HomeMy WebLinkAboutMinutes
STORM WATER UTILITY COMMITTEEMinutes
April 23,2015
Present:Paul Janty;Kyle Clark;John Kiefer; Sean Butler;
Absent:Maureen Muldoon
Also Present:Steve Gohde,AssistantDirector of Public Works;James Rabe, Civil
Engineering Supervisor;EmilyMakowski, Communications Coordinator;
Ashley Leisgang,AECOM; Chuck Boehm,AECOM;Jim Bachhuber, Brown
and Caldwell
I.Call to Order.
A.Mr.Kiefercalled the meeting to order at7:35am.
II.Discussion of Future Meeting Dates and Times.
A.Future meeting were tentatively scheduled for May 26, and June 25, 2015 at 7:30 am in
Room 404 of City Hall.
III.Approval ofMarch19,2015Meeting Minutes.
A.Mr. Clark moved to approve the minutes, as presented, seconded by Mr. Butler. Motion
carried (4–0).
IV.Presentation of Service Award.
A.Mr. Rabe and Mr. Gohde acknowledgedand congratulatedMr. Butlerfor his10 years of
service on the StormWater Utility Committee.A plaque recognizing this achievement was
presented to Mr. Butler.
V.Discussion of Future Meeting Agenda Items.
A.The following topics wereproposed:
i.Information / Education program update.
ii.Utility fee credit appeal (at the May meeting).Mr. Rabe will provide the Committee with
the procedures for the appeals process.Mr. Janty requested that if possible the City
attorney should attend the meeting.
iii.Mr. Janty asked for a topic on status of storm water utility paymentsand non-payments
over the past several years.
iv.Draft 2016 CIP.
VI.Citywide Storm Water Management Plan Update Presentation.
A.Mr. Rabe explained that the Plan Update was focused on stormwater pollution and updating
the city’s stormwater ordinances to meet new staterequirements. The study waspartially
funded by a state grant (about 60% state support).
B.Mr. Rabe introduced Chuck Boehm and Ashley Leisgangfrom AECOM to conduct the
presentation.
C.Mr.Boehm,and Ms. Leisgang presented a summaryof the study and results(handouts were
available).
D.Mr. Janty asked how accurate the modeled pollutant loads are. Mr. Boehm and Mr. Rabe
replied that the modeling results are based onWisconsin Department of Natural Resources
(WDNR)guidelines and land conditions fromtheCity’sGIS. Mr. Boehm added that all the
I:\\Engineering\\James\\Storm Water Utility Committee\\2015\\04-23-2015\\AgendaPage1of4
Discussion 04-23-2015.docx
affected cities are using the same tools and guidelines and thus the results for Oshkosh are
relatively comparable to other cities.
E.Mr. Janty asked if there has been any litigation regarding the model use. Mr. Rabe replied
that he is not aware of any litigation.
F.Mr. Janty asked whothe audience for this presentation is. Mr. Rabe replied that for today’s
purpose the audience is the Committee. In the future, other groups such astheCouncil will
be informed. Other public stakeholders will be targeted down the road.
G.Mr. Butler asked if theTotal Maximum Daily Load (TMDL)will impact specific industries.
Mr. Boehm respondedthat unless the industry has its own wastewater facility, their storm
water becomes part of the City’s management program.
H.Mr. Butler asked what pollutants are included in the TMDL. Mr. Rabe replied that it
depends on what pollutants are causing impairments to a particular waterbody. Right now,
the Upper Fox TMDLfocusesonTotal Suspended Solids (TSS)andTotal Phosphorus (TP).
I.Mr. Clark asked for a PDF file of just the Figure 4-13for easier viewing.
J.Mr. Janty asked how does the study incorporatethe streetimprovementsand flood
management measures the City has taken? Mr. Rabe replied that each stormwater project
that includes a water pollution control component (including street reconstruction that
incorporatescatch basin sumps), are accounted for in the modeling effort.
K.Mr. Janty asked how the current pollution control levels of Oshkosh compare with other
Cities–Appleton for example. Mr. Boehm replied that the City of Appleton is about at
37% TSS control level and Oshkosh is currently at 29% TSS control level.
L.Mr. Janty askedwhy UW-O and the County are excluded from the analysis, but other
entities are not(such as the state prison)? Mr. Rabe replied thatthe process on including
and excluding areas of city responsibilityis basedon the state’spolicies andrules.
M.Mr. Kiefer asked whatthe “date” of this analysis is. Mr. Boehm replied it accounted for
practices in place as of 2013.
VII.Update onCapital Improvement Program Project Statuses.
A.Mr.Rabe summarized about thestatus ofseveralcurrent projects:
Southwest Industrial Park Expansion (2013 CIP):The City Contractor, Dorner, Inc.
continues working on the mass site grading for the expansion of the Southwest Industrial
Park. This expansion includes the Global Parkway crossing of the Wisconsin Southern
Railroad Tracks, and continues out to Clairville Road. The work is highly visible from the
th
back side of the 20Avenue YMCA.
Armory Area Wet Detention Basin (2014 CIP):Construction was completed on the
Armory Area Wet Detention Basin in 2014. The planting of the wetland plant plugs on the
safety shelf, as well as tree and shrub planting around the surface of the detention basin will
occur as soon as plants are ready to be planted in the spring of 2015. The latest estimate
from the landscaping sub-contractor is mid-May before they can complete that work.
Glatz Creek Relief Sewer (2014 CIP):City staff continue coordination with Wittman
Regional Airport staff for the next stage of construction of the Glatz Creek Relief Sewer. It
is anticipated that this large diameter storm sewer will be constructed in conjunction with
an upcoming airport taxiway reconstruction project. The project is currently anticipated to
begin following Air Venture 2015, but the actual start date will be dependent on the timing
of federal funds for the airport portion of the project.
I:\\Engineering\\James\\Storm Water Utility Committee\\2015\\04-23-2015\\AgendaPage2of4
Discussion 04-23-2015.docx
th
9& Washburn Area Wet Detention Basin (2015 CIP):DNR issued “Notice of Complete
th
Application” for the project on April 8. Notice was published in the Oshkosh
th
Northwestern on April 11. There is a 30-day public comment period that starts on the
date of publication.
th
DNR issued Wetland Mitigation Credit Purchase Authorization on April 17. The wetland
mitigation credits must be purchased prior to issuance of the permit that authorizes wetland
disturbance. Common Council will be acting on the request to purchase the wetland
th
mitigation credits from the Wisconsin Wetland Conservation Trust (WCCT) on April 28.
Contract 15-04: Concrete Paving and Utilities (2015 CIP):This contract includes East
Parkway Avenue and Mount Vernon Street. Wisconsin Public Service began work on their
utility reconstruction work approximately 4 weeks ago. The City Contractor, Carl Bowers
th
& Sons Construction Co., Inc. began work on April20. The Storm Water Utility CIP
budgeted $2,234,000 for this project. The construction cost, including engineering came to
$1,722,597. The original project estimate included underground detention within the
Parkway Avenue right-of-way west of the railroad tracks. That strategy has changed, and
staff are in negotiations with the Canadian National Railroad to purchase vacant land to the
west of the tracks between Parkway Avenue and Irving Avenue to construct a dry detention
basin similar to the BaldwinDetention Basin.
Contract 15-05: Concrete Paving and Utilities (2015 CIP):This contract includes West
New York Avenue and Custer Avenue. Wisconsin Public Service began work on their
utility reconstruction work approximately 4 weeks ago. The City Contractor, Jossart
th
Brothers, Inc. began work on April 13. The Storm Water Utility CIP budgeted
$1,380,100 for this project. The construction cost, including engineering came to
$923,410.
Fernau Avenue Watershed–North Main Street Area Wet Detention Basin (2015 CIP):
The Department of Agriculture, Trade and Consumer Protection (DATCP) completed and
th
published the Agricultural Impact Statement (AIS) on April 10. The City is not allowed
to begin negotiating the acquisition with the current property owner until 30 days after the
publication of the AIS. Meanwhile, design work continues for the project.
Libbey / Nicolet Watersheds-North Main Street Area Detention Basin (2015 CIP):
AECOM has been selected to perform the design services for this contract. City staff and
AECOM staff are currently working through the scope of services required to complete this
work. We anticipate completing this, and getting started on the design work in the next
month. Construction of this project is scheduled for 2016and will be included in the 2016
CIP.
Gallups/Merritts Creek Watershed Study (2015 CIP):Brown and Caldwell has been
selected to perform the detailed planning level study for the Gallups/Merritts Creek
Watershed. City staff and Brown and Caldwell staffare currently working through the
scope of services required to complete this work. We anticipate completing this, and
getting started on the work in the next month.
I:\\Engineering\\James\\Storm Water Utility Committee\\2015\\04-23-2015\\AgendaPage3of4
Discussion 04-23-2015.docx
VIII.Update Regarding On-going Information and Educational Efforts
A.Mr. Butler moved to tablethis topic until the next meeting so that Ms. Muldoon can be
present for the discussion. Mr. Janty seconded the motion. Motion carried (3-1) with Mr.
Kiefer voting in opposition.
IX.Adjournment.
There being no otherbusiness before thecommittee,and uponbeing duly moved and seconded
(Mr.Clark/Mr.Butler),the meeting wasadjournedat9:01a.m.
Respectfully Submitted,
James Rabe PE, CPESC
Civil Engineering Supervisor
I:\\Engineering\\James\\Storm Water Utility Committee\\2015\\04-23-2015\\AgendaPage4of4
Discussion 04-23-2015.docx