HomeMy WebLinkAboutChange No 2- Al Dix ConcreteCityof
Oshkosh
March 23, 2020
Al Dix
Al Dix Concrete, Inc.
401 Gertrude Street
Kaukauna, WI 54130
RE: Change Order No. 2 (Final)
Contract 18-06
Dear Al:
Enclosed is an executed copy of Change Order No. 2 (Final) between the City of Oshkosh and
Al Dix Concrete, Inc. regarding the abovementioned project.
If you have any questions, please call our office at (920)236-5065.
Sincerely,
2es Rabe, P.E., CPESC /
Director of Public Works
JER/t1t
Enclosure: Change Order No. 2 (Final)
cc: Pam Ubrig, City Clerk (w/original);
RECEIVED
Jennifer Messerschmidt, Assistant Finance Director (w/copy) MAR 2 3 2020
File (w/original)
CITY CLERK'S OFFICE
I:\E Oeedn8U018CONrRACrS\18-06Sidewalk Rehab\ProjecLWomadw\contracthtfo\Gang. Page 1 of 1
Orders\1806 Ez Ied CO n (Final) Ltr-;1-73-28.doa
City Hall, 215 Church Avenue P.O. Box 1130 Oshkosh, WI 54903-1130 http://www.ci.oshkosh.,Wi.us
TO: AL DIX CONCRETE, INC.
401 GERTRUDE STREET
KAUKAUNA, WI 54130
CHANGE ORDER #2 FINAL
DATE: FEBRUARY 14, 2020
Your present contract with the City of Oshkosh, Contract No. 18-06, awarded March 27, 2018, is hereby amended
and changed as follows:
NET DECREASE TO UNIT A:
($12,749.92)
NET DECREASE TO UNIT B:
$0.00
NET DECREASE TO UNIT C:
$0.00
NET INCREASE DUE TO ADDITIONAL WORK REQUIRED:
$0.00
NET DECREASE TO CONTRACT ($12,749.92)
SECTION I
TOTALS
BID TOTAL
$1,279,130.00
$1,279,130.00
CO #1
$300,691.64
$300,691.64
PREVIOUS CONTRACT TOTAL
$1,579,821.64
$1,679,821.64
CO#2
($12,749.92)
($12,749.92)'
CONTRACTTOTAL
$1,567,071.72
$1,667,071.72
CITY OF OSHKOSH
M.
Approved and accepted:
Contractor
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin,
under the within Change Order.
Comptrpi er
CONTRACT 18-06 CHANGE ORDER 02 FINAL
18-06
VVUKR UM1I
M
INCREASE IN
DECREASE IN
ITEM
NUMBER I
DESCRIPTION
UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
CONTRACT
PRICE
CONTRACT
PRICE
Removing concrete and
asphalt sidewalk and
driveway; complete as
Square
A-1120
specified
Feet
133,796.74
130,796.79
-2,999.95
$1.50
$4499.92
7" concrete pavement
removal and replacement;
including sawing; pavement
ties; dowel bars; bond
breaker; integral curb and
fine grading; turf restoration;
and traffic control; complete
Square
A-1308
asspecified
Yards
91.27
91.27
$68.00
8" concrete pavement
removal and replacement;
including sawing; pavement
ties; dowel bars; bond
breaker; integral curb and
fine grading; turf restoration;
and traffic control; complete
Square
A-1318
asspecified
Yards
1,740.77
1.740.77
$75.00
8" concrete pavement HES
removal and replacement;
including sawing; pavement
ties; dowel bars; bond
breaker; integral curb and
fine grading; turf restoration;
and traffic control; complete
Square
A-1319
ass ecified
Yards
181.17
181.17
$83.00
Adjust manholes and inlets;
A-1360
complete as sDecified
Each
6.00
6.00
$400.00
Turf restoration; complete as
Square
A-1370
specified
Yards
94.97
94.97
$12.00
Up -charge for late season
cold weather concrete
:j_
pavement; complete as
Cubic
A-1390
specified
Yards
171.32
171.32
$9.00
12' radious curb with 6"
CABC and grading; complete
Linear
A-1410
asspecified
Feet
0.00
0.00
$12.00
18" concrete curb and gutter
removal and replacement;
including sawing; pavement
ties; dowel bars; bond
breaker; integral curb and
fine grading; turf restoration;
and traffic control; complete
Linear
A-1428
asspecified
Feet
304.30
304.301
$65.00
30" concrete curb and gutter
removal and replacement;
including sawing; pavement
ties; dowel bars; bond
breaker; integral curb and
fine grading; turf restoration;
and traffic control; complete
Linear
A-1448
asspecified
Feet
2,985.601
2,985.60
$68.00
Page 1 of 5
CONTRACT 18-06 CHANGE ORDER #2 FINAL
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
UNIT
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
NUMBER
QUANTITY
QUANTITIES
INCREASE
DECREASE
PRICE
PRICE
PRICE
Sidewalk curb; complete as
Linear
A-1460
specified
Feet
538.70
538.70
$50.00
4" concrete sidewalk with 3"
CABC and grading; complete
Square
A-1500
a specified
Feet
90,513.67
90.513.67
$4.50
4" concrete sidewalk with 3"
CABC and grading; in
existing subdivisions;
Square
com lete a s ecified
Feet
8,910.30
8.910.30
$5.25
E
4" concrete sidewalk with 3"
CABC and grading; water
dept. locations; complete a
Square
specified
Feet
1,832.69
1,832.69
$8.00
6" concrete
sidewalk/driveway /ramp with
3" CABC and grading;
Square
A-1510
complete asspecified
Feet
40,156.33
40,156.33
$6.25
6" concrete
sidewalk/driveway /ramp with
3" CABC and grading; water
dept. locations; complete as
Square
A-1512
specified
Feet
976.78
976.78
$8.75
8" concrete
sidewalk/driveway /ramp with
3" CABC and grading;
Square
A-1520
complete asspecified
Feet
3,709.85
2,709.85
-1,000.00
$8.25
$8,250.00
6" concrete sidewalk with 3"
CABC and grading; London
Paver Pattern; complete as
Square
A-1526
specified
Feet
62.80
62.80
$65.00
Curb ramp detectable
warning field (natural/non-
painted); complete as
Square
A-1540
specified
Feet
560.00
560.00
$35.00
No. 4 reinforcing rods -
deformed; epoxy -coated;
Linear
A-1550
complete ass specified
Feet
544.00
544.00
$2.50
Drilled No. 4 sidewalk tie bars
- deformed; epoxy -coated;
A-1560
complete asspecified
Each
9,298.00
9,298.00
$6.50
Cold weather covering
(sidewalk) - single visquine;
Square
A-1580
complete asspecified
Feet
0.00
0.00
$1.00
Cold weather covering
(sidewalk) - double visquine;
Square
A-1582
complete asspecified
Feet
0.00
0.00
$1.00
(sidewalk) - double visquine
with 6" hay; complete as
Square
specified
Feet
0.00
0.00
$1.00
Up -charge for late season
cold weather concrete
sidewalk; complete as
Cubic
E1700
specified
Yards
0.00
0.00
$9.00
Sawing existing pavement;
Linear
complete ass specified
Feet
2.046.40
2,046.40
$5.00
Profile saw cut concrete curb;
Linear
complete ass specified
Feet
39.00
39.00
$50.00
Page 2 of 5
CONTRACT 18-06 CHANGE ORDER #2 FINAL
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
UNIT
INCREASE IN
CONTRACT
DECREASE IN
CONTRACT
NUMBER
QUANTITY
QUANTITIES
INCREASE
DECREASE
PRICE
PRICE
PRICE
Re -grade existing gravel
driveways; complete as
Square
A-1820
specified
Feet
0.00
0.00
$20.00
5" asphaltic surface MT with
6" CABC and grading;
Square
A-1915
lcomplete asspecified
Yards
1 0.00
0.00
$65.00
4" asphaltic surface LT with
6" CABC and grading;
Square
A-1916
complete asspecified
Yards
494.13
494.13
$65.00
2" asphaltic surface LT with
6" CABC and grading;
Square
A-1917
complete asspecified
Yards
218.40
218.40
$65.00
WORK UNIT A (BID ITEMS A-1120 - A-1917) - SUBTOTAL: $0.00 ($12,749.92)
NET DECREASE TO WORK UNIT A: ($12,749.92)
WORK UNIT R
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
I
NET
UNIT
CONTRACT
CONTRACT
NUMBER
QUANTITY
QUANTITIES
INCREASE
DECREASE
PRICE
7" concrete pavement
removal and replacement;
including sawing; pavement
ties; dowel bars; bond
breaker; integral curb and
fine grading; turf restoration;
and traffic control; complete
Square
B-1308
asspecified
Yards
1 818.301
818.30
818.30
$68.00
Crushed aggregate base
course; complete as
B-1340
s ecified
Tons
112.78
112.78
112.78
1 $20.00
Adjust manholes and inlets;
1
B-1360
com fete as s ecified
Each
0.00
0.00
0.00
$400.00
WORK UNIT B (BID ITEMS B-1308 - B-1360) -SUBTOTAL: $0.00 $0.00
NET INCREASE TO WORK UNIT B: $0.00
WORK UNIT C
DESCRIPTION
UNIT
CONTRACT
QUANTITY
INSTALLED
QUANTITIES
NET
INCREASE
NET
DECREASE
UNIT
PRICE
INCREASE IN
CONTRACT
DECREISE IN
CONTRACT
Removing concrete and
asphalt sidewalk and
rITEM
driveway; complete as
Square
s ecified
Feet
784.00
784.00
$1.50
8" concrete pavement
removal and replacement;
including sawing; pavement
ties; dowel bars; bond
breaker; integral curb and
fine grading; turf restoration;
and traffic control; complete
Square
C-1318
lasspecified
I Yards
1 407.901
407.901
1
1 $75.00
Page 3 or 5
CONTRACT 18-06 CHANGE ORDER #2 FINAL
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
UNIT
ICREASEIN
CONTRACT
DECREASEIN
CONTRACT
NUMBER
QUANTITY
QUANTITIES
INCREASE
DECREASE
PRICE
PRICE
PRICE
8" concrete pavement HES
removal and replacement;
including sawing; pavement
ties; dowel bars; bond
breaker; integral curb and
fine grading; turf restoration;
and traffic control; complete
Square
C-1319 I
asspecified
Yards 1
0.00
0.00
1
$80.00
Crushed aggregate base
course; complete as
C-1340
specified
Tons
46.70
46.70
$25.00
Adjust manholes and inlets;
C-1360
complete asspecified
Each
0.00
0.00
$400.00
18" concrete curb and gutter
removal and replacement;
including sawing; pavement
ties; dowel bars; bond
breaker; integral curb and
fine grading; turf restoration;
and traffic control; complete
Linear
C-1428
asspecified
Feet
0.001
0.00
$65.00
30" concrete curb and gutter
removal and replacement;
including sawing; pavement
ties; dowel bars; bond
breaker; integral curb and
fine grading; turf restoration;
and traffic control; complete
Linear
C-1448
asspecified
Feet
100.00
100.00
$68.00
4" concrete sidewalk with 3"
CABC and grading; complete
Square
C-1500
a specified
Feet
457.20
457.20
$4.50
6" concrete sidewalk/
driveway/ramp with 3" CABC
and grading; complete as
Square
C-1510
specified
Feet
326.80
326.80
$5.25
Curb ramp detectable
warning field (natural/non-
painted); complete as
Square
C-1540
specified
Feet
24.001
24.00
$35.00
Drilled No. 4 sidewalk tie bars
- deformed; epoxy -coated;
C-1560
complete asspecified
Each
32.00
32.00
$6.50
Sawing existing pavement;
Linear
C-1700
complete asspecified
Feet
7.50
7.50
$5.00
WORK UNIT C (BID ITEMS C-1120 - C-1700) -SUBTOTAL: $0.00 $0.00
NET INCREASE TO WORK UNIT C: $0.00
AnnITInNAI WORK RFOI IIRFIP
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
UNIT
CONTRACT
CONTRACT
NUMBER
QUANTITY
QUANTITIES
INCREASE
DECREASE
PRICE
Cold Weather Covering
(concrete pavement) - Single
Square
1-1380
Vis uine
Yards
617.86
617.86
$3.50
Page 4 of 5
CONTRACT 18-06 CHANGE ORDER #2 FINAL
ITEM
DESCRIPTION
UNIT
CONTRACT
INSTALLED
NET
NET
UNIT
ICREASEIN
CONTRACT
DECREASEIN
CONTRACT
NUMBER
QUAN77TY
QUANTITIES
INCREASE
DECREASE
PRICE
PRICE
PRICE
Extra time and materials to
remove and fill the vaults
within the righ-of-way on
Brown Street and High
Lump
1-10000
Avenue
Sum
1.00
1.00
$2000.00
Extra time and materials to
pour light bases within
Lump
1-10001
Isidewalk rehab areas
I Sum
1 1.00
1 1.00
1
$2,900.00
Extra work for using a power
buggy to transport concrete
Lump
1-10002
through side yards
Sum
1.00
1.00
$250.00
ADDITIONAL WORK REQUIRED: CO #1 (BID ITEMS 1-1380 - 1-10002) - SUBTOTAL: $0.00 $0.00
NET INCREASE DUE TO ADDITIONAL WORK REQUIRED: $0.00
NET DECREASE TO WORK UNIT A
NET INCREASE TO WORK UNIT B
NET INCREASE TO WORK UNIT C
NET INCREASE DUE TO ADDITIONAL WORK REQUIRED:
NET DECREASE TO CONTRACT:
($12,749.92)
$0.00
$0.00
$0.00
($12,749.92)
Page 5 of