HomeMy WebLinkAboutChange Order No 2 DornerCityof
Oshkosh
March 31, 2020
Mark Schleis
PTS Contractors
4075 Eaton Road
Green Bay, WI 54311
RE: Change Order No. 2 (Final)
Contract 19-05
Dear Mark:
Enclosed is an executed copy of Change Order No. 2 (Final) between the City of
Oshkosh and Dorner, Inc. regarding the abovementioned project.
If you have any questions, please call our office at (920)236-5065.
Sincerely,
kRabe,P.Eor of Public Works
JER/t1t
Enclosure: Change Order No. 2 (Final)
cc: Pam Ubrig, City Clerk (w/original)
Jennifer Messerschmidt, Assistant Finance Director (w/copy)
File (w/original)
L\Engineering\2019 CONTEAM\1"52nd Paving\Projen_Irdonnation\Contract irdoWhange
orders\19-05 Executed CO A2 (FiM) Ltr_331-20.doa
Page 1 of 1
City Hall, 215 Church Avenue P.O. Box 1130 Oshkosh, WI 54903-1130 http://www.cl.oshkosh.wi.us
TO: PTS CONTRACTORS, INC.
4075 EATON ROAD
GREEN BAY, WI 54311
CHANGE ORDER #2 (FINAL)
DATE: FEBRUARY 28, 2020
Your present contract with the City of Oshkosh, Contract No. 19-05, awarded February 26, 2019, is hereby amended
and changed as follows:
NET DECREASE TO SECTION I: ($114,537.17)
NET DECREASE TO ALTERNATE 2: ($5,478.00)
NET INCREASE TO SECTION I: $4.054.61
NET DECREASE TO CONTRACT
($115,960.56)
SECTION I
TOTALS
BID TOTAL
$7,258,523.29
$7,258,523.29
CO #1
$192,625.55
$192,625.65
PREVIOUS CONTRACT TOTAL
$7.451,148.84
$7,451,148.84
CO#2
($115,960.56)
($115,960.56)
CONTRACT TOTAL
$7,335,188.28
$7,335,188.28
CITY OF OSHKOSH
BY:
Approved and acc pted:
Contractor
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin,
under the within Change Order. ,/
Comptroger
Approved a form:
City Aft
CONTRACT 19-05 CHANGE ORDER N2 (FINAL)
19-05
ITEM
DESCRIPTION
UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT
DECREASE IN
CONTRACTPRICE
NUMBER
PRICE
Mobilization; complete as
Lump
1050
specified
Sum
1.00
1.00
$532,000.00
Removing pavement;
Square
1100
complete asspecified
Yards
17,300.00
17.211.00
-89.00
$2.75
$244.75
Removing concrete and
asphalt sidewalk and
driveway; complete as
Square
1120 ispecified
Feet 1
46,000.001
45.889.60
1
-110.40
$0.40
$44.15
Unclassified excavation;
Cubic
1200
complete asspecified
Yards
3,950.00
3,932.20
-17.80
$15.75
$280.35
Excavation special (paving);
1220
complete ass specified
Tons
500.00
0.00
-500.00
$12.25
$6,125.00
concrete pavement HES;
�7"
with 5" CABC and grading;
Square
1303
complete ass specified
Yards
500.00
576.10
76.10
$65.20
$4,961.72
8" concrete pavement HES;
with 6" CABC and grading;
Square
1313
complete ass specified
Yards
590.00
577.00
-13.00
$65.70
$854.10
8" concrete pavement
doweled; with 6" CABC and
grading; complete as
Square
1314A
s ecified
Yards
6,850.00
11,702.30
4852.30
$51.00
$247,467.30
8" concrete pavement
doweled; HES; with 6" CABC
and grading; complete as
Square
1315
s ecified
Yards
7,450.00
2 557.30
-4,892.70
$53.25
$260,536.28
Concrete pavement gaps;
1334
complete as specified
Each
2.00
2.00
$1,025.00
Crushed aggregate base
course; complete as
1340
specified
Tons
1,550.00
51.80
-1,498.20
$6.15
$9,213.93
Pavement ties; complete as
1350
specified
Each
10.00
14.00
4.00
$8.20
$32.80
Drilled dowel bars; 1';
1352
complete as specified
Each
105.00
70.00
-35.00
$10.25
$358.75
Drilled dowel bars; 1 1/4";
1354
complete ass ecified
Each
75.00
93.00
18.00
$14.30
$257.40
manholes and inlets;
com lete ass ecified
Each
95.00
94.00
-1.00
$280.00
$280.00Turf
restoration; complete as
Square
s ecified
Yards
4,570.00
4.874.00
304.00
$9.20
$2,796.80
rAdjust
Restore gravel driveway/
Square
apron: complete ass specified
Yards
140.00
195.10
55.10
$11.25
$619.88
Cold weather covering
(concrete pavement) - single
visquine; complete as
Square
1380
specified
Yards
3,000.00
0.00
-3,000.00
$0.01
$30.00
Up -charge for late season
cold weather concrete
pavement; complete as
Cubic
1390
specified
Yards
670.00
0.00
-670.00
1 $5.12
$3,430.40
12" radius curb with 6" CABC
and grading; complete as
Linear
1410
specified
Feet
500.00
483.10
-16.90
$11.25
$190.13
30" curb and gutter; 8", with
6" CABC and grading;
Linear
1442
complete ass ecified
Feet
210.00
206.70
-3.30
$31.70
$104.61
Page 1 of 13
CONTRACT 19-05 CHANGE ORDER #2 (FINAL)
ITEM
DESCRIPTION
UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT
DECREASE IN
COMRACTPRICE
NUMBER
PRICE
30" curb and gutter; 8"; with
6" CABC and grading;
Linear
1443
complete as specified
Sidewalk curb; complete as
Feet
5,526.00
5,472.40
-52.60
$15.80
$831.08
Linear
1460
specified
Feet
250.00
197.80
-52.20
$50.00
$2,610.00
4" concrete sidewalk with 3"
CABC and grading; complete
Square
1500
asspecified
Feet
25,550.00
26.610.00
1060.00
$5.75
$6,095.00
6" concrete sidewalk/
driveway/ramp with 3" CABC
and grading; complete as
Square
1510 ispecified
Feet 1
11,070.00
10.607.10
-462.90
$6.00
$2,777.40
concrete sidewalk/
16"
driveway/ramp (HES) with 3"
CABC and grading; complete
Square
1514
asspecified
Feet
5,050.001
4848.40
-201.60
$6.30
$1,270.08
8" concrete sidewalk/
driveway/ramp with 3" CABC
and grading; complete as
Square
1520
specified
Feet
1,360.00
1.589.70
229.70
$7.00
$1,607.90
6" concrete step; complete as
Square
1530
specified
Feet
345.00
232.50
-112.50
$51.00
$5,737.50
Curb ramp detectable
warning field (natural/non-
painted); complete as
Square
1540
specified
Feet
192.00
200.00
8.00
$32.70
$261.60
No. 4 reinforcing rods -
deformed, epoxy -coated;
Linear
1550
Complete asspecified
Feet
5,140.00
4,950.00
-190.00
$1.25
$237.50
Drilled No. 4 sidewalk tie bars
- deformed, epoxy -coated;
1560
complete ass ecified
Each
425.00
301.00
-124.00
$4.60
$570.40
Cold weather covering
(sidewalk) - single visquine;
Square
1580
complete asspecified
Feet
81400.00
0.00
-8,400.00
$0.50
$4,200.00
Up -charge for late season
cold weather concrete
1
pavement; complete as
Cubic
1590
specified
Yards
130.00
0.00
-130.00
$9.20
$1,196.00
Locate existing property
monuments; complete as
1650
specified
Each
30.00
43.00
13.00
$128.00
$1,664.00
Replace section corner;
1651
complete asspecified
Each
2.00
2.00
$410.00
Replace existing property
monuments; complete as
1652
specified
Each
20.00
39.00
19.00
$51.00
$969.00
Sawing existing pavement;
Linear
1700
complete ass specified
Feet
1,275.00
1,288.00
13.00
$2.00
$26.00
Sawing concrete pavement
full depth; complete as
Linear
1710
S13ecified
Feet
255.00
339.001
84.00
1 $2.60
$218.40
Tack coat; complete as
1900
specified
Gallons
95.00
71.80
-23.20
$4.10
$95.12
4" asphaltic transition LT with
10" CABC and grading;
Square
1911
complete asspecified
Yards
1,195.00
1,259.90
64.90
$38.00
$2,466.20
4" asphaltic surface LT with
6" CABC and grading;
Square
1916
complete asspecified
Feet
150.00
147.60
-2.40
$46.00
$11 G.40
Page 2 of 13
CONTRACT 19-05 CHANGE ORDER #2 (FINAL)
m�rtcnucm DECREASEIN
CONTRACT INSTALLED NET NET UNIT CONTRACT CONTRACTPRICE
ITEM DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE
NUMBER
2" asphaltic surface LT with
6" CABC and grading; Square _ tog RR ($6.412.50'
cold weather I Square
Pavement marking epoxy; 8"
Linear
$2.0C
1974
white ; wm late ass ecified
Feet
4,940.00
4,606.80
-333.20
Pavement marking epoxy; 4"
Linear
$2.0(
1975
white ; com late as s ecified
Feet
5,450.00
5,522.00
72.00
Pavement markings epoxy;
4" (yellow); complete as
Linear
$4.01
1976
s ecified
Feet
260.00
267.50
7.50
Pavement markings parking
stall epoxy; 4" (white);
Linear
$6.01
1977
com fete ass ecified
Feet
565.00
542.00
-23.00
Pavement markings epoxy;
12" (white); complete as
Linear
Feet
175.00
153.80
-21.20
$9.0
1978
s ecified
Pavement markings arrow
epoxy; Type 2 (white);
Linear
$128.0
1980
complete ass ecified
Feet
3.00
3.00
Pavement markings; word
epoxy; Type 2 (white);
Linear
$180.0
1983
wm Iete ass ecified
Feet
2.00
2.00
Fumish and in10" storm
Linear
$96.(
2002
sewer; com late ass ecified
Feet
5.00
11.00
6.00
Fumish and install 12" storm
Linear
$80.(
2003
sewer; com late ass ecified
Feet
725.00
719.80
-5.20
Furnish and install 15" storm
Linear
$65.(
2006
sewer; com late ass ecified
Feet
325.00
325.30
0.30
Furnish and install 18" storm
Linear
$69.1
2009
sewer; com late as specified
Feet
11450.00
1,420.50
-29-50
Furnish and install 21"storm
Linear
$84.i
2012
sewer; com late ass ecified
Feet
350.00
344.20
-5.80
Furnish and install 24" storm
Linear
2015
sewer; com late ass ecified
Feet
500.00
496.10
-3.90�$$1822.
Furnish and install 36" storm
Linear
$ 80
2024
sewer; com late ass ecified
Feet
110.00
101.20
Furnish and install 54" storm
Linear
97.30
12 70
$181
2033
sewer; com late ass ecified
Feet
110.00
Furnish and install 34" x 53"
HERCP Class III storm
Linear
2053
sewer, com let ass ecified
Feet
z9u.uu
GOO.oU
Furnish and install W x 60"
HERCP Class III storm
Linear
20.00
8.00
-12.00
$2,076.00
2055
sewer; complete as s ecifeid
Feet
Furnish and install 48" x 76"
#$356.00
J$416.52
2059
HERCP Class III storm
sewer; complete ass ecified
Linear
Feet
80.00
78.50
-1 50
$270.00
Furnish and install standard
storm sewer manhole (4'
diameter); complete as
Vertical
48.75
49.92
1.17
2201
s cified
Feet
Page 3 of 13
CONTRACT 19-05 CHANGE ORDER #2 (FINAL)
CONTRACT INSTALLED
NET
NET
INCREASEIN DECREASEIN
UNIT CONTRACT CONTRACTPRICE
ITEM DESCRIPTION
UNIT QUANTITY QUANTITIES INCREASE
DECREASE
PRICE
PRICE
NUMBER
Furnish and install standard
storm sewer manhole (5'
diameter); complete as
Vertical
12.59
-0 Ot
$536.00
$5.36
2202 s ecified
Feet
12.60
Furnish and install standard
storm sewer manhole (6'
diameter); complete as
Vertical
4,29
0.19
$720.00
$136.80
2203 s ecified
Feet
4.10
Furnish and install standard
storm sewer manhole (8'
diameter); complete as
Vertical
8.78
0.38
$875.00
$332.50
2205 s ecified
Feet
8.40
Furnish and install standard
storm sewer manhole (7' x 7'
Vertical
0.50
$1,015.00
$507.50
2210 box; com late ass ecified
Feet
19.10
19.60
Furnish and install standard
storm sewer manhole (8' x 6'
Vertical
0.08
$1,800.00
$144.00
2211 box; complete ass ecified
Feet
26.85
26.93
Furnish and install standard
storm sewer inlet manhole (4'
diameter); complete as
Vertical
2.85
-0.60
$395.00
$237.00
2213 s ecified
Feet
3.45
Furnish and install Type 1
0.00
-1.00
$1,465.00
$1,465.00
2236 inlet; com late ass ecified
Each
1.00
Furnish and install Type 3
inlet (with 18" sump);
33.00
-1.00
$1,565.00
$1,565.00
2237 com late as s ecified
Each
34.00
Furnish and install 6" storm
sewer lateral; complete as
Linear
2,685.00
2,568.92
-116 OB
$62.00
$7,196.95
2400 s ecified
Feet
Furnish and install 8" storm
sewer lateral; complete as
Linear
-14.00
$76.00
$1,064.00
2402 s ecified
Feet
170.00
156.00
Furnish and install storm
sewer marker balls; complete
p0
$44.00
$176.00
2404 ass ecified
Each
155.00
151.00
.4
Furnish and install storm
sewer clay dams; complete
-g 00
$115.00
$345.00
2406 ass ecified
Each
78.00
75.00
Furnish and install storm
sewer lateral inlet; complete
-6.00
$476.00
$2,856.00
2408 ass ecified
Each
71.00
65.00
Storm lateral inlet
adjustments; complete as
71.00
9.00
-62.00
$23.00
$1,426.00
2414 s ecified
Each
Perforated drain tile;
Linear
0.00
-25.00
$36.00
$900.00
2416 com late ass ecified
Feet
25.00
Cleanouts; complete as
1.00
1.00
$488.00
2418 s ecified
Each
Furnish; install; maintain; and
remove Type D modified inlet
protection; complete as
107.00
83.00
-24 00
$72 00
$1,728.00
2508 s ecified
Each
Sediment removal -Type D
modified inlet protection;
107.00
16.00
_91 00
$6.00
$546.00
2510 complete ass ecified
Each
Page 4 of 13
CONTRACT 19-05 CHANGE ORDER #2 (FINAL)
ITEM DESCRIPTION
NUMBER
Furnish; install; maintain; and
remove stone tracking pad;
2512 complete asspecified
Furnish; install; maintain; and
remove stone bag; complete
UNIT I CONTRACT I INSTALLED
SEI NET I UNIT
QUANTT S INCREADECREASE PRICE
-emove 12" diameter
sediment logs; complete as I Linear
specified Feet
Furnish; install; maintain; and
remove ditch check;
com late ass ecified Each
Furnish; install; maintain; and
remove dewatering tank
system; complete as
as specinea
Abandon 8" -12" storm
sewer complete as specifie
Abandon 15" and larger
storm sewer; complete as
Ifiedve 30" and smaller sewer; complete asfiedve 33" - 60" stormr; com late ass ec�e
don storm seweroles and inlets;late ass ecifiedove storm sewerholes and inlets;late ass ecifiedned to existing stone
r main; complete asifiedned to existing storm
nr lateral: comDlete as
Linear
Linear
Feet
Linear
Feet
Linear
1
NCREASEIN DECREASEIN
CONTRACT CONTRACTPRICE
1S2R0.00)
2852
2856
s ecified
to existing storm
seanhole; complete as_1
s d
Stoewer utility line
CoEecifiled
Eachfuu.uu
Each.00
-
p0
--
$1,900.00
$1,900.00
op(ULO); complete as
-5.00
$230.00
$1,150.00
2914
s d
Each.00
Extion special (stone);
-200.00
$25.00
$5,000.00Fu
2950
cote as s ecified
and install 8" sanitaryse(relay);
Tons.00
complete as
Linear3000
-22.40
$100.00
$2,240.00Fuh
s d
Feet
.60
and install 12"sa
sewer (relay);
Linear20
$156.00
$967.203004
cote ass ecified
Feet4.80Furnish
and install 18"sanitary
sewer (relay);
Linear3008
-6.50
$157.00
$1,020.50
com lete ass ecified
Feet1.50
Page 5 of 13
CONTRACT 19-05 CHANGE ORDER #2 (FINAL)
ITEM
NUMBER
DESCRIPTION
UNIT
CONTRACT INSTALLED NET
QUANTITY QUANTITIES INCREASE
NET
DECREASE
UNIT
PRICE
Furnish and install 24"
sanitary sewer (relay);
Linear
7.00
10.50 3.50
$27i
3012
com late ass ecified
Feet
Furnish and install 8" sanitary
sewer (new); complete as
Linear
-2.00
$11
Feet
47.00
45.00
3030
s ecified
Furnish and install 8" sanitary
sewer drop; complete as
Vertical
-3 91
$37
Feet
47.00
43.09
3060
s ecified
Furnish and install 18"
sanitary sewer drop;
Vertical
5.00
4.67
0.33
$4E
3068
com late ass ecified
Feet
Furnish and install standard
sanitary sewer manhole (4'
diameter); complete as
Vertical
142.00
146.86 4.86
$2
3100
s ecified
Feet
Furnish and install external
sanitary sewer manhole
chimney seal; complete as
$4
3114
specified
Each
23.00
23.00
Furnish and install external
sanitary sewer manhole
chimney seal extension;
Each
2.00
0.00
-2.00
$4
3116
com late ass ecified
Furnish and install internal
sanitary sewer manhole
chimney seal; complete as
0.00
-1.00
$;
3118
s ecified
Each
1.00
Furnish and install internal
sanitary sewer manhole
chimney seal extension;
1.00
0.00
-1.0-
$
3120
com late ass ecified
Each
Install CITY supplied
manhole: complete as
Vertical
11.00
10.86
-0.14
$'
3149
s ecified
Feet
Famish and install 8" x 6"
INCREASEIN DECREASE IN
CONTRACT CONTRACT PRICE
sanitary sewer raccoiy wyca
or tees; complete as
Each
43.00
70.00
27.00
$ 96.00
$2,592.00
3210
s ecified
Furnish and install 12" x 6"
sanitary sewer factory wyes
or tees; complete as
1.00
0.00
-1 O0
$292.00
$292.00
3214
s ecified
Furnish and install 6" sanitary
Each
sewer "Inser-A-Tee" or " Kor-
N-Tee"; complete as
-4.00
$260.00
$1,040.00
Each
4.00
0.00
3222
s ecified
Furnish and in stall 4'y6"
sanitary sewer lateral (relay);
Linear
2,165.00
2,311.00
146.00
$100.00
$14,600.00
3234
com late ass ecified
Furnish and install 4"16"
Feet
sanitary sewer riser (relay);
Linear
20.00
102.00
82.00
$ 120.00
$9,840.00
3235
com late ass ecified
Furnish and install sanitary
Feet
sewer lateral marker balls;
157.00
159.00
2.00
$44.00
$88.00
3236
com late ass ecified
Furnish and install clay
Each
78.00
80.00
2.00
$115.00
$230.00
3238
dams; complete ass ecified
Each
Page 6 of 13
CONTRACT 19-05 CHANGE ORDER #2 (FINAL)
ITEM CONTRACT INSTALLED NET NET
DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE
NUMBER
Furnish and install sanitary
lateral extension (relay); Linear
Furnish and install
connection t0 existing 8"
300 mains; com fete ass ecifi
Furnish and install
connection to existing 12"
1304 mains; com late ass ecifi
Furnish and install
connection to existing 18"
sanitary sewer mains;
M8 com late ass ecifed
Furnish and install
connection to existing 24"
sanitary sewer mains;
3312 com late ass ecifed
Furnish and install
connection to existing 42"
sanitary sewer mains;
Each
concrete collars;
specified
Each
2.00
2.00
l 10"
en cutplete
;sewer
as
Linear
Feet
40.00
20.00
complete
Linear
Feet
3,570,00
3,001.7(
and damage survey;
e.e o�e'iflod
Each
100.00
92.0(
UNIT IMltlh ov DECREASE IN
PRICE CONTRACT CONTRACTPRICE
PRICE
using push camera; compinrc
5.00 10.00
5.00
$350.00
$1,75U.UU
3710
as s ecifed
Abandon sanitary sewer
Each
manholes; complete as
1.00 0.00
1 00
$780 00
$780.00
3800
s ecifed
Abandon 8" sanitary sewer;
Each
Linear
99.00 99.00
$14.30
3802
com late ass ecifed
Abandon 12" sanitary sewer;
Feet
Linear
24.70 24.70
$16.60
3806
complete as s ecified
Remove sanitary sewer
Feet
manholes; complete as
3.00 2.00
_ 1 p0
$870.00
$870.00
3852
s ecified
Remove sanitary sewer;
Each
Linear
233.00 233.00
$35.00
3854
com late ass ecified
Sanitary sewer utility line
Feet
opening (ULO); complete as
1.00
_2 Op
$500.00
$1,000.00
3890
s ecified
Excavation special (sanitary);
Each
3.00
$25.00
3892
com late asspecified
Furnish and install 4" ductile
Tons
4,621.63 4,521.63
iron water main (relay) with
polywrap; complete as
Linear
55.00 47.40
_7 60
$150.00
$1,140.00
4000
specified
Feet
Page 7 of 13
CONTRACT 19-05 CHANGE ORDER #2 (FINAL)
CONTRACT
INSTALLED
NET
NET
UNIT
INCREASE IN
CONTRACT
DECREASE IN
CONTRACTPRICE
ITEM
NUMBER
DESCRIPTION
UNIT
QUANTITY
QUANTITIES
INCREASE
DECREASE
PRICE
PRICE
and install 6" ductile
Furnish
iron
water main (relay) with
polywrap;
complete as
Linear
350.00
333.35
-16.65
$114.00
$1,898.10
4002 s
ecified
and install 8" ductile
Feet
Furnish
iron
water main (relay) with
polywrap;
complete as
Linear
3,450.00
3,429.95
-20.05
$95.00
$1,904.75
4004 s
ecified
and install 12" ductile
Feet
Furnish
iron
water main (relay) with
polywrap;
complete as
Linear
MOM
183.00
-17 00
$170.00
$2,890.00
4008 s
ecified
Furnish and install 1"water
Feet
service
(relay); complete as
Linear
2.628.00
2,404.50
-223.50
$78.00
$17,433.00
4036
s ecified
Furnish and install 2" water
Feet
service (relay); complete as
Linear
42.00
32.00
-10.00
$140.00
$1,400.00
4040
s ecified
Furnish and install 1"
Feet
corporation and stop box;
_2 00
$450.00
$900.00
4048
com late ass ecified
Furnish and install 2"
Each
80.00
78.00
corporation and stop box;
1.00
1.00
$1,280.00
4053
com fete ass ecified
Furnish and install water
Each
service clay dams; complete
80.00
77.00
-3.00
$116.00
$348.00
4055
ass ecified
Furnish and install
Each
connections to existing 4"
water main; complete as
1.00
1.00
$1,880.00
4056
s ecified
Furnish and install
Each
connections to existing 6"
water main; complete as
8.00
-1 p0
$1,940.00
$1,940.00
4058
s ecified
Furnish and install
Each
9.001
connections to existing 8"
water main; complete as
2.00
2.00
$2,300.00
4060
s ecified
Furnish and install
Each
connections to existing 12"
water main; complete as
2.00
2.00
$2,500.00
4064
s ecified
Furnish and install 8" x 4"
Each
water main tee; complete as
$375.00
4109
se cifed
Furnish and install 8" x 6"
Each
1.00
1.00
water main tee; complete as
9.00
_1 0p
$420.00
$420.00
4110
s ecified
Furnish and install 8" x 8"
Each
10.00
water main tee; complete as
4.00
$540.00
4111
s ecified
Furnish and install 12" x 6"
Each
4.00
water main tee; complete as
3.00
$765.00
4128
s ecified
Furnish and install 8" x 8"
Each
3.00
water main cross; complete
2.00
2.00
$690.00
4189
ass ecified
Furnish and install 8" x 12"
Each
water main cross; complete
1.00
1.00
$1,100.00
4191
ass ecified
Each
Page 8 or 13
CONTRACT 19-05 CHANGE ORDER #2 (FINAL)
CONTRACT INSTALLED NET
NET
INCREASE IN DECREASEIN
UNIT CONTRACT CONTRACTPRICE
ITEM DESCRIPTION
UNIT QUANTITY QUANTITIES
INCREASE
DECREASE
PRICE
PRICE
NUMBER
Furnish and install 4" 45
degree water main bend;
pp
$160.00
$320.00
4235 com late ass ecified
Each
2.00
0.00
_2
Furnish and install 6" 45
degree water main bend;
31.00
-15.00
$210.0-
$3,150.00
4236 com late ass ecified
Each
46.00
Furnish and install 8" 45
degree water main bend;
_2 pp
$290.00
$580.00
4237 com late as s ecified
Each
10.00
8.00
Furnish and install 12" 45
degree water main bend;
4.00
4.00
$645.00
4239 com late ass ecified
Each
Furnish and install 6" water
main cap; complete as
1.00
1.00
$110.00
4254 s ecified
Each
Furnish and install 8" x 6'
water main reducer; complete
$250.00
$250.00
4264 ass ecified
Each
8.00
7.00
-1.00
Cut and cap existing 6" water
1.00
7.00 6.00
$100.00
$600.00
4352 main; com late ass ecified
Each
Cut and cap existing 8" water
0.00
-1.00
$100.00
$100.00
4354 main; com late ass ecified
Each
1.00
Cut and cap existing 12"
water main; complete as
2.00
0.00
_2 pp
$100.00
$200.00
4358 s ecified
Each
Furnish and install 4" water
main gate valve; complete as
1.00
$1,000.00
4400 specified
Each
1.00
Furnish and install 6" water
main gate valve; complete as
14.00
14.00
$1,120.00
4401 s ecified
Each
Furnish and install 8" water
main gate valve; complete as
29.00 1.00
$1,580.00
$1,580.00
4402 s ecified
Each
28.00
Furnish and install 12" water
main gate valve; complete as
4.00
$2,570.00
4404 s ecified
Each
4.00
Furnish and install hydrant;
11.00
11.00
$3,940.00
4500 com late ass ecified
Each
Furnish and install 2" water
main casing pipe; complete
Linear
$54.00
4712 ass ecified
Feet
10.00
10.00
Furnish and install 4" water
main casing pipe; complete
Linear
$66.00
4714 ass ecified
Feet
10.00
10.00
Furnish and install 10" water
main casing pipe; complete
Linear
$66.00
$1,320.00
4720 ass ecified
Feet
20.00
0.00
-20.00
Furnish and install 18" water
main casing pipe; complete
Linear
-6.00
$98.00
$588.00
4726 ass ecified
Feet
40.00
34.00
Rock excavation; complete
Linear
237.00
175.00
-62.00
$0.01
$0.62
4801 ass ecified
Feet
Abandon water main on
Oregon Street; complete as
Lump
1.00
$6,000.00
4900 s ecified
Sum
1.00
Remove water main;
Linear
920.00
920.00
$34.00
4920 com late ass ecified
Feet
Page 9 of 13
CONTRACT 19-05 CHANGE ORDER #2 (FINAL)
ITEM
NUMBER
DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
on special (water); -25.00 $2'
e� enoeifiwd Tons 25.00 0.00
VCREASEIN DECREASEIN
CONTRACT CONTRACT PRICE
Furnish and install pull box
(non-conductive); 18" x 36"; _1 pp $1,480.00 $1,480.00
013 complete ass specified Each 33.00 32.00
Furnish and install pull box
(nonconductive); 24" x 42"; -1.00 :$1,5
30.00 $1,530.00
,019 comp late ass ecified Each 12.00 11.00
Cdh.st nnll hox: complete as .. __ .. ne nn 1R5 R32.001
pull box; complet
fled
:concrete base;
e as specified
and install control
complete as
Furnish and install 2"
Schedule 40 PVC; complete
Linear
20
ass ecified
Furnish and install 3"
Feet
3,
Schedule 40 PVC; complete
Linear
Feet
7
Furnish and install 4 gauge
red -coated wire; complete as
Linear
ed
Furnish and install 4 gauge
Feet
coated wire; complete
Linear
cified
h and install 6 gauge
WecifiedFeet
Feet
ated wire; complete as
Linear
fied
and install 6 gauge
Feeth
....��uA u im- emm�letP
a Linear
5261
1
-1.00
-1.00
Ito qna nm
s ecified
Feet
3,640.00
1,434.00
-�.���•��
Furnish and install 8 gauge
green -coated wire; complete
Linear
3.00
$1 pp
$3.00
ass ecified
Feet
7,500.00
7,503.00
Furnish and install 10 gauge
red -coated wire; complete as
Linear
$0.60
$19.80
s ecified
Feet
620.00
587.00
-33.00
Furnish and install 10 gauge
black -coated wire; complete
Linear
-33.00
$0.60
$19.80
ec� as s ed
Feet
620.00
587.00
Furnish and install 10 gauge
green -coated wire; complete
Linear
$0.60
$9.60
ass ecified
Feet
880.00
864.00
-16.00
Furnish and install 12 gauge
red -coated wire; complete as
Linear
640.00
720.00
80.00
$0.60
$48.00
s cified
Feet
Furnish and install 12 gauge
black -coated wire; complete
Linear
640.00
720.00
80.00
$0.60
$48.00
ass ecified
Feet
Page 10 of 13
CONTRACT 19-06 CHANGE ORDER #2 (FINAL)
INCREASEIN DECREASEIN
UNIT
CONTRACT INSTALLED NET
ITEM DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE
NET
DECREASE
CONTRACT CONTRACTPRICE
PRICE PRICE
NUMBER
Furnish and install 12 gauge
green -coated wire; complete Linear
640.00
720.00 80.00
$0.60
$48.00
5272 ass ecified Feet
Furnish and install 14 gauge
green -coated wire; complete Linear
3'I MOO 3,135.00
25.00
$0.60
$15.00
5282 ass ecified Feet
Furnish and install 14 gauge
stranded single pair twisted
with shield; complete as Linear
780.00
760.00
-20.00
$1.50
$30.00
5356 s ecified Feet
Furnish and install 14 AWG
solid 3 conductor; complete Linear
-15.00
$1.25
$18.75
5360 as ecified Feet
60.00
45.00
Furnish and install 14 AWG
solid 5 conductor; complete Linear
-20.00
$1.50
$30.00
5362 ass ecified Feet
90.00
70.00
Furnish and install 14 AWG
solid 7 conductor; complete Linear
0.00
-180.00
$1.50
$270.00
5364 ass ecified Feet
180.00
Furnish and install 14 AWG
solid 9 conductor; complete Linear
291.00 81.00
$2 p0
$162.00
5366 ass ecified Feet
210.00
Furnish and install 14 AWG
solid 21 conductor; complete Linear
1,140.00
1,206.00 66.00
$3.60
$237.60
5372 as ecified Feet
Furnish and install fuse
70.00
68.00
_2 pp
$51.00
$102.00
5380 holder; com late ass ecified Each
Furnish and install 5A fuse;
70.00
68.00
_2 0p
$5.00
$10.00
5392 com late ass ecified Each
Install single head fixture;
City Supplied'; complete as
2.00
2.00
$155.00
5400 s ecified Each
Install light pole and pole top
lights; "City Supplied";
33.00
33.00
$515.00
5410 com late ass ecified Each
Install 13' traffic signal pole
with a decorative base; "City
Supplied; complete as
3.00
5.00 2.00
$200.00
$400.00
5421 s ecified Each
Install 15traffic signal pole;
,,City Supplied'; complete as
2.00
-1.00
$200.00
$200.00
5422 s ecified Each
3.00
Install 20' traffic signal pole;
,,City Supplied"; complete as
1.00
$400.00
5424 s ecified Each
1.00
Install 30' traffic signal pole;
"City Supplied" complete as
1.00
$410.00
5426 s ecified Each
1.00
Install 25' trombone arm;
,,City Supplied" complete as
2.00
$335.00
5431 s ecified Each
2.00
Install five -head traffic signal;
,,City Supplied" complete as
7.00
7.00
$180.00
5434 s ecified Each
Install three -head traffic
signal; ,City Supplied"
2.00
2.00
$255.00
5436 com late ass ecified Each
Page 11 of 13
CONTRACT 19-05 CHANGE ORDER #2 (FINAL)
ITEM
NUMBER
5438
5440
5504
DESCRIPTION
UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET UNIT
DECREASE PRICE
INCREASEIN
CONTRACT
PRICE
DECREASEIN
CONTRACTPRICE
Install pedestrian signal; "City
Supplied"; complete as
6.00
6.00
$155.00
s ecified
Each
Install pedestrian push
button; "City Supplied";
$130.00
complete asspecified
Each
6.00
6.00
Furnish and install Type 2
-3.00 $900.00
$2,700.00
Base; com late ass ecified
Each
13.00
10.00
Furnish and install Type 5
$766.00
Base; corn late as s ecified
Each
33.00
33.00
Furnish and install Type 9
$5,100.00
Base; complete ass ecified
Each
2.00
2.00
SECTION I (BID ITEMS 1050 - 5506) - SUBTOTAL:
NET DECREASE TO SECTION I:
$314,129.32 ($428,666.49)
($114,537.17)
ALTERNATE 2
CONTRACT INSTALLED NET NET UNIT CONTRACT
DECREASE IN
CONTRACTPRICE
ITEM DESCRIPTION UNIT
QUANTITY QUANTITIES INCREASE DECREASE PRICE
NUMBER
Furnish and install 42"
sanitary sewer (new); Linear
Feet
3,010.00 3001.70 -8.30 $660.00
-$5,478.00
3048-2
wm late ass ecified
Furnish and install sanitary
sewer manhole junction
chamber 0-1; complete as
Each
1.00 1.00 $12,000.00
3113A-2
s ecified
Furnish and install sanitary
sewer manhole junction
chamber 0-3; complete as
1.00 $12,000.00
3113B-2
s ecified Each
Furnish and install sanitary
1.00
sewer manhole junction
chamber 0-4; complete as
1.00 $12,000.00
3113C-2
s ecified Each
Furnish and install sanitary
1.00
sewer manhole junction
chamber 0-5; complete as
1.00 $12,000.00
3113D-2
s ecified Each
Furnish and install sanitary
1.00
sewer manhole junction
chamber 0-6; complete as
1.00 $12,000.00
3113E-2
s ecified Each
Furnish and install sanitary
1.00
sewer manhole junction
chamber 0-8; complete as
1.00 $12,000.00
3113F-2
s ecified Each
Furnish and install sanitary
1.00
sewer manhole junction
chamber 0-9; complete as
1.00 $12,000.00
3113G-2
s ecified Each
Furnish and install sanitary
1.00
sewer manhole junction
chamber 0-10; complete as
1.00 $12,000.00
3113H-2
s ecified Each
1.00
Page 12 of 13
CONTRACT 19-05 CHANGE ORDER #2 (FINAL)
ITEM
CONTRACT
INSTALLED
NET
NET
UNIT
INCREASE IN
CONTRACT
DECREASE IN
NUMBER
DESCRIPTION
UNIT
QUANTITY
QUANTITIES
INCREASE
DECREASE
PRICE
PRICE
CONTRACT PRICE
ALTERNATE 2 (BID ITEMS 3048-2 - 3113H-2) - SUBTOTAL:
NET DECREASE TO ALTERNATE 2:
$0.00 ($5,478.UU)
($5,478.UU)
HUUI I I V 14Mu
V V V M, V
JNCREASEIN
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
INCREASE
NET
DECREASE
UNIT
PRICE
CONTRACT
DECREASE IN
CONTRACTPRICE
R NUMBER
QUANTITY
QUANTITIES
combined 8" relay
along existing sanitary sewer
alignment; complete as
Linear
s ecifed
Feet
732.00
732.00
$67.50
ECB#1
Individual 8" relay along
existing sanitary sewer
alignment; complete as
Linear
specified
Feet
300.00
300.00
$79.00
Furnish and install 12"
sanitary sewer drop at
manhole 0-4; complete as
Vertical
1-30002
specified
Feet
7.64
7.64
$420.00
Furnish and install bentonite
1-30003
1 dam; complete asspecified
Each
2.00
2.00
$2,007.00
Furnish and install small
bentonite dam 19th/Oregon;
1-30004
complete asspecified
Each
1.00
1.00
$1,252.00
ADDITIONAL WORK REQUIRED: CO #1 (BID ITEMS 1-30000 - 1-30004) - SUBTOTAL:
NET INCREASE:
$0.00 $0.00
$0.00
HUUI I I V IIryL
ITEM
NUMBER
V V V MM nCW UIn"V. — me
DESCRIPTION
UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT
PRICE
DECREASEIN
CONTRACTPRICE
Time and materials for storm
sewer plates; complete as
2-20000
specified
0.00
1.00
1.00
$2,929.03
$2,929.03
Time and materials for
Lsmm
setting hydrant at 17th
intersection; complete as
2-40000
s ecifed
0.00
1.00
1.00
$1,125.58
$1,125.58
ADDITIONAL WORK REQUIRED: CO #2 (BID ITEMS 2-20000 - 2-40000) - SUBTOTAL: $4,054.61 $0.00
NET INCREASE: $4,054.61
NET DECREASE TO SECTION I: ($114,537.17)
NET DECREASE TO ALTERNATE 2: ($5,478.00)
NET INCREASE TO SECTION I: $4,054.61
NET DECREASE TO CONTRACT: ($115,960.56)
Page 13 of 13