HomeMy WebLinkAboutChange Order No 1 (Final)- Carl Bowers & Sons /3
rA
City
0fFWV
Oshkosh
November 30, 2018
Mr. Bill Bowers
Carl Bowers & Sons Construction Co., Inc.
N1844 Maloney Road
Kaukauna, WI 54130
RE: Change Order No. 1 (Final)
Contract 17-04 (Eveline Street)
Dear Mr. Bowers:
Enclosed is an executed copy of Change Order No. 1 (Final.) between the City of Oshkosh and
Carl Bowers &Sons Construction Co., Inc. regarding the abovementioned project.
If you have any questions, please call our office at (920)236-5065.
Sincerely,
J es Rabe, P.E., CPESC
Director of Public Works
JER/t1t
Enclosure: Change Order No. 1 (Final)
cc: Pam Ubrig, City Clerk (w/original)
Jennifer Messerschmidt, Assistant Finance Director (w/copy)
File (w/original)
1:\Engineeringk2017 CONTRACTS\17-04 Cone Paving&Uffl\Eveline St\Projectjiifol7nitiol)\Cotitract
Info\Change Orders\17-404(Eveline)Executed CO 01(Final)Ltr.-11-30-18.docx Page I of 1
City Hall,215 Church Avenue P.O. Box 1130 Oslikosh,W154903-1130 http://www.ci.oshkosh.wi,us
TO: CARL BOWERS&SONS CONST. CO., INC. CHANGE ORDER#1 (FINAL)
N1844 MALONEY ROAD DATE: July 20,2018
KAUKAUNA,WI 54180
Your present contract with the City of Oshkosh,Contract No. 17-04 Eveline Street,awarded April 11, 2017, is hereby
amended and changed as follows,
NET INCREASE TO: SECTION 1 $34,978.00
NET DECREASE TO: SECTION 1 ($30$143.45)
NET INCREASE TO CONTRACT $4,834.55
EVELINE ST TOTALS
BID TOTAL $1,240,801.75 $1$240,801.75
MINUS PAVING ($358,339J5) ($358,339.76)
$082,46100 $082,462,00
CO#'1 $4,834.55 $4,834.55
T, 2X557
CONTRAC JPT,�L��' V
CITY OF OSHKOSH
BY:
City Man, er,
City Clerk
A roved and accepted:
Vo'n—tr—actor
I certify that provision has been made to pay the liability that will accrue to the,City of Oshkosh,Wisconsin, under the
within Change Order.
Comgir&4
Approved as tWorm
A�OA
City Alt rna
CONTRACT 17-04 EVELINE STREET CHANGE ORDER#1 (FINAL)
SECTION I
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE'IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Furnish and install 10"storm Linear
2002 sewer;complete ass ecified Feet 40.00 38.00 -2.00 $60.00 ($120.00)
Furnish and install 12"storm Linear 1
2003 sewer;complete asspecified Feet 255.00 255.50 0.50 $60.00 $30.00
Furnish and install 15"storm Linear
2006 sewer;complete asspecified Feet 1 25.00 18,30 -6.70 1 $60.00 ($402.00)
Furnish and install 18"storm Linear
2009 sewer;complete as specified Feet 335.00 331.50 -3.50 $70.00 ($245.00)
Furnish and install 24"storm Linear
2015 sewer;complete as specified Feet 525.00 522.10 -2.90 $70.00 ($203.00)
Furnish and install 27"storm Linear
2018 sewer;complete asspecified Feet 325.00 321.80 -3.20 $80.00 ($256.00)
Furnish and install 30"storm Linear
2021 sewer;complete as specified Feet 255.00 253.30 -1.70 $100.00 ($170.00)
Furnish and install standard
storm sewer manhole(4'
diameter);complete as Vertical
2201 specified Feet 25.40 25.13 -0.27 $350.00 ($94.50)
Furnish and install standard
storm sewer manhole(5'
diameter);complete as Vertical
2202 specified Feet 5.15 5.18 0.03 $450.00 $13.50
Furnish and install standard
storm sewer manhole(6'
diameter);complete as Vertical
2203 specified Feet 4.70 4.72 0.02 $500,00 $10.00
Furnish and install standard
storm sewer inlet manhole(4'
diameter); complete as Vertical
2213 specified Feet 4.25 4.32 0,07 $350.00 $24.50
Furnish and install Type 3
inlet(with 18"sump);
2237 complete asspecified Each 15.00 15,00 $1,700.00
Furnish and install 6"storm
sewer lateral;complete as Linear
2400 specified Feet 1,300.00 1,245.50 -54.50 $50.00 ($2,725.00)
Furnish and install storm
sewer marker balls;complete
2404 asspecified Each 89.00 85.00 -4.00 $25.00 ($100.00)
Furnish and install storm
sewer clay dams;complete
2406 _as specified Each 43.00 42.00 -1.00 $100,00 ($100.00)
Furnish and install storm
sewer lateral inlet;complete
2408 _as specified Each 43.00 40.00 -3.00 $500.00 ($1,500.00)
Storm lateral inlet
adjustments;complete as
2414 specified Each MOO 0.00 -10.00 $275.00 ($2,750.00)
Furnish; install; maintain; and
remove Type D modified inlet
protection;complete as
2508 specified Each 37.00 21.00 -16.00 $90.00 ($1,440,00)
Sediment removal-Type D
modified inlet protection;
2510 complete asspecified Each 37.00 0.00 -37.00 , $10.00 $370.00)
Page 1 of 5
CONTRACT 17-04 EVELINE STREET CHANGE ORDER#1 (FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Furnish; install;maintain;and
remove stone bag;complete
2516 asspecified Each 25.00 23.00 -2.00 $15.00 ($30.00)
Furnish;install;maintain;and
remove 12"diameter
sediment logs;complete as Linear
2518 specified Feet 20.00 0.00 -20.00 $10.00 ($200.00)
Abandon 8"-12"storm Linear
2800 sewer;complete asspecified Feet 260.00 260.00 1 $5.00
Abandon 15"and larger
storm sewer;complete as Linear
2802 specified Feet 1 245.00 245.00 $10.00
Remove 30"and smaller
storm sewer;complete as Linear
2804 _specified Feet 180.00 180.00 1 $20.00
Abandon storm sewer
manholes and inlets;
2810 _complete asspecified Each 9.00 9.00 $400.00
Remove storm sewer
manholes and inlets;
2812 _complete asspecified Each 2.00 2.00 $500.00
Connect to existing storm
sewer main;complete as
2850 specified Each 2.00 2.00 1 $1,200.00
Connect to existing storm
sewer manhole;complete as
2856 specified Each 2.00 2.00 $1,250.00
Furnish and install 8"sanitary
sewer(relay);complete as Linear
3000 specified Feet 1,412.00 1,397.30 -14.70 $95.00 ($1,396.50)
Furnish and install 10"
sanitary sewer(relay); Linear
3002 complete asspecified Feet 35.00 8.50 -26.50 $100.00 ($2,650, 0)
Furnish and install standard
sanitary sewer manhole(4'
diameter);complete as Vertical
3100 specified Feet 51.00 38,61 -12.39 $325.00 ($4,026.75)
Furnish and install external
sanitary sewer manhole
chimney seal;complete as
3114 ,specified Each 1.00 5.00 4.00 $450.00 $1,800,00
Furnish and install external
sanitary sewer manhole
chimney seal extension;
3116 complete asspecified Each 1.00 1.00 $400.00
Furnish and install internal
sanitary sewer manhole
chimney seal;complete as
3118 specified Each 1.00 0.00 -1.00 $350,00 ($350.00)
Furnish and install internal
sanitary sewer manhole
chimney seal extension;
3120 complete asspecified Each 1.00 0.00 -1.00 $300.00 ($300.00)
Furnish and install 4"sanitary
sewer laterals(new); Linear
3230 complete asspecified Feet 60.00 31.00 -29.00 $85,00 ($2,465.00),
Page 2 of 5
CONTRACT 17-04 EVELINE STREET CHANGE ORDER#1 (FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Furnish and install 4"/6"
sanitary sewer lateral(relay); Linear
3234 complete as specified Feet 1,350.00 1,423.50 73.50 $85.00 $6,247.50
Furnish and install sanitary
sewer lateral marker balls;
3236 complete asspecified Each 94.00 93.00 -1.00 $25.00 ($25.00)
Furnish and install clay
3238 dams;complete ass ecified Each 47.00 46.00 1 -1.00 $95.00 ($95.00)
Furnish and install
connection to existing 8"
3300 mains;complete as specified Each 3.00 1.00 -2.00 $800.00 $1,600.00
Abandon sanitary sewer
manholes;complete as
3800 specified Each 2.00 2.00 $400.00
Abandon 8"sanitary sewer; Linear
3802 complete asspecified Feet 1,620.00 1,620.00 $3.00
Abandon 10"sanitary sewer; Linear
3804 complete asspecified Feet 1 568.00 568.00 $4.00
Remove sanitary sewer
manholes;complete as
3852 specified Each 7.00 7.00 $600.00
Remove sanitary sewer; Linear
3854 complete asspecified Feet 284.00 284.00 1 $20.00
Furnish and install 4"ductile
iron water main(relay)with
polywrap;complete as Linear
4000 specified Feet 29.00 26.00 -3.00 $90.00 ($270.00)
Furnish and install 6"ductile
iron water main(relay)with
polywrap;complete as Linear
4002 specified Feet 103.00 79.67 -23.33 $90.00 ($2,099.70)
Furnish and install 8"ductile
iron water main(relay)with
polywrap;complete as Linear
4004 specified Feet 1,460.00 1,522.50 62.50 $85.00 $5,312.50
Furnish and install 1"water
service(relay);complete as Linear
4036 specified Feet 1,188.00 1,393.00 205.00 $60.00 $12,300.00
Furnish and install 1"water
service(new);complete as Linear
4042 specified Feet 72.00 38.00 -34,00 $65.00 $2,210.00)
Furnish and install 1"
corporation and stop box;
4048 complete asspecified Each 46.00 1 46.00 $500.00
Furnish and install water
service clay dams;complete
4055 as specified Each 46.00 46.00 $95.00
Furnish and install
connections to existing 4"
water main;complete as
4056 specified Each 1.00 1.00 $1,500.00
Furnish and install
connections to existing 6"
water main;complete as
4058 specified Each 2.00 2.00 $1,600,00
Page 3 of 5
CONTRACT 17-04 EVELINE STREET CHANGE ORDER#1 (FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Furnish and install
connections to existing 8"
water main;complete as
4060 specified Each 1.00 1.00 $1,800.00
Furnish and install 6"x 6"
water main tee;complete as
4101 specified Each 1.00 1.00 $460.00
Furnish and install 8"x 6"
water main tee;complete as
4110 specified Each 5.00 4.00 1 -1.00 $450.00 ($450.00)
Furnish and install 8"x 8"
water main tee;complete as
4111 _specified Each 2.00 2.00 $550,00
Furnish and install 4"45
degree water main bend;
4235 _complete asspecified Each 2.00 2.00 $210.00
Furnish and install 6"45
degree water main bend;
4236 complete as specified Each 14.00 12.00 -2.00 $200.00 ($400.00)
Furnish and install 8"45
degree water main bend;
4237 _complete asspecified Each 2.00 2.00 $300.00
Furnish and install 8"x 4"
water main reducer;complete
4263 _as specified Each 1.00 1.00 1 $260.00
Furnish and install 8"x 6"
water main reducer;complete
4264 as specified Each 1.00 1.00 1 $225.00
Cut and cap existing 6"water
4352 main;complete asspecified Each 1.00 0.00 -1.00 $500.00 ($500,00)
Cut and cap existing 8"water
4354 main;complete as specified Each 1.00 0.00 -1.00 $600.00 ($600.00)
Furnish and install 6"water
main gate valve;complete as
4401 specified Each 7.00 7.00 1 $1,200.00
Furnish and install 8"water
main gate valve;complete as
4402 specified Each 9.00 10.00 1.00 $1,500.00 $1,500.00
Furnish and install hydrant;
4500 complete asspecified Each 4.00 4.00 $3,500.00
Remove water main; Linear
4920 complete asspecified Feet 40.00 40,00 $15.00
SECTION-(BID ITEMS 2002-4920)-SUBTOTAL $27,238.00 ($30,143.45)
NET DECREASE ($2,905.45)
ADDITIONAL WORK REQUIRED:CO#1
ITEM DESCRIPTION UNIT BID INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Furnish and install 8"x 6"
sanitary sewer factory wyes
or tees;complete as
1-3210 Ispecified Each 1 0.00 46.00 46.00 $140.00 $6,440.00
Page 4 of 5
CONTRACT 17-04 EVELINE STREET CHANGE ORDER#1 (FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE CONTRACT PRICE
Furnish and install
connection to existing 10"
1-3302 mains;com fete asspecified Each 0.00 1.00 1.00 $1,000.00 $1,000.00
Furnish and install 6"11.25
degree water main bend;
1-4218_complete asspecified Each 0.00 1.00 1.00 $300.00 $300.00 —ADDITIONAL WORK:CO#1 (ITEMS 1-3210-1-4218)-SUBTOTAL $7,740.00 $0.00
NET INCREASE $7,740.00
NET INCREASE TO SECTION $34,978.00
NET DECREASE TO SECTION ($30,143.45)
NET INCREASE TO CONTRACT: $4,834.55
Page 5 of 5