HomeMy WebLinkAboutChange Order No 1 Vinton Construction CoTO: VINTON CONSTRUCTION COMPANY P.O. BOX 1987 MANITOWOC, WI 54221-1987 Your present contract with the City of Oshkosh, Contract No. and changed as follows: CHANGE ORDER #1 (REVISED) DATE: NOVEMBER 7, 2019 19-14, awarded July 9, 2019, is hereby amended NET INCREASE TO SECTION I: $120,017.80$6,222.00 NET INCREASE TO ADDITIONAL WORK: NET INCREASE TO CONTRACT $126,239.80 SECTION TOTALS BID TOTAL $1,033,693.40 $1,033,593.40 2201 $126,239.80 $126,239.80 CONTRACT TOTAL $1,159,833.20 $1,159,833.20 CITY OF OSHKOSH BY: y�L(i1 City Ma City Clerk Il/ Approved and acc pted: v Contractor I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin, under the within Change Order. Comptroller Approved _�. ' 1 9 _r CONTRACT 19-14 CHANGE ORDER NO. #1 (REVISED) 19-14 INCREAS DECREASE IN ITEM DESCRIPTION UNIT T CONTRACT INSTALLED NET NET UNIT CONTRACCTT CONTRACT QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE —PRICE Excavation special (paving); 1220 complete asspecified Tons 100.00 1,729.14 1629.14 $35.50 $57,834.47 Base aggregate dense; 3"; 1802 complete asspecified Tons 2,500.00 3,391.00 891.00 $12.00 $10.692.00 Furnish and install 18" storm Linear 2009 sewer; complete ass specified Feet 100.00 244.50 144.50 $74.00 $10,693.00 Excavation special (storm); I 2950 complete ass ecified Tons 292.00 1,629.65 1337.65 $30.50 $40,798.33 SECTION I (BID ITEMS 1220 .2960) - SUBTOTAL: NET INCREASE TO SECTION I: $120,017.80 $0.00 $120,017.80 MUUI I IVINYL vevnn nCVIlInCv. INCREASE IN DECREASE IN DESCRIPTION UNIT CONTRACT INSTALLED NET INCREASE NET DECREASE UNIT PRICE CONTRACT CONTRACT QUANTITY QUANTITIES Time and materials for removal of guard rail; Lump complete ass specified Sum 0.00 1.00 1.00 $1,302.00 $1,302.00 r1-5OOOO Furnish and install Click 2 Enter System; complete as Lump s ecified Sum 0.00 1.00 1.00 $2,825.00 $2,825.050% labor cost for cardaccess; complete as Lump s ecified Sum 0.00 1.00 1.00 $2,095.00 $2,095.00 ADDITIONAL WORK REQUIRED: CO #1 (BID ITEMS 1.10000 - 1-50001) - SUBTOTAL: $6,222.00 $0.00 NET INCREASE: $6,222.00 NET INCREASE TO SECTION I NET INCREASE TO ADDITIONAL WORK NET INCREASE TO CONTRACT: $120,017.80 $6,222.00 $126,239.80 Page 1 of 1