HomeMy WebLinkAboutChange Order No 1- Vinton Construcation Co J)
I A &
r
City
ofv
Oshkosh
October 8, 2018
Mr. Ron Raboine
Vinton Construction Company
PO Box 1.987
Manitowoc, WI 54221-1987
RE: Change Order No. 1
Contract 17-19
Dear Mr. Raboine:
Enclosed is an executed copy of Change Order No. 1 between the City of Oshkosh and Vinton
Construction Company regarding the abovementioned project.
If you have any questions, please call our office at (920)236-5065.
Sincerely,
mes Rabe, P.E., CPESC
Director of Public Works
JER/tlt
Enclosure: Change Order No. 1.
cc: Pam'Ubrig, City Clerk (w/original)
Jennifer Messerschmidt, Assistant Finance Director (w/copy)
File (w/original)
E\rngincering\2017 CONTRACT'S\17-19 Aviation Wtr MnVroject-Informat ion\Contract Info\Change
Orders\17-19 Executed C,'0#1-10-8-18.docx Page 1 of 1
City Hall,215 Church Avenue P.O. Box 1130 Oshkosh,WI 54903-1130 http://WWW,Ci.oShkosh.wi,us
TO: VINTON CONSTRUCTION COMPANY CHANGE ORDER#1
P.O. BOX 1987 DATE- SEPTEMBER 12, 2018
MANITOWOC, W1 54221-1987
Your present contract with the City of Oshkosh,Contract No. 17-19,awarded July 25,2017, is hereby amended
and changed as follows:
NET INCREASE: $137,990.00
NET DECREASE: $0.00
NET INCREASE TO CONTRACT $137,990.00
TOTALS
BID TOTAL 3.98 0'5*i-6.98
co#1 $137,990,00 $137,990.00
CONTRACT TOTAL $1,736,103.98 $1,736,103.98
CITY OF OSHKOSH
BY:
City Manager
�J
City Clerk
Approved and accepted:
�nYtractor
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin, under the
within Change Order.
J'
Comptroller
Approved form:
City Mtorneil')
VINTON CONSTRUCTION COMPANY...Road Contractors
An Equal Opportunity Employer
.!1►y. P.O. Box 1987
INTON -' 2705 N. Rapids !l oad
-' ""'` Manitowoc, Wisconsin 54221-1987
- Office 920-682-0376
Fax 920-682-2838
Attn : Justin Gierach, P.E. 8/31/2018
City of Oshkosh - Engineering Division
Re: Project 17-19
Aviation Business Park Water Main Loop
RE: Field Order 1
Install the Ripple Ave Pressure Regulating Valve (PRV) Station
Work to include as follows:
Notice of Mobilization
Coordinate Flushing of water main
Coordinate delivery of owner purchased materials
Off load materials
Excavate, shoring, subbase and concrete foundation slab, Set PRV Station and anchor to slab.
Furnish and Install Connections and valuing to connect PRV Station to system, including disinfection
Install sump pump discharge and exhaust system supply and piping external to Vault
Coordinate electric Service with WPS(WPS fees paid by City)
Provide and install electrical system per installation drawings
Install Cathodic Protection System
Provide and install telemetry antenna pole. Coordinate and assist Radio Communication Supplier.
Barricading and protecting the site
Restore work site as required
Total $ 137,990.00
If a 3" OD pole is required for and Antenna at
the Waukau Site ADD $6,752�00
if you have any questions please feel to call.
Sincerely,
Ronald J. Raboine
Vinton Construction Co.
CONTRACT 17.19 CHANGE ORDER#1
AVIATION BUSINESS PARK WATER MAIN LOOP
ADDITIONAL WORK REQUIRED:CO#1
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT
Install the Ripple Avenue
Pressure Regulating Valve
(PRV)Station;complete as
FO1 Ispecified I Stations 1 0.00 1 1.00 1 1.00 $137,990.00 1 $137,990.00
$137,990.00 $0.00
NET INCREASE: $137,990.00
NET INCREASE $137,990.00
NET DECREASE $0.00
NET INCREASE TO CONTRACT: _$137,990.00
Page 1 of 1