10,000
10,000
10,000
50,000
Total 10,000
10,000
10,000
10,000
10,000
50,000
Produced Using the Plan -It Capital Planning Software Page 58 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 STR POLES
Project Name TR: Purchase Streetlighting Poles
Data in Year 2021
Type Infrastructure - Replacement
Department 400 - Traffic
Useful Life 20 years
Contact Transit Director
Category 7206 - Capital Construction
Priority 3 Important
CTP Proj. Score: 55/200
Division Code 0460
PASER Rating: n/a
Status Active
Description
Total Project Cost: $125,000
The city owns over 1,000 street lighting poles.
While the poles are expected to have a long service life, we do lose poles through damage from car
accidents (about 1/2 are hit and nm/unrecoverable).
In addition, we are working on expanding the number of city owned poles. This would help
increase our inventory both for replacement and
further expansion.
Justification
We need to have an adequate supply to replace poles that are knocked down in addition to spreading the cost of new poles for expansion
Budget Tmpact/Other
This project avoids emergency orders and shipments.
Expenditures
2021
2022
2023
2024
2025
Total
Traffic
25,000
25,000
25,000
25,000
25,000
125,000
Funding Sources
Total 25,000
2021
25,000
2022
25,000
2023
25,000
2024
25,000
2025
125,000
Total
Levy
25,000
25,000
25,000
25,000
25,000
125,000
Total 25,000
25,000
25,000
25,000
25,000
125,000
Produced Using the Plan -It Capital Planning Software Page 59 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 TRF SGNL
Project Name TR: Traffic Signal Equipment
Data in Year 2021
Type hifiastructure - Replacement Department 400 - Traffic
Useful Life 20 years Contact Transit Director
Category 7206 - Capital Construction Priority 3 Important
CTP Proj. Score: 55/200 Division Code 0801
PASER Rating: n/a
Status Active
Description Total Project Cost: $225,000
This project pays for traffic signal equipment to be installed at various intersections as needed in order to repair knockdowns and/or replace
obsolete equipment. Typical purchases include poles, cabinets, controllers, and vehicle detection equipment.
Justification
Signal infrastructure equipment can last 20-25 years and is a long-term capital investment. It should be noted that additional funding would be
requested for new signals or required upgrades once locations are known.
Budget Trnpact/Other
It is important to maintain the signals and inventory to prevent emergency purchases and shipments.
Expenditures
2021
2022
2023
2024
2025
Total
Traffic
45,000
45,000
45,000
45,000
45,000
225,000
Funding Sources
Total 45,000
2021
45,000
2022
45,000
2023
45,000
2024
45,000
2025
225,000
Total
Levy
45,000
45,000
45,000
45,000
45,000
225,000
Total 45,000
45,000
45,000
45,000
45,000
225,000
Produced Using the Plan -It Capital Planning Software Page 60 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 VEH SIGN1
Project Name TR: Sign Service Truck 1 to 1 1/2 Tn (rep12004)
Data in Year 2021
Type Asset - Replacement Department 400 - Traffic
Useful Life 10 years Contact Transit Director
Category 7210 - Vehicles Priority 2 Very Important
CTP Proj. Score: n/a Division Code 0810
PASER Rating:
Status Active
Description Total Project Cost: $90,000
This replaces truck 4522, a 2004 service truck that is at the end of its useful life. The new truck will be a 1 to 1 1 /2 ton pick-up with set -vice body
for use in sign installation and maintenance.
Justification
This truck is used by the sign department for installation and maintenance of signs as well as street painting
Budget Tmpact/Other
The maintenance of this truck averages $1200 per year which would be greatly reduced with a new vehicle.
Expenditures
2021 2022
2023 2024 2025 Total
EquipmentNehicles
90,000
90,000
Funding Sources
Total 90,000
2021 2022
90,000
2023 2024 2025 Total
Debt
90,000
90,000
Total 90,000
90,000
Produced Using the Plan -It Capital Planning Software Page 61 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 GOH SIGNS
Project Name GS: Grand Opera House Signage Updates
Data in Year 2021
Type Asset - Replacement Department 501 - Grand Opera House
Useful Life 20 years Contact General Services Manager
Category 7214 - Buildings Priority 3Important
CTP Proj. Score: 75/200 Division Code 1020
PASER Rating: n/a
Status Active
Description Total Project Cost: $75,000
The Grand Opera House Foundation is seeking to update three exterior signs on the Grand exterior (an electronic messaging board) on the west
wall, a "blade" sign on the side side, and signage over the front steps. The Foundation has shared sign designs with the Landmarks Commission.
Justification
Staff has been told the Landmarks Commission feels the sign designs, color and style are in concert with this historic building. Staff have yet to
confirm installation details and any State Historical Preservation Office review of this project.
Budget Trnpact/Other
Note: the GOHF has indicated they are willing to fully fund this project.
Expenditures
2021 2022
2023 2024 2025 Total
Improvements
75,000
75,000
Funding Sources
Total 75,000
2021 2022
75,000
2023 2024 2025 Total
Donations
75,000
75,000
Total 75,000
75,000
Produced Using the Plan -It Capital Planning Software Page 62 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Data in Year 2021
Project * 21 GOH STAGE
Project Name GS: Grand Opera House Stage Floor Replacement
Type Asset - Replacement Department 501 - Grand Opera House
Useful Life 25 years Contact General Services Manager
Category 7214 - Buildings Priority 2 Very Important
CTP Proj. Score: 95/200 Division Code 1020
PASER Rating:
Status Active
Description Total Project Cost: $35,000
A 2020 assessment of the stage floor (circa 1986) confirmed the hardwood floor is in need of full replacement with cracked, splintered and flaking
wood evident throughout the stage area. Replacement would include removing the existing floor, patching the subfloor as necessary, installing
new maple flooring and sanding and refinishing the flooring.
Justification
New stage flooring will eliminate safety concerns with the current flooring and improve the functionality and appearance of the stage for
Budget Trnpact/Other
Vote: the GOHF has indicated they are able to donate $10,000 towards this project.
Expenditures
2021 2022
2023 2024 2025 Total
Improvements
35,000
35,000
Funding Sources
Total 35,000
2021 2022
35,000
2023 2024 2025 Total
Donations
Levy
10,000
25,000
10,000
25,000
Total 35,000
35,000
Produced Using the Plan -It Capital Planning Software Page 63 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Data in Year 2021
Project * 21 OCC AHU
Project Name GS: OCC Air Handler Unit (Mezzanine) Replacement
Type Asset - Replacement Department 503 - Convention Center
Useful Life 20 years Contact General Services Manager
Category 7214 - Buildings Priority 1 Critical
CTP Proj. Score: 90/200 Division Code 1040
PASER Rating:
Status Active
Description
The air handler units above the mezzanine within the ballroom of the Convention Center are over 30 years old and need to be replaced due to their
age and condition. The units are very noisy and impeed the ability of patrons being able to hear presenters when the units are running. Sound
insulation in the past has helped, but the units continue to get louder.
Justification
Staff recommends having the units replaced to improve the efficiency of the HVAC system and reduce unnecessary noise when the units are
running.
Budget Tmpact/Other
This project would be funded from the State Trust Fund Loan.
Expenditures
2021 2022
2023 2024 2025 Total
Improvements
200,000
200,000
Funding Sources
Total 200,000
2021 2022
200,000
2023 2024 2025 Total
Prior Year Funding
200,000
200,000
Total 200,000
200,000
Produced Using the Plan -It Capital Planning Software Page 64 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 TR STP IM
Project Name TR: Transit Stop Improvements
Data in Year 2021
Type
Infrastructure - New
Department 511 -Transit
Useful Life
20 years
Contact Transit Director
Category
7216 - Land Tmprovements
Priority 3 Important
CTP Proj. Score:
65/200
Division Code 1728
PASER Rating:
n/a
Status Active
Description
Total Project Cost: $50,000
This project pays for transit shelters, paving, and curbing improvements to bring high usage transit stops in compliance with ADA. Locations are
prioritized based on the stop accessibility survey in conjuction with ridership.
Justification
The survey done by ECWRPC along with the TDP identified numerous transit stops which are not compliant with ADA. We must continue to
improve these stops. Accessiblity to stops also enhances the safety and comfort of riders which helps sustain and potentially increase ridership.
Budget Tmpact/Other
Expenditures 2021 2022 2023 2024 2025 Total
Improvements 10,000
10,000
10,000
10,000
10,000
50,000
Total 10,000
10,000
10,000
10,000
10,000
50,000
Funding Sources 2021
2022
2023
2024
2025
Total
Transit Fund 10,000 10,000 10,000 10,000 10,000 50,000
Total 10,000 10,000 10,000 10,000 10,000 50,000
Produced Using the Plan -It Capital Planning Software Page 65 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Data in Year 2021
Project * 21 AUT WHLCH
Project name TR: Automated Wheelchair Securement Sys 12 buses
Type
Infrastructure - Upkeep
Department 511 -Transit
Useful Life
15 years
Contact Transit Director
Category
7204 - Machinery & Equip
Priority 2 Very Important
CTP Proj. Score:
n/a
Division Code 1728
PASER Rating:
Status Active
Description
Total Project Cost: $180,000
Adds an automated wheelchair securement system to each of the 12 newer buses, one system per bus
Justification
Drivers currently secure wheelchairs by hand requiring very close and personal interactions. This project would install a Quantum Automatic
Wheelchair securement system in each bus. There would be one per bus. The system allows passengers to secure themselves without close
personal contact Mth operators
Budget Tmpact/Other
This will help reduce COVID 19 exposure and possible risks and costs asssociated with it
Expenditures
2021 2022
2023 2024 2025 Total
Improvements
180,000
180,000
Funding Sources
Total 180,000
2021 2022
180,000
2023 2024 2025 Total
Grant
180,000
180,000
Total 180,000
180,000
Produced Using the Plan -It Capital Planning Software Page 66 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
reject * 21 TR BUSES
roject Name TR: 2 hybrid & 2 clean diesel buses (repl 2010's)
Type
Asset - Replacement
Useful Life
12 years
Category
7210 - Vehicles
CTP Proj. Score:
90/200
PASER Rating:
Department 511 -Transit
Contact Transit Director
Priority 1 Critical
Division Code 1728
Data in Year 2021
F
Status Active A
Description Total Project Cost: $2,600,000
This project replaces the 2010 buses that have passed their useful life. These bases are hybrids that are experiencing mechanical failures due to age
and worn out parts. Repairs are very costly on hybrid buses. We have two active grants to replace 2 of these buses at 80% funding and another
grant to replace the other 2 at 100% federal funding. The active grants are for clean diesel buses and the other for hybrids.
Justification
Heavy duty buses have a useful life of 12 years. We are required to maintain our fleet in a state of good repair. These new buses preserve our
fleet's high level of reliability. The purchase will also reduce maintenance costs, emmision and improve fuel efficiency. We plan to order 2 hybrid
and 2 clean diesel buses
Budget Tmpact/Other
We need to take advantage of the current available grant funding as grant funding is hard to get and very unpredictable. New buses reduce
emissions, improve fuel effrcency and reduce repair costs. A clean diesel bus is estimated at $550,000, a hybrid bus is estimated at $750,000
Expenditures
2021 2022 2023 2024 2025 Total
EquipmentNehicles
2,600,000
2,600,000
Total 2,600,000
2,600,000
Funding Sources
2021 2022
2023 2024 2025 Total
Debt
56,061
56,061
Grant
2,360,000
2,360,000
Prior Year Funding
183,939
183,939
Total 2,600,000
2,600,000
Produced Using the Plan -It Capital Planning Software Page 67 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Data in Year 2021
Project * 21 TR FRKLFT
Project Name TR: Forklift (repl 1993 Komatsu FD 25VT-11 Diesel)
Type
Asset - Replacement
Department 511 -Transit
Useful Life
20 years
Contact Transit Director
Category
7210 - Vehicles
Priority 3 Important
CTP Proj. Score:
n/a
Division Code 1728
PASER Rating:
n/a
Status Active
Description
Total Project Cost: $35,000
Replace 1993 Komatsu FD 25VT-11 Diesel 6,000 lbs capacity
Justification
The forklift is used to load and unload trucks as well as aid in transit vehicle and building maintenance and repairs. This forklift is also used by the
sign/electric shop and water distribution facility.
Budget Tmpact/Other
A newer forklift will reduce maintenance costs and possibly costly emergency rentals
Expenditures
2021 2022
2023 2024 2025 Total
EquipmentNehicles
35,000
35,000
Funding Sources
Total 35,000
2021 2022
35,000
2023 2024 2025 Total
Grant
35,000
35,000
Total 35,000
35,000
Produced Using the Plan -It Capital Planning Software Page 68 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 TRAN FARE
Project Name TR: Electronic Fare Readers/Farebox for Buses
Data in Year 2021
Type
Other
Department 511 -Transit
Useful Life
10 years
Contact Transit Director
Category
7230 - Computer Software
Priority 1 Critical
CTP Proj. Score:
n/a
Division Code 1728
PASER Rating:
n/a
Status Active
Description
Total Project Cost: $200,000
Mobile Fares are a way to purchase fares via a mobile device and/or vending machine and supplement the manual farebox
Justification
Mobile Fares will make the purchase and use of fares more efficient and effective. Mobile/Automatic Fares will also reduce driver interaction.
Budget Tmpact/Other
Mobile Fares will reduce cash handling, saving time for staff as well as drivers. Mobile Fares may also encourage more riders to use transit. This
may allow us to take credit and debit cards as well.
Expenditures 2021 2022 2023 2024 2025 Total
Other 200,000 200,000
Total 200,000 200,000
Funding Sources 2021 2022 2023 2024 2025 Total
Grant 160,000 160,000
Prior Year Funding 40,000 40,000
Total 200,000 200,000
Produced Using the Plan -It Capital Planning Software Page 69 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 TRANS CTR
Project name TR: Downtown Transit Center
Data in Year 2021
Type Facility -Upkeep Department 511-Transit
Useful Life 30 years Contact Transit Director
Category 7214 - Buildings Priority 1 Critical
CTP Proj. Score: 100/200 Division Code 1728
PASER Rating: n/a =
Status Active
Description Total Project Cost: $2,320,000
The current transit center is nothing more than a transfer location with a heated shelter and driver restroom. There is a need for a driver breakroom,
a pass sales/customer service presence and a supervisor office. A public restroom may or may not be needed. This will follow a planning study
being done in 2020 and follows recommendations in the transit development plan.
Justification
The construction of a downtown transit center would allow for customer interaction and a sales outlet downtown. It will also provide space for the
driver supervisor to work from, a driver breakroom, and possibly a public restroom. It is possible that other uses such as parking or office space
could be incorporated.
Budget Tmpact/Other
This facility would improve driver morale which could reduce driver turnover. It would also allow for convenient pass sales, which may increase
revenue.
Expenditures
2021 2022
2023 2024 2025 Total
Other
2,320,000
2,320,000
Funding Sources
Total 2,320,000
2021 2022
2,320,000
2023 2024 2025 Total
Grant
2,320,000
2,320,000
Total 2,320,000
2,320,000
Produced Using the Plan -It Capital Planning Software Page 70 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 ENG LEAD
Project name ENG: Misc. Utility -Owned Lead Service Repl.
Data in Year 2021
Type
Infrastructure - Replacement
Department 541 - Water
Useful Life
75-100 years
Contact Public Works Director
Category
7206 - Capital Construction
Priority n/a
CTP Proj. Score:
105/200
Division Code 1810
PASER Rating:
n/a
Status Active
Description
Total Project Cost: $1,000,000
As utility -owned lead water services are discovered, these services will be replaced under the Lead Sen ice Replacement Program
Justification
EPA is mandating all lead water services be removed from the system.
Budget Tmpact/Other
Expenditures
2021
2022
2023
2024
2025
Total
Future
Water
100,000
100,000
100,000
100,000
100,000
500,000
500,000
Funding Sources
Total 100,000
2021
100,000
2022
100,000
2023
100,000
2024
100,000
2025
500,000
Total
Total
Future
Water Utility Fund
100,000
100,000
100,000
100,000
100,000
500,000
500,000
Total 100,000
100,000
100,000
100,000
100,000
500,000
Total
Produced Using the Plan -It Capital Planning Software Page 71 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 WD ST BDG
Project Name WD: Heated Storage Building
Data in Year 2021
Type Facility - New Department 541 - Water
Useful Life 40 years Contact Public Works Director
Category 7214 - Buildings Priority n/a
CTP Proj. Score: Division Code 1810
PASER Rating: n/a
Status Active
Description Total Project Cost: $440,000
Construct a heated storage building to store materials and fleet vehicles. In 2021, design services are planned. Construction is planned to be
performed in 2022.
Justification
Water Distribution needs additional storage to store larger new equipment and materials. A study will be performed in 2020 to determine location
and size needs.
Budget Tmpact/Other
Expenditures 2021 2022 2023 2024 2025 Total
Water 90,000 350,000 440,000
Total 90,000 350,000 440,000
Funding Sources 2021 2022 2023 2024 2025 Total
Water Revenue Bonds 90,000 350,000 440,000
Total 90,000 350,000 440,000
Produced Using the Plan -It Capital Planning Software Page 72 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 WF CLRWLL
Project Name WFP: Clearwell Replacement
Type Infrastructure - Replacement
Useful Life 50 years
Category 7214 - Buildings
CTP Proj. Score:
PASER Rating: n/a
Data in Year 2021
Department 541 - Water
Contact Public Works Director
Priority n/a
Division Code 1810
Status Active
Description I Total Project Cost: $22,000,000
The Water Filtration Plant has three concrete structures on site called clearwells that store 2.4 million gallons of treated drinking water. This water
is pumped into the water distribution system to maintain pressure for water use by consumers and for fire protection. The clearwells also provide
storage of water needed to backwash filters as part of the treatment process. Two of the tanks were installed in 1916 and the third was installed in
the 1950's. They have been regularly inspected and maintained, but they no longer meet WDNR regulatory requirements. Due to age and WDNR
r"ulatory requirements, all of these tanks are proposed to be replaced.
Justification
A portion of the existing cleat -well structures are below ground and do not meet the WDNR regulation that requires a two -foot separation between
the bottom of a tank and the groundwater. This has been noted in the WDNR Sanitary Survey as a deficiency starting in 2007. The structures were
inspected regularly and well maintained, so the WDNR allowed a 10-year window to start design, receive regulatory approvals, and construct new
cleat -wells. The design was completed and submitted to the WDNR and the Public Service Commission (PSC) in 2017. At that time, the
anticipated construction completion was late 2020 or early 2021. WDNR agreed with the design, but the PSC had numerous questions that needed
to be addressed. The PSC questions led to a detailed Water System Capacity Study that was completed in 2019 and included some minor
modifications that could be considered in a re -design. In 2019, the WDNR Sanitary Survey again cited the clearwell deficiency and showed an
anticipated completion date of March 2020. WDNR was aware of the issues with PSC approval, but stated they could not take that into
consideration and could not extend the completion date. They also stated at that time that a consent order would need to be entered into on the
clealwell replacement. WDNR has since decided they will review and take action on compliance with the 2022 Sanitary Survey. if the clearwells
are marked as a significant deficiency during the 2022 Sanitary Survey, it could trigger a regulatory noncompliance public notification of a
significant health risk. By getting this project under way, we would be in a better positon to avoid a possible significant deficiency on our next
Sanitary Survey and the related public notice.
Document/Study/Planning Document: 2014 Water Filtration Plant Clearwell Safe Drinking Water Preliminary Design Study, WDNR Sanitary
Survev Requirement, and Water Svstem Canacitv Studv (2019)
Budget Impact/Other
It is anticipated Safe Drinking Water Loan Funds will be used.
Expenditures
2021
2022
2023 2024
2025 Total
Water
10,000,000
8,000,000
4,000,000
22,000,000
Total
Funding Sources
10,000,000
2021
8,000,000
2022
4,000,000
2023 2024
22,000,000
2025 Total
Safe Drinking Water Loan
10,000,000
8,000,000
4,000,000
22,000,000
Total
10,000,000
8,000,000
4,000,000
22,000,000
Produced Using the Plan -It Capital Planning Software Page 73 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Data in Year 2021
Project * 00 WF FER TW
Project Name WFP: Re -Paint Fernau Water Tower and Add Mixing
Type h1fiastructure - Upkeep Department 541 - Water
Useful Life 15 years Contact Public Works Director
Category 7214 - Buildings Priority n/a
CTP Proj. Score: Division Code 1810
PASER Rating: n/a
Status Active
Description Total Project Cost: $1,200,000
The Fernau Water Tower is due for a complete re -painting (inside and outside). Adding mixing will improve water quality and the disinfecting
process. In 2021, engineering senTices are planned. Contractor services are planned to be performed in 2022.
Justification
The tower was last painted in 2001 during original construction. Painting is needed to protect the tower's metal surfaces.
Document/Study/Planning Document: Water Utility Asset Management Plan Update (2015 and 2020 draft)
Budget Tmpact/Other
Expenditures 2021 2022 2023 2024 2025 Total
Water 75,000 1,125,000 1,200,000
Total 75,000 1,125,000 1,200,000
Funding Sources 2021 2022 2023 2024 2025 Total
Water Utility Fund 75,000 1,125,000 1,200,000
Total 75,000 1,125,000 1,200,000
Produced Using the Plan -It Capital Planning Software Page 74 Thursday, July 9, 2020
Manager Recommended CIP Project Details Data in Year 2021
City of Oshkosh, Wisconsin
Project * 00 WF M BAY
Project name WFP: 36" Intake Miller's Bay Bypass min
Type Asset - Upkeep Department 541 - Water
Useful Life 50 years Contact Public Works Director
Category 7206 - Capital Construction Priority n/a
CTP Proj. Score: Division Code 1810
PASER Rating: n/a
Status Active
Description Total Project Cost: $2,300,000
Re -configure the connection of the 36" intake to bypass Miller's Bay and upgrade existing intake to meet current requirements. In 2021, study and
design services are planned. Construction is planned to be performed in 2022.
Justification
The 24" backup intakes are in failing condition, and we are in need of a backup raw water intake. The 36" intake is in place, but we cannot use it,
since it utilitizes the Miller's Bay Sedimentation Basin. Re -configuring the intake will allow us to utilize assets that are currently in place.
Document/Study/Planning Document: Water Utility Asset Management Plan Update (2015 and 2020 draft)
Budget Tmpact/Other
Expenditures 2021 2022 2023 2024 2025 Total
Water 300,000 2,000,000 2,300,000
Total 300,000 2,000,000 2,3003000
Funding Sources 2021 2022 2023 2024 2025 Total
Water Revenue Bonds 300,000 2,000,000 2,300,000
Total 300,000 2,000,000 2,300,000
Produced Using the Plan -It Capital Planning Software Page 75 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Data in Year 2021
Project * 21 ENG KNAPP
Project Name ENG: Knapp Street Area Water Main Replacements
Type
Infrastructure - Replacement
Department 541 - Water
Useful Life
75+ years
Contact Public Works Director
Category
7206 - Capital Construction
Priority n/a
CTP Proj. Score:
90/200
Division Code 1810
PASER Rating:
n/a
Status Active
Description I Total Project Cost: $3,709,600
4
PA
C s
k
"
x
R mwk�
s
Replace 5,190' of existing 6" water mains with 8" water mains on Knapp Street, from Osborn Avenue to West 18th Avenue; Erie Avenue, from
Knapp Street to Rugby Street; Florida Avenue, from Knapp Street to Sanders Street; Rugby Street, from West South Park Avenue to Florida
Avenue; and Sanders Street, from West South Park Avenue to Florida Avenue.
Justification
The existing water mains have had large amounts of breaks and their replacements were requested by the Water Distribution Division.
Age of Infrastructure:
Water - 1948, 1950, 1951, 1954, and 1964
Budget Tmpact/Other
Expenditures
2021 2022
2023 2024 2025 Total
Water
3,709,600
3,709,600
Total
Funding Sources
3,709,600
2021 2022
3,709,600
2023 2024 2025 Total
Water Revenue Bonds
3,709,600
3,709,600
Total
3,709,600
3,709,600
Produced Using the Plan -It Capital Planning Software Page 76 Thursday, July 9, 2020
Manager Recommended CIP Project Details Data in Year 2021
City of Oshkosh, Wisconsin
Project * 21 WD VEH 1
Project Name WD: #830, 3/4-Ton CNG Full -Size Van
Type Equipment Department 541 - Water
Useful Life 10-15 years Contact Public Works Director
Category 7210 - Vehicles Priority n/a
CTP Proj. Score: n/a Division Code 1810
PASER Rating: n/a
Status Active
Description Total Project Cost: $44,000
This will replace 4830, a 2010 3/4-ton CNG full-size van, with a 1/2-ton work van. This vehicle is primarily used as a meter technician van or for
daily hydrant flushing.
Justification
A 1-ton vehicle is no longer needed for the duties performed by this vehicle. The life to date cost of maintenance and repair of this vehicle is $0.09
per mile. In 2019, this cost rose to $0.22 per mile. The newer Ford Transit 1/2-ton meter vans get around 11-12 miles per gallon. In 2019, this
vehicle averaged 7 miles per gallon.
Budget Trnpact/Other
Expenditures 2021 2022 2023 2024 2025 Total
EquipmentNehicles 44,000 44,000
Total 44,000 44,000
Funding Sources 2021 2022 2023 2024 2025 Total
Trade -In 2,000 2,000
Water Utility Fund 42,000 42,000
Total 44,000 44,000
Produced Using the Plan -It Capital Planning Software Page 77 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project# 21 WF VEH1
Project name WFP: #891, 3/4-Ton 4x4 Pickup Truck
Data in Year 2021
Type
Equipment
Department 541 - Water
Useful Life
10-15 years
Contact Public Works Director
Category
7210 - Vehicles
Priority n/a
CTP Proj. Score:
n/a
Division Code 1810
PASER Rating:
n/a
Status Active
Description
Total Project Cost: $50,000
This will replace 4891, 2010 Ford, with a 3/4-ton 4x4 short -box pickup truck
Justification
This pickup truck is over 10 years old. The undercarriage is rusted. Unit has issues with 4-wheel drive auto -locking hubs.
Budget Tmpact/Other
Expenditures
2021 2022
2023 2024 2025 Total
EquipmentNehicles
50,000
50,000
Funding Sources
Total 50,000
2021 2022
50,000
2023 2024 2025 Total
Trade -In
Water Utility Fund
3,000
47,000
3,000
47,000
Total 50,000
50,000
Produced Using the Plan -It Capital Planning Software Page 78 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Data in Year 2021
Project# 21 WF WSH TW
Project Name WFP: Re -Paint Washburn Water Tower and Add Mixing
Type hifiastructure - Upkeep Department 541 - Water
Useful Life 15 years Contact Public Works Director
Category 7214 - Buildings Priority n/a
CTP Proj. Score: Division Code 1810
PASER Rating: n/a
Status Active
Description Total Project Cost: $1,100,000
The Washburn Water Tower is due for a complete re -painting (inside and outside). Adding mixing will improve water quality and the disinfecting
Justification
Purpose is to protect the tower's metal surfaces. This project was originally budgeted in 2020, but was not done due to estimated project cost being
more than was originally budgeted.
Document/Study/Planning Document: Water Utility Asset Management Plan Update (2015 and 2020 draft)
Budget Tmpact/Other
Expenditures
2021 2022
2023 2024 2025 Total
Water
1,100,000
1,100,000
Funding Sources
Total 1,100,000
2021 2022
1,100,000
2023 2024 2025 Total
Water Utility Fund
1,100,000
1,100,000
Total 1,100,000
1,100,000
Produced Using the Plan -It Capital Planning Software Page 79 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 ENG LEAKS
Project Name ENG: Inflow/Infiltration Removal
Data in Year 2021
Type Infrastructure - Replacement Department 551 - Sewer
Useful Life 75-100 years Contact Public Works Director
Category 7206 - Capital Construction Priority n/a
CTP Proj. Score: 120/200 Division Code 1910
PASER Rating: n/a
Status Active
Description Total Project Cost: $13,500,000
The program rotates through the City to repair or replace leaking sanitary sewer infrastructure. The program also includes areas where problems
are identified through regular inspections. Work includes identification and elimination of clear water entering the sanitary sewer system and
implementation of CMOM/SECAP recommendations. Work may include manhole inspections and repairs, flow monitoring, and/or sewer lining
or replacement. Sanitary sewer lining and grouting of laterals and mainline will be performed in areas that have newer concrete streets with aging
sanitary sewer infrastructure. Televising inspections will be used to determine the areas of work.
Justification
This work helps to remove clear water from the sanitary sewer system. Clear water entering the sanitary system is a significant problem. The
sanitary sewer system is not designed to handle these flows, which may result in sanitary sewer backups into residents' homes.
Budget Impact/Other
Expenditures 2021 2022 2023 2024 2025 Total Future
Wastewater
Funding Sources
1,000,000 1,000,000 1,000,000 1,500,000 1,500,000 6,000,000 7,500,000
Total 1,000,000 1,000,000 1,000,000 1,500,000 1,500,000 6,000,000 Total
2021 2022 2023 2024 2025
Sewer Revenue Bonds 500,000
Sewer Utility Fund 500,000
500,000
500,000
500,000
500,000
1,000,000
500,000
1,000,000
500,000
Total 1,000,000
1,000,000
1,000,000
1,500,000
1,500,000
Total Future
3,500,000 7,500,000
2,500,000 Total
6,000,000
Produced Using the Plan -It Capital Planning Software Page 80 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Data in Year 2021
Project# 00 WW CLRFRS
Project Name WW: Clarifiers #1, #2, #3, & #4 Floor Replacement
0�5 �-74 - �,
Type Asset - Upkeep Department 551 - Sewer
Useful Life 30 years Contact Public Works Director
Category 7214 - Buildings Priority n/a
CTP Proj. Score: Division Code 1910
PASER Rating: n/a
Status Active
Description Total Project Cost: $900,000
Replace the floors of Clarifiers #1, #2, #3, and 44. Each clarifier is 96' in diameter and areas of the top surface of the concrete floors need to be
repaired and re -grouted to fill in the voids. Construction is planned to be performed in 2021 and 2022.
Justification
The current concrete floors are in poor condition and will need to be replaced to improve operational efficiency
Budget Tmpact/Other
Expenditures
2021 2022 2023 2024 2025 Total
Wastewater 450,000 450,000 900,000
Total 450,000 450,000 900,000
Funding Sources 2021 2022 2023 2024 2025 Total
Sewer Revenue Bonds 450,000 450,000 900,000
Total 450,000 450,000 900,000
Produced Using the Plan -It Capital Planning Software Page 81 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project# 00 WW EUSS
Project Name WW: Replace Electrical Unit Substations
Type Asset - Replacement
Useful Life 30-50 years
Category 7214 - Buildings
CTP Proj. Score:
PASER Rating: n/a
Data in Year 2021
Department 551 - Sewer
Contact Public Works Director
Priority n/a
Division Code 1910
Status Active
Description I Total Project Cost: $7,665,500
� A
Replace select entrance switchgear and Motor Control Centers. In 2021, design services are planned. Construction is planned to be performed in
2022 and 2023. A substantial amount of the electrical substation equipment within the Wastewater Treatment Plant was installed in 1975 when the
plant was contructed, making it about 45 years old. The entrance switchgear in the main electrical room was installed in 2005 with the generator
project, and added to again in 2014 with the influent pump motor and variable -frequency drives upgrade. All of the substations in the solids
building and the digester building were installed in 1997. This critical equipment takes the 4160 medium voltage power, supplied by Wisconsin
Public Service, and converts it to the necessary 480 voltage power for the plant equipment to operate, and it provides a centralized location to
protect, control, and isolate the electrical systems. The equipment has been well maintained, but was identified as a significant risk in the 2017
Asset Management Plan. Replacements parts are becoming more difficult to obtain and the system lacks many safety features of modern
Justification I
This electrical equipment is about 45 years old and while well maintained, it needs to be replaced due to equipment obsolescence issues.
Replacement will improve power distribution system reliability.
Document: Asset Management Plan (Jacobs - 201
Budget Tmpact/Other
Expenditures
2021
2022
2023 2024
2025 Total
EquipmentNehicles
890,000
2,593,500
4,182,000
7,665,500
Total
Funding Sources
890,000
2021
2,593,500
2022
4,182,000
2023 2024
7,665,500
2025 Total
Sewer Revenue Bonds
890,000
2,593,500
4,182,000
7,665,500
Total
890,000
2,593,500
4,182,000
7,665,500
Produced Using the Plan -It Capital Planning Software Page 82 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project# 00 WW PM SYS
Project Name WW: Replace Polymer Mixing System
Data in Year 2021
fk7'
Type Equipment Department 551- Sewer
Useful Life 20 years Contact Public Works Directort�
+ J
J!I w
F �'
Category 7204 - Machinery & Equip Priority n/a
CTP Proj. Score: Division Code 1910
PASER Rating: n/a
Status Active
r
Description
Total Project Cost: $420,000
The polymer mixing systems were originally installed during the 1997 WWTP digester upgrade.
The system includes a dry polymer wetting
system, polymer -aging tank with mixer, aged -polymer storage, polymer -feed pumps, and a dry -polymer hoist. In 2021, design of the system is
planned. In 2022, construction of the system is planned to be performed.
Justification
The existing polymer system has surpassed its useful life and has become unreliable. This results in increased polymer usage, leading to additional
costs. The new system will improve reliability, reduce maintenance, and decrease polymer usage.
Document/Study/Planning Document: Asset Management Plan (Jacobs - 2017)
Budget Tmpact/Other
Expenditures
2021
2022 2023
2024 2025 Total
EquipmentNehicles
50,000
370,000
420,000
Total
Funding Sources
50,000
2021
370,000
2022 2023
420,000
2024 2025 Total
Sewer Revenue Bonds
50,000
370,000
420,000
Total
50,000
370,000
420,000
Produced Using the Plan -It Capital Planning Software Page 83 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 ENG FDL
Project Name ENG: Fond du Lac Sanitary Sewer
Data in Year 2021
Type Infrastructure - Replacement Department 551 - Sewer
Useful Life 75-100 years Contact Public Works Director
Category 7206 - Capital Construction Priority n/a
CTP Proj. Score: 110/200 Division Code 0410
PASER Rating: n/a
Status Active
Description Total Project Cost: $5,400,400
3,900' of sanitary sewer will be relayed on Fond du Lac Road, from the West 28th Avenue Pump Station to the Waukau Avenue Pump Station.
The sanitary sewer will be increased in size from 15" to 21". This project will eliminate the Waukau Avenue Pump Station.
Justification
This project will aid in reducing the occurrence of basement backups in the area.
Document/Study/Planning Document: Sanitary Sewer System 2050 Planning Study (2017)
Budget Tmpact/Other
Expenditures
2021 2022
2023 2024 2025 Total
Storm
50,000
50,000
Wastewater
5,250,400
5,250,400
Water
100,000
100,000
Total
5,400,400
5,400,400
Funding Sources
2021 2022
2023 2024 2025 Total
Assessment
23,000
23,000
Sewer Revenue Bonds
5,227,400
5,227,400
Storm Revenue Bonds
50,000
50,000
Water Revenue Bonds
100,000
100,000
Total
5,400,400
5,400,400
Produced Using the Plan -It Capital Planning Software Page 84 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project# 21 WW ASSESS
Project Name WW: Assessment of WWTP Piping Condition
Data in Year 2021
4-
Type Facility - Upkeep Department 551 -Sewer
Useful Life 10 years Contact Public Works Director
Category 6401 -Contractual Services Priority n/a
CTP Proj. Score: Division Code 1910
PASER Rating: n/a
Status Active
Description Total Project Cost: $30,000
An outside contractor will be hired to do a condition assessment on pipes in the pipe gallery of the WWTP.
Justification
The pipes are original to the structure, 1974 ductile iron. A condition assessment is needed to determine the maintenance and repair or replacement
schedule.
Budget Tmpact/Other
Expenditures 2021 2022 2023 2024 2025 Total
EquipmentNehicles 30,000 30,000
Total 30,000 30,000
Funding Sources 2021 2022 2023 2024 2025 Total
Sewer Utility Fund 30,000 30,000
Total 30,000 30,000
Produced Using the Plan -It Capital Planning Software Page 85 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Data in Year 2021
Project# 21 WW BR PSI
Project Name WW: Repl Broad St Pump Station Make-up Air Unit #1
Type Equipment Department 551 -Sewer
Useful Life 20 years Contact Public Works Director
Category 7204 - Machinery & Equip Priority n/a
CTP Proj. Score: Division Code 1910
PASER Rating: n/a
Status Active
Description Total Project Cost: $15,000
Replace the make-up air unit at the Broad Street Pump Station.. It was installed in 1985
Justification
This is original equipment and has surpassed its useful life (rusting out) and needs to be replaced.
Document/Study/Planning Document: Asset Management Plan (Jacobs - 2017)
Budget Tmpact/Other
Expenditures 2021 2022 2023 2024 2025 Total
EquipmentNehicles 15,000 15,000
Total 15,000 15,000
Funding Sources 2021 2022 2023 2024 2025 Total
Sewer Utility Fund 15,000 15,000
Total 15,000 15,000
Produced Using the Plan -It Capital Planning Software Page 86 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project# 21 WW CF SYS
Project Name WW: Chlorine Feed System Upgrade
Data in Year 2021
Type Equipment Department 551 -Sewer Y
Useful Life 15 years Contact Public Works Director
Category 7204 - Machinery & Equip Priority n/a
CTP Proj. Score: Division Code 1910
PASER Rating: n/a -
Status Active
Description Total Project Cost: $555,000
Chlorine gas has been used for effluent disinfection since 1975, with an upgrade to a vacuum system in 1992. This project includes the installation
of an Emergency Chlorine Scrubber, relocation of the vacuum regulators for the chlorine ton cylinders, a new automatic switchover valve, and
chlorine gas piping replacement within the chlorine ton container storage room.
Justification
Updates were made to the feed system in 2007, and now individual chlorine vacuum feed regulators and new piping for improved safety and
efficiency are needed.
Document/Study/Planning Document: Asset Management Plan (Jacobs - 2017)
Budget Tmpact/Other
Expenditures 2021 2022 2023 2024 2025 Total
EquipmentNehicles 555,000 555,000
Total 555,000 555,000
Funding Sources 2021 2022 2023 2024 2025 Total
Sewer Revenue Bonds 555,000 555,000
Total 555,000 555,000
Produced Using the Plan -It Capital Planning Software Page 87 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project# 21 WW CONCRT
Project Name WW: WWTP Concrete Condition Assessment
Data in Year 2021
Type hifiastructure - Upkeep Department 551 - Sewer
Useful Life 25 years Contact Public Works Director
Category 6401 -Contractual Services Priority n/a
CTP Proj. Score: Division Code 1910
PASER Rating: n/a
Status Active
Description Total Project Cost: $23,000
A full facility assessment of the WWTP concrete needs to be completed
Justification
The concrete in this facility is 45 years old and is showing signs of fatigue. There are a few leaks in the expansion joints that were not replaced in
2012.
Budget Tmpact/Other
Expenditures
2021 2022
2023 2024 2025 Total
Planning
23,000
23,000
Funding Sources
Total 23,000
2021 2022
23,000
2023 2024 2025 Total
Sewer Utility Fund
23,000
23,000
Total 23,000
23,000
Produced Using the Plan -It Capital Planning Software Page 88 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project# 21 WW DUMP
Project Name WW: Update/Relocation of Dump Site
Type
Facility - Replacement
Useful Life
50 years
Category
7208 - Land
CTP Proj. Score:
PASER Rating:
n/a
Data in Year 2021
Department 551 - Sewer
Contact Public Works Director
Priority n/a
Division Code 1910
Status Active
Description Total Project Cost: $2,000,000
The Septic Hauler and Street Sweepers Dump Site at the Wastewater Treatment Plant is used by Public Works and other waste haulers. This
project will segregate the waste stream from the Wastewater Treatment Plant. This project will be funded equally by the Storm Water and
Wastewater Utilities.
Justification
This current site is too small, provides no availability for flow monitoring or sampling, and is not protected from rainfall. The co -mingling of
wastes and the introduction of rainfall creates waste that has high concentrations of nutrients and heavy metals that disrupts the balance of the
treatment processes at the Wastewater Treatment Plant. This project will allow that waste to be more effectively managed and properly disposed.
Budget Tmpact/Other
Expenditures
2021 2022
2023 2024 2025 Total
Storm
Wastewater
1,000,000
1,000,000
1,000,000
1,000,000
Total
Funding Sources
2,000,000
2021 2022
2,000,000
2023 2024 2025 Total
Sewer Revenue Bonds
Storm Revenue Bonds
1,000,000
1,000,000
1,000,000
1,000,000
Total
2,000,000
2,000,000
Produced Using the Plan -It Capital Planning Software Page 89 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project# 21 WW LADDR
Project Name WW: Add Ladder Access in WWTP Pump Room
Data in Year 2021
Type Facility - Upkeep Department 551 - Sewer in
Useful Life 50 years Contact Public Works Director'Category 7214-Buildings Priority n/a
CTP Proj. Score: Division Code 1910
PASER Rating: n/aStatus Active 4
Description Total Project Cost: $13,000
Add platform, handrail, and ship ladder to pump room in order to access 36" valve by ceiling. The valve is equipped with remote operation
equipment. However, over the past few years, staff have needed to access the valve to manually close it, due to debris in the valve, which prevents
the remote operation equipment from sealing the valve closed.
Justification
Currently, if we need to operate the valve in hand mode or manual operation, we need to tie off and crawl across a pipe 40' above the floor. This is
for the safety of the plant staff.
Budget Tmpact/Other
Expenditures
2021 2022
2023 2024 2025 Total
Wastewater
13,000
13,000
Funding Sources
Total 13,000
2021 2022
13,000
2023 2024 2025 Total
Sewer Utility Fund
13,000
13,000
Total 13,000
13,000
Produced Using the Plan -It Capital Planning Software Page 90 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project# 21 WW PUTERS
Project Name WW: Replace Computers and Related Equipment
Data in Year 2021
.z
Type Equipment Department 551 -Sewer r
Useful Life 5 years Contact Public Works Director I
Category 7204 - Machinery & Equip Priority n/a
CTP Proj. Score: Division Code 1910
PASER Rating: n/a
Status Active
Description Total Project Cost: $25,000
Replace computers with updated hardware and software to maintain dependability
Justification
Computers need to be updated to prevent operating system obsolescence.
Budget Tmpact/Other
Expenditures 2021 2022 2023 2024 2025 Total
EquipmentNehicles 25,000 25,000
Total 25,000 25,000
Funding Sources 2021 2022 2023 2024 2025 Total
Sewer Utility Fund 25,000 25,000
Total 25,000 25,000
Produced Using the Plan -It Capital Planning Software Page 91 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 W W VEH 1
Project Name WW: #172, Zero -Turn Lawn Mower
Data in Year 2021
Type
Equipment
Department 551 -Sewer
Useful Life
15 years
Contact Public Works Director
Category
7210 - Vehicles
Priority n/a
CTP Proj. Score:
Division Code 1910
PASER Rating:
n/a
Status Active
Description
Total Project Cost: $11,300
This will replace 4172, a 2004 Toro Zero -Turn lawn mower with 60" deck
Justification
The oroginal Toro has high hours and has had multiple repairs over the last few years.
Budget Tmpact/Other
Expenditures
2021 2022
2023 2024 2025 Total
EquipmentNehicles
11,300
11,300
Total
Funding Sources
11,300
2021 2022
11,300
2023 2024 2025 Total
Sewer Revenue Bonds
Trade -In
9,800
1,500
9,800
1,500
Total
11,300
11,300
Produced Using the Plan -It Capital Planning Software Page 92 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Data in Year 2021
Project * 00 ENG GALMR
Project Name ENG: Glatz Cr/Gallups-Merritts/Johnson Av Wtrsheds
Type Infrastructure - New Department 561 - Storm Water
Useful Life 100+ years Contact Public Works Director
Category 7206 - Capital Construction Priority n/a
CTP Proj. Score: 95/200 Division Code 2010
PASER Rating: n/a
Status Active
Description Total Project Cost: $3,685,000
These sombside watersheds have along history of flooding that has been validated by computer models of the drainage systems. This project will
target key areas where flooding is most acute and where development could occur once flooding is brought under control. In 2021, design services
are planned. Construction is planned to be performed in 2022. Planting of the detention basin is planned to be performed in 2024.
Justification
Gallups-Merritts Creek Watershed is in need of flood control assistance. This project will construct a floodplain storage area to assist downstream
flooding.
Document/Study/Planning Document: Glatz Creek Storm Water Study, Gallups-Merritts Creek Watershed Storm Water Management Plan, and
Johnson Avenue Watershed Storm Water Management Plan
Budget Tmpact/Other
Expenditures 2021 2022 2023 2024 2025 Total
Storm 500,000 3,000,000 185,000 3,685,000
Total 500,000 3,000,000 185,000 3,685,000
Funding Sources 2021 2022 2023 2024 2025 Total
Storm Revenue Bonds 500,000 3,185,000 3,685,000
Total 500,000 3,185,000
3,685,000
Produced Using the Plan -It Capital Planning Software Page 93 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 00 ENG MINT
Project Name ENG: Mini Storm Sewers/Storm Laterals
Data in Year 2021
Type Infrastructure - New Department 561 - Storm Water
Useful Life 100+ years Contact Public Works Director
Category 7206 - Capital Construction Priority n/a
CTP Proj. Score: 90/200 Division Code 2010
PASER Rating: n/a
Status Active
Description Total Project Cost: $6,750,000
This project will provide mini storm sewers and laterals to property owners that had requested them.
Justification
The laterals allow property owners to connect to the storm sewer system without discharging water over the sidewalk.
Budget Tmpact/Other
Expenditures 2021 2022 2023 2024 2025 Total Future
Street 25,000 25,000 25,000 25,000 25,000 125,000 3,375,000
Storm 650,000 650,000 650,000 650,000 650,000 3,250,000 Total
Total 675,000 675,000 675,000 675,000 675,000 3,375,000
Funding Sources
2021
2022
2023
2024
2025
Total
Future
Assessment
25,000
25,000
25,000
25,000
25,000
125,000
3,375,000
Levy
25,000
25,000
25,000
25,000
25,000
125,000
Total
Storm Water Utility Fund
625,000
625,000
625,000
625,000
625,000
3,125,000
Total
675,000
675,000
675,000
675,000
675,000
3,375,000
Produced Using the Plan -It Capital Planning Software Page 94 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Data in Year 2021
Project * 00 ENG RR LI
Project Name ENG: Anchorage Watershed RR-Libbey Storm Sewer
Type Infrastructure - Replacement Department 561 - Storm Water
Useful Life 100+ years Contact Public Works Director
Category 7206 - Capital Construction Priority n/a
CTP Proj. Score: 95/200 Division Code 2010
PASER Rating: n/a
Status Active
Description Total Project Cost: $3,272,000
i
This project is for storm sewer construction from East Nevada Avenue to East Murdock Avenue and from East Murdock Avenue to the Libbey
Channel along the eastern side of CN's railroad tracks. In 2021, acquisition of the land and/or easements for the storm sewer is planned. In 2022,
Part 1 of the construction, from East Murdock Avenue to the Libbey Channel, will begin. In 2023, Part 2 of the construction, from East Nevada
Avenue to East Murdock Avenue, will begin.
Justification
Age of Infrastructure:
Storm - 1931
Document/Study/Planning Document: Anchorage Basin H&H Analysis Update Memorandum Addendum
Budget Tmpact/Other
Expenditures 2021 2022 2023 2024 2025 Total
Storm 100,000
2,179,000
993,000
3,272,000
Total 100,000
2,179,000
993,000
3,272,000
Funding Sources 2021
2022
2023 2024
2025 Total
Storm Revenue Bonds 100,000 2,179,000 993,000 3,272,000
Total 100,000 2,179,000 993,000 3,272,000
Produced Using the Plan -It Capital Planning Software Page 95 Thursday, July 9, 2020
Manager Recommended CIP Project Details Data in Year 2021
City of Oshkosh, Wisconsin
Project * 00 ENG SAWYR
Project Name ENG: Sawyer Creek Watershed Detention Basin
Type Infrastructure - New Department 561 - Storm Water
Useful Life 100+ years Contact Public Works Director
Category 7206 - Capital Construction Priority n/a
CTP Proj. Score: 100/200 Division Code 2010
PASER Rating: n/a
Status Active
Description Total Project Cost: $6,800,000
This project involves constructing a detention basin that will be capable of capturing approximately 300 - 400 acre-feet of flood water from Sawyer
Creek. The property currently has an agricultural land use and is located south of West 20th Avenue and west of Clairville Road. The detention
basin will be constructed similarly to the James Road Detention Basin and is the last of the large proposed projects for the Sawyer Creek
watershed. The proposed basin will capture flood waters just before Sawyer Creek enters into the City of Oshkosh limits. In 2021, acquisition of
the land on which the detention basin will be construction is planned. In 2022, design of the detention basin will be performed. In 2023,
construction of the detention basin will begin.
Justification
This basin will be designed to reduce flood risks to homes, businesses, and public utilities downstream in the City of Oshkosh and will make some
properties more suitable for development.
Document/Study/Planning Document: Sawver Creek Storm Water Management Plan (2009)
Budget Impact/Other
Expenditures
2021
2022
2023 2024
2025 Total
Storm
1,500,000
300,000
5,000,000
6,800,000
Total
Funding Sources
1,500,000
2021
300,000
2022
5,000,000
2023 2024
6,800,000
2025 Total
Storm Revenue Bonds
1,500,000
300,000
5,000,000
6,800,000
Total
1,500,000
300,000
5,000,000
6,800,000
Produced Using the Plan -It Capital Planning Software Page 96 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project# 00ENGWSTWN
Project Name ENG: Westowne Area Detention Basin
Data in Year 2021
Type Infrastructure - New Department 561 - Storm Water
Useful Life 100+ years Contact Public Works Director
Category 7206 - Capital Construction Priority n/a
CTP Proj. Score: 90/200 Division Code 2010
PASER Rating: n/a
Status Active
Description Total Project Cost: $985,000
47 ', a21
9
This project is for construction to expand the limits of the current City -owned wet detention basin at the intersection of Westowne Avenue and
North Washburn Street. Planting of the detention basin is planned for 2022.
Justification
The Westowne Watershed is the 4th highest generator of pollutants (total suspended solids/acre) in the City, and increasing the detention basin size
increases the removal of the total suspended solids in this watershed from 12% to 73%.
Budget Tmpact/Other
Expenditures 2021 2022 2023 2024 2025 Total
Storm 800,000 185,000 985,000
Total 800,000 185,000 985,000
Funding Sources 2021 2022 2023 2024 2025 Total
Storm Revenue Bonds 800,000 185,000 985,000
Total 800,000 185,000 985,000
Produced Using the Plan -It Capital Planning Software Page 97 Thursday, July 9, 2020
Manager Recommended CIP Project Details
City of Oshkosh, Wisconsin
Project * 21 SW VEH 1
Project Name SW: #100, Zero -Turn Mower
Data in Year 2021
Type
Equipment
Department 561 - Storm Water
Useful Life
10 years
Contact Public Works Director
Category
7210 - Vehicles
Priority n/a
CTP Proj. Score:
n/a
Division Code 2010
PASER Rating:
n/a
Status Active
Description
Total Project Cost: $10,000
This will replace 4100, a 2009 Toro zero -turn mower
Justification
It has 2,251 hours on it. The throttle and choke cables for the engine regularly fail. The metal for mower deck is fatigued and cracks often.
Budget Tmpact/Other
Expenditures 2021 2022 2023 2024 2025 Total
EquipmentNehicles 10,000 10,000
Total 10,000 10,000
Funding Sources 2021 2022 2023 2024 2025 Total
Storm Revenue Bonds 10,000 10,000
Total 10,000 10,000
Produced Using the Plan -It Capital Planning Software Page 98 Thursday, July 9, 2020