PURPOSE: APPROVE CHANGE ORDER NO. 2 FOR PUBLIC WORKS
CONTRACT NO. 19-05 OREGON STREET (WEST 16TH AVENUE
TO WEST 21ST AVENUE) RECONSTRUCTION PTS
CONTRACTORS, INC. (-$115,960.56)
INITIATED BY: PUBLIC WORKS DEPARTMENT
BE IT RESOLVED by the Common Council of the City of Oshkosh that the
following change Order, a copy of which is attached, is hereby approved:
PTS CONTRACTORS, INC.
4075 Eaton Road
Green Bay, WI 54311
Net Decrease to Contract: (-$115,960.56)
PURPOSE: See attached Change Order.
r,A
City
0fW
Oshkosh
MEMORANDUM
TO: Honorable Mayor and Members of the Common Council
FROM: Justin Gierach, Engineering Division Manager/City Engineer
DATE: March 19, 2020
RE: Change Order No. 2 for Public Works Contract No. 19-05
Oregon Street (West 161"Avenue to West 21s1 Avenue) Reconstruction
PTS Contractors,Inc. (-$115,960.56)
BACKGROUND
Change Order No. 2 for Contract 19-05 is scheduled for consideration by the Common Council
at the March 24, 2020 meeting. The contract was originally awarded to PTS Contractors, Inc. in
February of 2019. Change Order No. 1 was approved by Council in August of 2019. This
change order is for additional services provided.
ANALYSIS
Following is a summary of the significant changes to each section of the CIP:
• Street-Final quantities adjusted to match field conditions.
• Storm Sewer-Final quantities adjusted to match field conditions.
• Sanitary Sewer-Final quantities adjusted to match field conditions.
• Water Main-Final quantities adjusted to match field conditions.
• Sidewalk-Final quantities adjusted to match field conditions.
• Traffic-Final quantities adjusted to match field conditions.
I:\Engineering\2019CONTRACTS\19-052nd Page 1 of 2
Paving\Project_Information\Correspondence\Memo\19-05 Memo for CO#2_3-19-20.docx
FISCAL IMPACT
New Construction
Contract Section Change Order Amount Costs with Engr CIP Budget Amount
Street -$46,216.56 $1,685,855.49 $1,898,600
Storm Sewer -$33,249.97 $892,828.90 $995,800
Sanitary Sewer $16,315.34 $4,214,330.75 $4,316,800
Water Main -$30,510.32 $1,048,456.02 $1,309,400
Sidewalk -$6,758.75 $54,909.40 $70,000
Traffic -$15,540.30 $508,410.08 $625,000
Total -$115,960.56 $8,404,790.64 $9,215,600
Adequate funds are available in the relating sections of the 2019 Capital Improvement Budget.
RECOMMENDATIONS
I recommend approval of Change Order No. 2 to Contact No. 19-05 in the amount of
-$115,960.56 to PTS Contractors, Inc.
Approved:
Mark A. Rohloff
City Manager
J.G/tir
i
I
i
i
i
I
C
E I:\Engineering\2019CONTRACTS\19-052nd Page 2 Of 2
€' Paving\Project_Information\Correspondence\Memo\19-05 Memo for CO#2_3-19-20.docx
s
e
i
TO: PTS CONTRACTORS, INC. CHANGE ORDER#2(FINAL)
4075 EATON ROAD DATE: FEBRUARY 28,2020
GREEN BAY,WI 54311
Your present contract with the City of Oshkosh, Contract No. 19-05,awarded February 26, 2019, is hereby amended
and changed as follows:
NET DECREASE TO SECTION I: ($114,537.17)
NET DECREASE TO ALTERNATE 2: ($5,478.00)
NET INCREASE TO SECTION I: $4,054.61
NET DECREASE TO CONTRACT ($115,960.56)
SECTION I TOTALS
BID TOTAL $7,258,523.29 $7,258,523.29
CO#1 $192,625.55 $192,625.55
PREVIOUS CONTRACT TOTAL $7,451,148.84 $7,451,148.84
CO#2 ($115,960.56) ($115,960.56)
CONTRACT TOTAL $7,335,188.28 $7,335,188.28
CITY OF OSHKOSH
BY:
City Manager
City Clerk
Approved and accept d:
Contractor
I certify that provision has been made to pay the liability that will accrue to the City of Oshkosh,Wisconsin,
under the within Change Order.
Comptroller
Approved as to form:
City Attorney
CONTRACT 19-05 CHANGE ORDER#2(FINAL)
19-05
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT CONTRACT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE CONTRACT PRICE
Mobilization;complete as Lump
1050 specified Sum 1.00 1.00 $532,000.00
Removing pavement; Square
1100 complete asspecified Yards 17,300.00 17,211.00 -89.00 $2.75 $244.75
Removing concrete and
asphalt sidewalk and
driveway;complete as Square
1120 specified Feet 46,000.00 45,889.60 -110.40 $0.40 $44.15
Unclassified excavation; Cubic
1200 complete asspecified Yards 3,950.00 3,932.20 -17.80 $15.75 $280.35
Excavation special(paving);
1220 complete asspecified Tons 500.00 0.00 -500.00 $12.25 $6,125.00
7"concrete pavement HES;
with 5'CABC and grading; Square
1303 complete asspecified Yards 500.00 576.10 76.10 $65.20 $4,961.72
8"concrete pavement HES;
with 6"CABC and grading; Square
1313 complete asspecified Yards 590.00 577.00 -13.00 $65.70 $854.10
8"concrete pavement
doweled;with 6"CABC and
grading;complete as Square
1314A specified Yards 6,850.00 11,702.30 4852.30 $51.00 $247,467.30
8"concrete pavement
doweled;HES;with 6"CABC
and grading; complete as Square
1315 specified Yards 7,450.00 2,557.30 -4,892.70 $53.25 $260,536.28
Concrete pavement gaps;
1334 complete asspecified Each 2.00 2.00 $1,025.00
Crushed aggregate base
course;complete as
1340 specified Tons 1,550.00 51.80 -1,498.20 $6.15 $9,213.93
Pavement ties; complete as
1350 specified Each 10.00 14.00 4.00 $8.20 $32.80
Drilled dowel bars; 1";
1352 complete as specified Each 105.00 70.00 -35.00 $10.25 $358.75
Drilled dowel bars; 1 1/4";
1354 complete asspecified Each 75.00 93.00 18.00 $14.30 $257.40
Adjust manholes and inlets;
1360 complete asspecified Each 95.00 94.00 -1.00 $280.00 $280.00
Turf restoration;complete as Square
1370 specified Yards 4,570.00 4,874.00 304.00 $9.20 $2,796.80
Restore gravel driveway/ Square
1372 apron;complete asspecified Yards 140.00 195.10 55.10 $11.25 $619.88
Cold weather covering
(concrete pavement)-single
visquine;complete as Square
1380 specified Yards 3,000.00 0.00 -3,000.00 $0.01 $30.00
Up-charge for late season
cold weather concrete
pavement;complete as Cubic
1390 Ispecified Yards 1 670.00 0.00 -670.00 $5.12 $3,430.40
12"radius curb with 6"CABC
and grading;comt8";
Linear
1410 specified Feet 500.00 483.10 -16.90 $11.25 $190.13
30"curb and guth6"CABC and graLinear
1442 com lete ass e Feet 210.00 206.70 -3.30 $31.70 $104.61
Page 1 of 13
CONTRACT 19-05 CHANGE ORDER#2(FINAL)
ITEM CONTRACT INSTALLED NET NET UNIT INCREASEIN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT PRICE
PRICE
30"curb and gutter;8";with
6"CABC and grading; Linear
1443 complete as specified Feet 5,525.00 5,472.40 -52.60 $15.80 $831.08
Sidewalk curb; complete as Linear
1460 specified Feet 250.00 197.80 -52.20 $50.00 $2,610.00
4"concrete sidewalk with 3"
CABC and grading;complete Square
1500 asspecified Feet 25,550.00 26,610.00 1060.00 $5.75 $6,095.00
6"concrete sidewalk/
driveway/ramp with 3"CABC
and grading;complete as Square
1510 specified Feet 11,070.00 10,607.10 -462.90 $6.00 $2,777.40
6"concrete sidewalk/
driveway/ramp(HES)with 3"
CABC and grading;complete Square
1514 asspecified Feet 5,050.00 4,848.40 -201.60 $6.30 $1,270.08
8"concrete sidewalk/
driveway/ramp with 3"CABC
and grading;complete as Square
1520 specified Feet 1,360.00 1,589.70 229.70 $7.001 $1,607.90
6"concrete step;complete as Square
1530 specified Feet 345.00 232.50 -112.50 $51.00 $5,737.50
Curb ramp detectable
warning field(natural/non-
painted);complete as Square
1540 specified Feet 192.00 200.00 8.00 $32.70 $261.60
No.4 reinforcing rods-
deformed,epoxy-coated; Linear
1550 complete asspecified Feet 5,140.00 4,950.00 -190.00 $1.25 $237.50
Drilled No.4 sidewalk tie bars
-deformed,epoxy-coated;
1560 complete asspecified Each 425.00 301.00 -124.00 $4.60 $570.40
Cold weather covering
(sidewalk)-single visquine; Square
1580 complete asspecified Feet 8,400.00 0.00 -8,400.00 $0.50 $4,200.00
Up-charge for late season
cold weather concrete
pavement;complete as Cubic
1590 specified Yards 130.00 0.00 -130.00 $9.20 $1,196.00
Locate existing property
monuments;complete as
1650 specified Each 30.00 43.00 13.00 $128.00 $1,664.00
Replace section corner;
1651 complete asspecified jah
2.00 2.00 $410.00
Replace existing property
monuments;complete as
1652 specified 20.00 39.00 19.00 $51.00 $969.00
Sawing existing pavement;1700 com lete as specified 1,275.00 1,288.00 13.00 $2.00 $26.00
Sawing concrete pavement
full depth;complete as 1710 s ecified 255.00 339.00 84.00 $2.60 $218.40
Tack coat;complete as
1900 specified Gallons 95.00 71.80 -23.20 $4.10 $95.12
4"asphaltic transition LT with
10"CABC and grading; Square
1911 com lete asspecified Yards 1,195.00 1,259.90 64.90 $38.00 $2,466.20
4"asphaltic surface LT with
6"CABC and grading; Square
1916 com lete asspecified Feet 150.00 147.60 -2.40 $46.00 $110.40
Page 2 of 13
CONTRACT 19-05 CHANGE ORDER#2(FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT CONTRACT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE CONTRACT PRICE
2"asphaltic surface LT with
6"CABC and grading; Square
1917 com lete asspecified Yards 250.00 0.00 -250.00 $25.65 $6,412.50
Asphaltic cold weather Square
1918 paving;complete asspecified Yards 300.00 0.00 -300.00 $4.60 $1,380.00
Pavement marking epoxy;8" Linear
1974 (white);complete asspecified Feet 4,940.00 4,606.80 -333.20 $2.00 $666.40
Pavement marking epoxy;4" Linear
1975 (white);complete asspecified Feet 5,450.00 5,522.00 72.00 $2.00 $144.00
Pavement markings epoxy;
4"(yellow);complete as Linear
1976 specified Feet 260.00 267.50 7.50 $4.00 $30.00
Pavement markings parking
stall epoxy;4"(white); Linear
1977 complete asspecified Feet 565.00 542.00 -23.00 $6.00 $138.00
Pavement markings epoxy;
12"(white);complete as Linear
1978 specified Feet 175.00 153.80 -21.20 $9.00 $190.80
Pavement markings arrow
epoxy;Type 2(white); Linear
1980 complete asspecified Feet 3.001 3.00 $128.00
Pavement markings;word
epoxy;Type 2(white); Linear
1983 complete asspecified Feet 2.00 2.00 $180.00
Furnish and install 10"storm Linear
2002 sewer;complete asspecified Feet 5.00 11.00 6.00 $96.00 $576.00
Furnish and install 12"storm Linear
2003 sewer;complete asspecified Feet 725.00 719.80 -5.20 $80.00 $416.00
Furnish and install 15"storm Linear
2006 sewer;complete asspecified Feet 325.00 325.30 0.30 $65.00 $19.50
Furnish and install 18"storm Linear
2009 sewer;complete asspecified Feet 1,450.00 1,420.50 -29.50 $69.00 $2,035.50
Furnish and install 21"storm Linear
2012 sewer;complete asspecified Feet 350.00 344.20 -5.80 $84.00 $487.20
Furnish and install 24"storm Linear
2015 sewer;complete asspecified Feet 500.00 496.10 -3.90 $82.00 $319.80
Furnish and install 36"storm Linear
2024 sewer;complete as specified Feet 110.00 101.20 -8.80 $122.00 $1,073.60
Furnish and install 54"storm Linear
2033 sewer;complete asspecified Feet 110.00 97.30 -12.70 $181.00 $2,298.70
Furnish and install 34"x 53"
HERCP Class III storm Linear
2053 sewer;complete asspecified Feet 290.001 285.80 -4.20 1 $110.00 $462.00
Furnish and install 38"x 60"
HERCP Class III storm Linear
2055 sewer;complete ass ecifeid Feet 20.00 8.00 -12.00 $173.00 $2,076.00
Furnish and install 48"x 76"
HERCP Class III storm Linear
2059 sewer;complete asspecified Feet 80.00 78.50 -1.50 $180.00 $270.00
Furnish and install standard
storm sewer manhole(4'
diameter); complete as Vertical
2201 specified Feet 48.75 49.92 1.17 $356,00 $416.52
Page 3 of 13
CONTRACT 19-05 CHANGE ORDER#2(FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT CONTRACT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE CONTRACT PRICE
Furnish and install standard
storm sewer manhole(5'
diameter);complete as Vertical
2202 Ispecified Feet 1 12.60 12.59 -0.01 $536.00 $5.36
Furnish and install standard
storm sewer manhole(6'
diameter);complete as Vertical
2203 specified Feet 4.10 4.29 0.19 $720.00 $136.80
Furnish and install standard
storm sewer manhole(8'
diameter);complete as Vertical
2205 specified Feet 8.40 8.78 0.38 $875.00 $332.50
Furnish and install standard
storm sewer manhole(7'x 7' Vertical
2210 box);complete asspecified Feet 19.10 19.60 0.50 $1,015.00 $507.50
Furnish and install standard
storm sewer manhole(8'x 8' Vertical
2211 box);complete as specified Feet 26.85 26.93 0.08 $1,800.00 $144.00
Furnish and install standard
storm sewer inlet manhole(4'
diameter);complete as Vertical
2213 specified Feet 3.45 2.85 -0.60 $395.00 $237.00
Furnish and install Type 1
2236 inlet;complete asspecified Each 1.00 0.00 -1.00 $1,465.00 $1,465.00
Furnish and install Type 3
inlet(with 18"sump);
2237 complete as specified Each 34.00 33.00 -1.00 $1565.00 $1,565.00
Furnish and install 6"storm
sewer lateral;complete as Linear
2400 specified Feet 2,685.00 2,568.92 -116.08 $62.00 $7,196.95
Furnish and install 8"storm
sewer lateral;complete as Linear
2402 specified Feet 170.00 156.00 -14.00 $76.00 $1,064.00
Furnish and install storm
sewer marker balls;complete
2404 asspecified Each 155.00 151.00 -4.00 $44.00 $176.00
Furnish and install storm
sewer clay dams;complete
2406 asspecified Each 78.00 75.00 -3.00 $115.00 $345.00
Furnish and install storm
sewer lateral inlet;complete
2408 as specified Each 71.00 65.00 -6.00 $476.00 $2,856.00
Storm lateral inlet
adjustments;complete as
2414 specified Each 71.00 9.00 -62.00 $23.00 $1,426.00
Perforated drain tile; Linear
2416 complete asspecified Feet 25.00 0.00 -25.00 $36.00 $900.00
Cleanouts;complete as
2418 specified Each 1.00 1.00 $488.00
Furnish; install; maintain;and
remove Type D modified inlet
protection;complete as
2508Lecifieed Each 107.00 83.00 -24.00 $72.00 $1,728.00removal-Type D
nlet protection;
2510asspecified Each 107.00 16.00 -91.00 $6.00 $546.00
Page 4 of 13
CONTRACT 19-05 CHANGE ORDER#2(FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT CONTRACT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE CONTRACT PRICE
Furnish;install;maintain;and
remove stone tracking pad;
2512 complete asspecified Each 1.00 0.00 -1.00 $100.00 $100.00
Furnish;install;maintain;and
remove stone bag;complete
2516 asspecified Each 25.00 23.00 -2.00 $10.00 $20.00
Furnish;install;maintain;and
remove 12"diameter
sediment logs;complete as Linear
2518 specified Feet 100.00 60.00 -40.00 $10.00 $400.00
Furnish; install; maintain;and
remove ditch check;
2522 complete as specified Each 20.00 4.00 -16.00 $76.00 $1,216.00
Furnish; install; maintain;and
remove dewatering tank
system;complete as
2524 specified Each 4.00 3.00 -1.00 $1,000.00 $1,000.00
Rock excavation;complete Cubic
2750 asspecified Yards 10.00 0.00 -10.00 $0.01 $0.10
Abandon 8"-12"storm Linear
2800 sewer;complete asspecified Feet 240.00 231.00 -9.00 $10.00 $90.00
Abandon 15"and larger
storm sewer; complete as Linear
2802 specified Feet 1 600.00 597.00 -3.00 $32.00 $96.00
Remove 30"and smaller
storm sewer; complete as Linear
2804 specified Feet 445.00 437.00 -8.00 $26.00 $208.00
Remove 33"-60"storm Linear
2806 sewer;complete as specified Feet 80.00 75.00 -5.00 $44.00 $220.00
Abandon storm sewer
manholes and inlets;
2810 complete asspecified Each 6.00 5.00 -1.00 $440.00 $440.00
Remove storm sewer
manholes and inlets;
2812 complete asspecified Each 15.00 14.00 -1.00 $440.00 $440.00
Connect to existing storm
sewer main;complete as
2850 specified Each 9.00 8.00 -1.00 $650.00 $650.00
Connect to existing storm
sewer lateral;complete as
2852 specified Each 3.00 2.00 -1.00 $280.00 $280.00
Connect to existing storm
sewer manhole;complete as
2856 specified Each 1.00 0.00 -1.00 $1,900.00 $1,900.00
Storm sewer utility line
opening(ULO);complete as
2914 specified Each 5.00 0.00 -5.00 $230.00 $1,150.00
Excavation special(storm);
2950 complete asspecified Tons 200.00 0.00 -200.00 $25.00 $5,000.00
Furnish and install 8"sanitary
sewer(relay);complete as Linear
3000 specified Feet 1,724.00 1,701.60 -22.40 $100.00 $2,240.00
Furnish and install 12"
sanitary sewer(relay); Linear
3004 complete asspecified Feet 111.00 104.80 -6.20 $156.00 $967.20
Furnish and install 18"
sanitary sewer(relay); Linear
3008 complete asspecified Feet 38.00 31.50 -6.50 $157.00 $1,020.50
Page 5 of 13
CONTRACT 19-05 CHANGE ORDER#2(FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT CONTRACT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE CONTRACT PRICE
Furnish and install 24"
sanitary sewer(relay); Linear
3012 complete asspecified Feet 7.00 10.50 3.50 $270.00 $945.00
Furnish and install 8"sanitary
sewer(new);complete as Linear
3030 specified Feet 47.00 45.00 -2.00 $115.00 $230.00
Furnish and install 8"sanitary
sewer drop;complete as Vertical
3060 specified Feet 47.00 43.09 -3.91 $375.00 $1,466.25
Furnish and install 18"
sanitary sewer drop; Vertical
3068 complete asspecified Feet 5.00 4.67 -0.33 $480.00 $158.40
Furnish and install standard
sanitary sewer manhole(4'
diameter);complete as Vertical
3100 specified Feet 142.00 146.86 4.86 $215.00 $1,044.90
Furnish and install external
sanitary sewer manhole
chimney seal;complete as
3114 specified Each 23.00 23.00 $485.00
Furnish and install external
sanitary sewer manhole
chimney seal extension;
3116 complete as specified Each 2.00 0.00 -2.00 $410.00 $820.00
Furnish and install internal
sanitary sewer manhole
chimney seal;complete as
3118 specified Each 1.00 0.00 -1.00 $360.00 $360.00
Furnish and install internal
sanitary sewer manhole
chimney seal extension;
3120 Icomplete asspecified Each 1.00 0.00 -1.00 $360.00 $360.00
Install CITY supplied
manhole:complete as Vertical
3149 specified Feet 11.00 10.86 -0.14 $230.00 $32.20
Furnish and install 8"x 6"
sanitary sewer factory wyes
or tees;complete as
3210 Ispecified Each 1 43.00 70.00 27.00 $96.00 $2,592.00
Furnish and install 12"x 6"
sanitary sewer factory wyes
or tees;complete as
3214 specified Each 1.00 0.00 -1.00 $292.00 $292.00
Furnish and install 6"sanitary
sewer"Inser-A-Tee"or"Kor-
N-Tee';complete as
3222 Ispecified Each 1 4.00 0.00 -4.00 $260.00 $1,040.00
Furnish and install 4"/6"
sanitary sewer lateral(relay); Linear
3234 complete asspecified Feet 2,165.00 2,311.00 146.00 $100.00 $14,600.00
Furnish and install 4"/6"
sanitary sewer riser(relay); Linear
3235 complete asspecified Feet 20.00 102.00 82.00 $120.00 $9,840.00
Furnish and install sanitary
sewer lateral marker balls;
3236 complete asspecified Each 157.00 159.00 2.00 $44.00 $88.00
Furnish and install clay
3238 dams;complete ass ecified Each 78.00 80.00 2.00 $115.00 $230.00
Page 6 of 13
CONTRACT 19-05 CHANGE ORDER#2(FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT CONTRACT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE
PRICE
Furnish and install sanitary
lateral extension(relay); Linear
3243 complete as specified Feet 24.00 90.00 66.00 $110.00 $7,260.00
Furnish and install
connection to existing 8"
3300 mains;complete as specified Each 5.00 1.00 -4.00 $830.00 $3,320.00
Furnish and install
connection to existing 12"
3304 mains;complete as specified Each 4.00 4.00 $1,560.00
Furnish and install
connection to existing 18"
sanitary sewer mains;
3308 complete as specified Each 2.00 2.00 $2,240.00
Furnish and install
connection to existing 24"
sanitary sewer mains;
3312 complete as specified Each 1.00 1.00 $2,240.00
Furnish and install
connection to existing 42"
sanitary sewer mains;
3318 complete as specified Each 1.001 1.00 $520,000.00
Furnish and install sanitary
sewer concrete collars;
3330 complete as specified Each 2.00 2.00 $1,080.00
Furnish and install 10"
sanitary sewer open cut
casing pipes;complete as Linear
3404 specified Feet 40.00 20.00 -20.00 $156.00 $3,120.00
Rock excavation;complete Linear
3601 as specified Feet 3,570.00 3,001.70 -568.30 $0.01 $5.68
Crack and damage survey;
3650 complete as specified Each 100.00 92.00 -8.00 $500.00 $4,000.00
Closed circuit televising; Linear
3700 complete as specified Feet 4,937.00 5,000.50 63.50 $2.00 $127.00
Closed circuit televising-
using push camera;complete
3710 as specified Each 5.00 10.00 5.00 $350.00 $1,750.00
Abandon sanitary sewer
manholes;complete as
3800 specified Each 1.00 0.00 -1.00 $780.00 $780.00
Abandon 8"sanitary sewer; Linear
3802 complete as specified Feet 99.00 99.00 $14.30
Abandon 12"sanitary sewer; Linear
3806 complete asspecified Feet 24.70 24.70 $16.60
Remove sanitary sewer
manholes; complete as
3852 specified Each 3.00 2.00 -1.00 $870.00 $870.00
Remove sanitary sewer; Linear
3854 complete as specified Feet 233.00 233.00 $35.00
Sanitary sewer utility line
opening(ULO); complete as
3890 specified Each 3.00 1.00 -2.00 $500.00 $1,000.00
Excavation special(sanitary);
3892 complete asspecified Tons 4,521.63 4,521.63 $25.00
Furnish and install 4"ductile
iron water main(relay)with
polywrap;complete as Linear
4000 specified Feet 55.00 47.40 -7.60 $150.00 $1,140.00
Page 7 of 13
CONTRACT 19-05 CHANGE ORDER#2(FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT CONTRACT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE CONTRACT PRICE
Furnish and install 6"ductile
iron water main(relay)with
polywrap;complete as Linear
4002 specified Feet 350.00 333.35 -16.65 $114.00 $1,898.10
Furnish and install 8"ductile
iron water main(relay)with
polywrap;complete as Linear
4004 specified Feet 3,450.00 3,429.95 -20.05 $95.00 $1,904.75
Furnish and install 12"ductile
iron water main(relay)with
polywrap;complete as Linear
4008 Ispecified Feet 1 200.00 183.00 -17.00 $170.00 $2,890.00
Furnish and install 1"water
service(relay);complete as Linear
4036 specified Feet 2,628.00 2,404.50 -223.50 $78.00 $17,433.00
Furnish and install 2"water
service(relay);complete as Linear
4040 specified Feet 42.00 32.00 -10.00 $140.00 $1,400.00
Furnish and install 1"
corporation and stop box;
4048 complete asspecified Each 80.00 78.00 -2.00 $450.00 $900.00
Furnish and install 2"
corporation and stop box;
4053 complete asspecified Each 1.00 1.00 $1,280.00
Furnish and install water
service clay dams;complete
4055 asspecified Each 80.00 77.00 -3.00 $116.00 $348.00
Furnish and install
connections to existing 4"
water main;complete as
4056 specified Each 1.00 1.00 $1,880.00
Furnish and install
connections to existing 6"
water main;complete as
4058 Ispecified Each 1 9.00 8.00 -1.00 $1,940.00 $1,940.00
Furnish and install
connections to existing 8"
water main;complete as
4060 specified Each 2.00 2.00 $2,300.00
Furnish and install
connections to existing 12"
water main;complete as
4064 Ispecified Each 1 2.00 2.00 $2,500.00
Furnish and install 8"x 4"
water main tee; complete as
4109 se cified Each 1.00 1.00 $375.00
Furnish and install 8"x 6"
water main tee;complete as
4110 specified Each 10.00 9.00 -1.00 $420.00 $420.00
Furnish and install 8"x 8"
water main tee; complete as
4111 specified Each 4.00 4.00 $540.00
Furnish and install 12"x 6"
water main tee;complete as
4128 Ispecified Each 1 3.00 3.00 $765.00
Furnish and install 8"x 8"
water main cross;complete
4189 asspecified Each 2.00 2.00 $690.00
Furnish and install 8"x 12"
water main cross;complete
4191 asspecified Each 1.001 1.00 $1,100.00
Page 8 of 13
CONTRACT 19-05 CHANGE ORDER#2(FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT CONTRACT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE CONTRACT PRICE
Furnish and install 4"45
degree water main bend;
4235 complete asspecified Each 2.00 0.00 -2.00 $160.00 $320.00
Furnish and install 6"45
degree water main bend;
4236 lcomplete asspecified Each 1 46.00 31.00 -15.00 $210.00 $3,150.00
Furnish and install 8"45
degree water main bend;
4237 complete asspecified Each 10.00 8.00 -2.00 $290.00 $580.00
Furnish and install 12"45
degree water main bend;
4239 complete asspecified Each 4.00 4.00 $645.00
Furnish and install 6"water
main cap;complete as
4254 specified Each 1.00 1.00 $110.00
Furnish and install 8"x 6"
water main reducer;complete
4264 asspecified Each 8.00 7.00 -1.00 $250.00 $250.00
Cut and cap existing 6"water
4352 main;complete asspecified Each 1.00 7.00 6.00 $100.00 $600.00
Cut and cap existing 8"water
4354 main; complete asspecified Each 1.00 0.00 -1.00 $100.00 $100.00
Cut and cap existing 12"
water main;complete as
4358 specified Each 2.00 0.00 -2.00 $100.00 $200.00
Furnish and install 4"water
main gate valve;complete as
4400 specified Each 1.00 1.00 $1,000.00
Furnish and install 6"water
main gate valve;complete as
4401 specified Each 14.00 14.00 $1,120.00
Furnish and install 8"water
main gate valve;complete as
4402 specified Each 28.00 29.00 1.00 $1,580.00 $1,580.00
Furnish and install 12"water
main gate valve;complete as
4404 specified Each 4.00 4.00 $2,570.00
Furnish and install hydrant;
4500 complete asspecified Each 11.00 11.00 $3,940.00
Furnish and install 2"water
main casing pipe;complete Linear
4712 asspecified Feet 10.00 10.00 $54.00
Furnish and install 4"water
main casing pipe;complete Linear
4714 asspecified Feet 10.00 10.00 $66.00
Furnish and install 10"water
main casing pipe;complete Linear
4720 asspecified Feet 20.00 0.00 -20.00 $66.00 $1,320.00
Furnish and install 18"water
main casing pipe;complete Linear
4726 asspecified Feet 40.00 34.00 -6.00 $98.00 $588.00
Rock excavation;complete Linear
4801 asspecified Feet 237.00 175.00 -62.00 $0.01 $0.62
Abandon water main on
Oregon Street;complete as Lump
4900 specified Sum 1.00 1.00 $6,000.00
Remove water main; Linear
4920 complete asspecified Feet 920.00 920.00 $34.00
Page 9 of 13
CONTRACT 19-05 CHANGE ORDER#2(FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT CONTRACT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE CONTRACT PRICE
Excavation special(water);
4990 complete asspecified Tons 25.00 0.00 -25.00 $25.00 $625.00
Furnish and install pull box
(non-conductive); 18"x 36';
5013 complete asspecified Each 33.00 32.00 -1.00 1 $1,480.00 $1,480.00
Furnish and install pull box
(non-conductive);24"x 42';
5019 complete asspecified Each 12.00 11.00 -1.00 $1,530.00 $1,530.00
Adjust pull box; complete as
5025 specified Each 44.00 0.00 -44.00 $128.00 $5,632.00
Remove pull box;complete
5026 as specified Each 1.00 0.00 -1.00 $51.00 $51.00
Remove concrete base;
5027 complete asspecified Each 13.00 12.00 -1.00 $102.00 $102.00
Furnish and install control
cabinet;complete as
5050 specified Each 2.00 2.00 $14,500.00
Install electrical service;
5054 complete asspecified Each 1.00 1.00 $1,230.00
Furnish and install 2"
Schedule 40 PVC;complete Linear
5120 asspecified Feet 3,070.00 3,067.00 -3.00 $5.00 $15.00
Furnish and install 3"
Schedule 40 PVC;complete Linear
5130 asspecified Feet 7,455.00 7,410.00 -45.00 $6.00 $270.00
Connect to existing conduit;
5184 complete asspecified Each 3.00 3.00 $128.00
Furnish and install 4 gauge
red-coated wire;complete as Linear
5230 specified Feet 7,670.00 7,974.00 304.00 $1.25 $380.00
Furnish and install 4 gauge
black-coated wire;complete Linear
5231 asspecified Feet 7,670.00 7,974.00 304.00 $1.25 $380.00
Furnish and install 6 gauge
red coated wire;complete as Linear
5240 specified Feet 3,640.00 1,434.00 -2,206.00 $1.00 $2,206.00
Furnish and install 6 gauge
black coated wire;complete a Linear
5241 specified Feet 3,640.00 1,434.00 -2,206.00 $1.00 $2,206.00
Furnish and install 8 gauge
green-coated wire;complete Linear
5252 asspecified Feet 7,500.00 7,503.00 3.00 $1.00 $3.00
Furnish and install 10 gauge
red-coated wire;complete as Linear
5260 specified Feet 620.00 587.00 -33.00 $0.60 $19.80
Furnish and install 10 gauge
black-coated wire;complete Linear
5261 asspecified Feet 620.00 587.0.0 -33.00 $0.60 $19.80
Furnish and install 10 gauge
green-coated wire;complete Linear
5262 asspecified Feet 880.00 864.00 -16.00 $0.60 $9.60
Furnish and install 12 gauge
red-coated wire; complete as Linear
5270 specified Feet 640.00 720.00 80.00 $0.60 $48.00
Furnish and install 12 gauge
black-coated wire;complete Linear
5271 asspecified Feet 640.00 720.00 80.00 $0.60 $48.00
Page 10 of 13
CONTRACT 19-05 CHANGE ORDER#2(FINAL)
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT CONTRACT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE PRICE CONTRACTPRICE
Furnish and install 12 gauge
green-coated wire;complete Linear
5272 asspecified Feet 640.00 720.00 80.00 $0.60 $48.00
Furnish and install 14 gauge
green-coated wire;complete Linear
5282 as specified Feet 3,110.00 3,135.00 25.00 $0.60 $15.00
Furnish and install 14 gauge
stranded single pair twisted
with shield;complete as Linear
5356 specified Feet 780.00 760.00 -20.00 $1.50 $30.00
Furnish and install 14 AWG
solid 3 conductor;complete Linear
5360 asspecified Feet 60.00 45.00 -15.00 $1.25 $18.75
Furnish and install 14 AWG
solid 5 conductor;complete Linear
5362 as specified Feet 90.00 70.00 -20.00 $1.50 $30.00
Furnish and install 14 AWG
solid 7 conductor;complete Linear
5364 asspecified Feet 180.00 0.00 -180.00 $1.50 $270.00
Furnish and install 14 AWG
solid 9 conductor;complete Linear
5366 asspecified Feet 210.00 291.00 81.00 $2.00 $162.00
Furnish and install 14 AWG
solid 21 conductor;complete Linear
5372 asspecified Feet 1,140.00 1,206.00 66.00 $3.60 $237.60
Furnish and install fuse
5380 holder;complete asspecified Each 70.00 68.00 -2.00 $51.00 $102.00
Furnish and install 5A fuse;
5392 complete asspecified Each 70.00 68.00 -2.00 $5.00 $10.00
Install single head fixture;
City Supplied';complete as
5400 specified Each 2.00 2.00 $155.00
Install light pole and pole top
lights;"City Supplied";
5410 complete asspecified Each 33.00 33.00 $515.00
Install 13'traffic signal pole
with a decorative base;"City
Supplied;complete as
5421 specified Each 3.00 5.00 2.00 $200.00 $400.00
Install 15'traffic signal pole;
"City Supplied";complete as
5422 specified Each 3.00 2.00 -1.00 $200.00 $200.00
Install 20'traffic signal pole;
"City Supplied"; complete as
5424 specified Each 1.00 1.00 $400.00
Install 30'traffic signal pole;
"City Supplied";complete as
5426 specified Each 1.00 1.00 $410.00
Install 25'trombone arm;
"City Supplied"; complete as
5431 specified Each 2.00 2.00 $335.00
Install five-head traffic signal;
"City Supplied";complete as
5434 s ecified Each 7.00 7.00 $180.00
Install three-head traffic
signal;"City Supplied";
5436 complete asspecified Each 2.00 2.00 $255.00
Page 11 of 13
i
I
CONTRACT 19-05 CHANGE ORDER#2(FINAL)
I
i ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT CONTRACT INCREASE IN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE
PRICE
Install pedestrian signal;"City
Supplied";complete as
5438 specified Each 6.00 6.00 $155.00
Install pedestrian push
button;"City Supplied';
5440 complete asspecified Each 6.00 6.00 $130.00
Furnish and install Type 2
5502 Base;complete asspecified Each 13.00 10.00 -3.00 $900.00 $2,700.00
Furnish and install Type 5
5504 Base;complete asspecified Each 33.00 33.00 $766.00
Furnish and install Type 9
5506 Base;com lete asspecified Each 2.00 2.00 $5,100.00
SECTION I(BID ITEMS 1050-5506)-SUBTOTAL: $314,129.32 ($428,666.49)
NET DECREASE TO SECTION I: ($114,537.17)
ALTERNATE 2
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT CONTRACT DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT PRICE
PRIrF
Furnish and install 42"
sanitary sewer(new); Linear
3048-2 complete asspecified Feet 3,010.00 3001.70 -8.30 $660.00 -$5,478.00
Furnish and install sanitary
sewer manhole junction
chamber 0-1;complete as
3113A-2 specified Each 1.00 1.00 $12,000.00
Furnish and install sanitary
sewer manhole junction
chamber 0-3;complete as
311313-2 Ispecified Each 1 1.00 1.00 $12,000.00
Furnish and install sanitary
sewer manhole junction
chamber 0-4;complete as
3113C-2 specified Each 1.00 1.00 $12,000.00
Furnish and install sanitary
sewer manhole junction
chamber 0-5;complete as
3113D-2 Ispecified Each 1 1.00 1.00 $12,000.00
Furnish and install sanitary
sewer manhole junction
chamber 0-6; complete as
3113E-2 specified Each 1.00 1.00 $12,000.00
Furnish and install sanitary
sewer manhole junction
chamber 0-8; complete as
3113F-2 Ispecified Each 1 1.00 1.00 $12,000.00
Furnish and install sanitary
sewer manhole junction
chamber 0-9; complete as
3113G-2 specified Each 1.00 1.00 $12,000.00
Furnish and install sanitary
sewer manhole junction
chamber 0-10; complete as
31131-1-2 Ispecified Each 1.00 1.00 $12,000.00
Page 12 of 13
CONTRACT 19-05 CHANGE ORDER#2(FINAL)
INCREASE IN
ITEM FDESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT DECREASE IN
NU MBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT PRICE
PRICE
ALTERNATE 2(BID ITEMS 3048-2 - 3113H-2)-SUBTOTAL: $0.00 ($5,478.00)
NET DECREASE TO ALTERNATE 2: ($5,478.00)
ADDITIONAL WORK REQUIRED:CO#1
ITEM DESCRIPTION UNIT CONTRACT INSTALLED NET NET UNIT INCREASEIN DECREASE IN
NUMBER QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT PRICE
PRIrF
CB#1 combined 8"relay
along existing sanitary sewer
alignment;complete as Linear
1-30000 specified Feet 732.00 732.00 $67.50
Individual 8"relay along
existing sanitary sewer
alignment;complete as Linear
1-30001 specified Feet 300.00 300.00 $79.00
Furnish and install 12"
sanitary sewer drop at
manhole 0-4;complete as Vertical
1-30002 specified Feet 7.64 7.64 $420.00
Furnish and install bentonite
1-30003 dam;complete asspecified Each ri00
2.00 $2,007.00
Furnish and install small
bentonite dam 19th/Oregon;
1-30004 com lete as s ecified Each 1.00 $1,252.00
ADDITIONAL WORK REQUIRED: CO#1 (BID ITEMS 1-30000-1-30004)-SUBTOTAL: $0.00 $0.00
NET INCREASE: $0.00
ADDITIONAL WORK REQUIRED:CO#2
ITEM CONTRACT INSTALLED NET NET UNIT INCREASE IN DECREASE IN
NUMBER DESCRIPTION UNIT QUANTITY QUANTITIES INCREASE DECREASE PRICE CONTRACT CONTRACT PRICE
PRICE
Time and materials for storm
sewer plates;complete as Lump
2-20000 specified Sum 0.00 1.00 1.00 $2,929.03 $2,929.03
Time and materials for
setting hydrant at 17th
intersection; complete as Lump
2-40000 specified Sum 0.00 1.00 1.00 $1,125.58 $1,125.58
ADDITIONAL WORK REQUIRED: CO#2(BID ITEMS 2-20000-2-40000)-SUBTOTAL: $4,054.61 $0.00
NET INCREASE: $4,054.61
NET DECREASE TO SECTION I: ($114,537.17)
NET DECREASE TO ALTERNATE 2: ($5,478.00)
NET INCREASE TO SECTION I: $4,054.61
NET DECREASE TO CONTRACT: ($115,960.56)
Page 13 of 13