HomeMy WebLinkAboutChange Order No 1 Wood Sewer & ExcavatingTO: WOOD SEWER &EXCAVATING, INC. CHANGE ORDER #1 (FINAL)DATE: DECEMBER 18, 2019 E9238 CTY RD X NEW LONDON, WI 54961 Your present contract with the City of Oshkosh, Contract No. 19.20, awarded May 14, 2019, is hereby amended and changed as follows: NET INCREASE TO SECTION I: $9,743.79 NET DECREASE TO SECTION I: ($20,302.90) NET DECREASE TO CONTRACT ($10,559.11) SECTION I TOTALS BID TOTAL $599,814.06 $599,814.06 ($10,559.11) CO #1 ($10,559.11) CONTRACT TOTAL $539,264.95 $589,254.95 CITY OF OSHKOSH BY: !Cv City Man City Clerk Appr ad and accepted: Contractor Grey L.. VJOod I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh, Wisconsin, under the within Change Order. / f v - - Com rol r Approved s oform: n ' City Attorne P CONTRACT 19-20 CHANGE ORDER p1 (FINAL) 19-20 ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASEIN CONTRACT DECREASE IN CONTRACT NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE PRICE Removing pavement; Square 1100 complete asspecified Yards 834.83 888.47 53.64 $14.90 $799.24 Removing concrete and asphalt sidewalk and driveway; complete as Square 1120 Ispecified Feet 1 2.579.10 2,651,00 71.90 $5.00 $359.50 7" concrete pavement removal and replacement; including sawing; pavement lies; dowel bars; bond breaker; integral curb and fine grading; turf restoration; and traffic control; complete Square 1308 ass specified Yards 715.47 716.20 0.73 $110.00 $80.30 Adjust manholes and inlets; 1360 complete as specified Each 1.00 1.00 $1 000.00 Turf restoration; complete as Square 1370 specified Yards 1.200.00 1,209.00 9.00 $14.00 $126.00 30" concrete curb and gutter removal and replacement; including sawing; pavement ties; dowel bars; bond breaker; integral curb and fine grading; turf restoration; and traffic control; complete Linear 1448 asspecified Feet 20.00 18.00 -2.00 1 $48.00 $96.00 4" concrete sidewalk with 3" CABC and grading; complete Square 1500 las specified Feet 1,586.59 1431.50 -155.09 $11.00 $1,705.00 6" concrete sidewalk/ driveway/ramp with 3" CABC and grading; complete as Square 1510 specified Feet 999.50 1,151.50 152.00 $12.00 $1,824.00 No. 4 reinforcing rods - deformed; epoxy -coated; Linear 1550 complete as specified Feet 370.00 364.00 -6.00 $2.00 $12.00 Drilled No. 4 sidewalk tie bars - deformed; epoxy -coated; 1560 complete as s ecified Each 192.00 188.00 -4.00 $5.00 $20.00 Sawing existing pavement; Linear 1700 complete asspecified Feet 1,590.40 1,761.50 171.10 $4.50 $769.95 4" asphaltic pavement LT with 10" CABC and grading; Square 1906 complete asspecified Yards 830.06 888.47 58.41 $80.00 $4,672.80 Furnish and install 8" storm Linear 2001 sewer; complete ass specified Feet 360.00 370.00 10.00 $101.00 $1,010.00 Furnish and install 12" storm Linear 2003 sewer; complete as specified Feet 16.00 17.00 1.00 $102.00 $102.00 Furnish and install 15" storm Linear 2006 sewer; Complete asspecified Feet 635.00 621.00 -14.00 $110.00 $1,540.00 Furnish and install standard storm sewer manhole (4' diameter); complete as Vertical 2201 specified Feet 8.80 7.80 -1.00 $490.00 $490.00 Page 1 ol2 R CONTRACT 19-20 CHANGE ORDER 01 (FINAL) INCREASEIN DECREASE IN ITEM UNIT CONTRACT INSTALLED NET NET UNIT CONTRACT CONTRACT NUMBER DESCRIPTION QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE PRICE Furnish and install Type 3 Inlet (with 18" sump); $2,100.00 2237 complete as s eked Each 2.00 2.00 Furnish and install 6" storm sewer lateral; complete as Linear 1,445.50 -100.50 $119.80 $12,039.90 2400 s ecified Feet 1,546.00 Furnish and install storm sewer marker balls; complete 94.00 •6.00 $40.00 $240.00 2404 as s ecified Each 100.00 Furnish and install storm sewer clay dams; complete 47.00 -3.00 $90.00 $270.00 2406 asspecified Each 50.00 Furnish and install storm sewer lateral inlet; complete Each 30.00 23.00 -7.00 $500.00 $3,500.00 2408 as specified Cleanouts; complete as 2418 specified Each 6.00 6.00 $900.00 Furnish; install; maintain; and remove Type D modified inlet protection; complete as 77.00 -3.00 $110.00 $330.00 2608 specified Each 80.00 Furnish; install; maintain; and 2516 remove stone bag; complete ass ecified Each 46.00 44.00 -2.00 $10.00 $20.00 2800 Abandon 8" -12" storm sewer; complete as s ecifled Linear I Feet 45.00 42.00 .3.00 $13.00 $39.00 Connect to existing storm sewer main; complete as 2850 specified Each 1.00 1.00 $760.00 Connect to existing storm sewer lateral; complete as 2652 specified Each 3.00 3.00 $100.00 Connect lateral to existing storm sewer main; complete 2864 asspecified Each 29.00 29.00 $760.00 Connect to existing storm sewer manhole; complete as 2856 specified Each 3,00 3.00 $760.00 Connect to existing storm sewer inlet; complete as 2858 specified Each 2.00 2.00 $760.00 Storm sewer utility line opening (ULO); complete as 2914 s ecified Each 4.00 4.00 $800.00 Furnish and install external sanitary sewer manhole chimney seat; complete as 3114 s ecified Each 1.00 1.00 $1,900.00 SECTION (BID ITEMS 1100 -3114) - SUBTOTAL: $9,743.79 ($20,302.90) NET DECREASE SECTION I: ($10,669.11) NET DECREASE TO CONTRACT: ($10,659.11) Page 2 or