HomeMy WebLinkAbout22. 19-535 SEPTEMBER 24, 2019 19-535 ORDINANCE
FIRST READING
(CARRIED LOST LAID OVER WITHDRAWN )
PURPOSE: APPROVE TEMPORARY CLOSURE OF WAUGOO AVENUE AND
OTTER AVENUE AT THE CANADIAN NATIONAL RAILROAD
CROSSINGS
INITIATED BY: DEPARTMENT OF PUBLIC WORKS
A GENERAL ORDINANCE OF THE CITY OF OSHKOSH AUTHORIZING A VARIANCE
TO SECTION 25-23 OF THE OSHKOSH MUNICIPAL CODE PERTAINING TO STREETS
TO REMAIN OPEN TO TRAFFIC DURING THE COURSE OF EXCAVATION WORK.
WHEREAS, the City of Oshkosh Municipal Code Section 25-23 requires a
passageway of not less than ten(10)feet in the travelled portion of the street to remain open
on various streets within the City of Oshkosh, including one way streets; and
WHEREAS, Canadian National Railroad (CN)has requested full closure of Waugoo
Avenue and Otter Avenue, both one way streets, at the intersections with their tracks for
replacement of tracks, bedding, timbers and adjacent roadway pavement; and
WHEREAS, it is necessary therefore to grant a variance from the terms of section 25-
23 for this purpose; and
WHEREAS,the anticipated time to complete the work is five(5)days per intersection
to be completed during the period from October 14 to November 1, 2019.
NOW, THEREFORE the Common Council of the City of Oshkosh do ordain as
follows:
SECTION 1. Canadian National Railroad (CN) is hereby granted a variance from
the provisions of Section 25-23 of the City of Oshkosh Municipal Code to close Waugoo
Avenue and Otter Avenue at the intersections with the CN tracks for replacement of tracks,
bedding, timbers and adjacent roadway pavement subject to the following conditions:
SEPTEMBER 24, 2019 19-535 ORDINANCE
CONT'D
A. CN shall provide all necessary and required signage for the closure of the
street and detour of traffic.
B. CN shall at least seven (7) days prior to the anticipated closure provide
notice to the Department of Public Works and install advance warning
signs for motorists.
C. CN shall work with the Police and Fire Departments to minimize the effects
of the street closure upon emergency services and the public.
D. The Director of Public Works is hereby authorized to approve such closure
and detour route,with conditions as he/she may deem necessary, and to take
such other action as may be necessary and appropriate in consultation with
the Police and Fire Chiefs of the City of Oshkosh to protect the health, safety
and welfare of the citizens.
SECTION 2. This ordinance shall be in full force and effect from and after its
passage, publication and placement of the appropriate temporary signage indicating the
closure.
SECTION 3. Publication Notice. Please take notice that the City of Oshkosh enacted
ordinance #19-XXX APPROVE TEMPORARY CLOSURE OF WAUGOO AVENUE AND
OTTER AVENUE AT THE CANADIAN NATIONAL RAILROAD CROSSINGS (A
GENERAL ORDINANCE OF THE CITY OF OSHKOSH AUTHORIZING A VARIANCE
TO SECTION 25-23 OF THE OSHKOSH MUNICIPAL CODE PERTAINING TO STREETS
TO REMAIN OPEN TO TRAFFIC DURING THE COURSE OF EXCAVATION WORK) on
October 8,2019.The ordinance allows the temporary closure of Waugoo Avenue and Otter
Avenue, both one way streets, at the intersections with the Canadian National tracks for
replacement of tracks,bedding, timbers and adjacent roadway pavement. Advance notice
of the closure to motorists and installation of signage and detour signage shall be provided
during the closure.
The full text of the ordinance may be obtained at the Office of the City Clerk, 215
Church Avenue and through the City's website at www.ci.oshkosh.wi.us. Clerk's phone:
920-236-5011.
City
f
Oshkosh
MEMORANDUM
TO: Honorable Mayor and Members of the Common Council
FROM: Justin Gierach, Engineering Division Manager/City Engineer
DATE: September 19, 2019
RE: Approve Closure of Waugoo Avenue and Otter Avenue at the Railroad Crossings
on Broad Street
BACKGROUND
Canadian National Railroad(CN)is planning to repair the existing railroad tracks which intersect
the right-of-ways of Waugoo Avenue and Otter Avenue. The work to be performed by CN's
railroad crews will require the full replacement of the tracks, bedding, timbers, and the adjacent
roadway pavement that the tracks are encased in. Section 25-23 of the Municipal Code of the City
of Oshkosh requires all one-way streets (including Waugoo Avenue and Otter Avenue) to remain
open during excavation.
It is anticipated that each crossing will take five(5)days to be completed. CN requests the closure
of Waugoo Avenue and Otter Avenue to allow full access to the section of rail that requires
replacement, while maintaining a safe and secure working environment for the construction
crew, operators, and the general public. This is not uncommon, given the equipment and work
zone required for completion of this work.
A detour route will be posted for the duration of the work on Waugoo Avenue using Broad Street,
Washington Avenue, and Bay Street. A detour route will be posted for the duration of the work
on Otter Avenue using North Main Street, East Irving Avenue, and Bowen Street. Access to
businesses will be maintained for the duration of the work. The closures are anticipated to be
continuous over five(5)days,weather permitting. Advanced warning signs will be placed seven
(7) days prior to the closures to warn drivers.
ANALYSIS
Based on the excavation limits needed for the repair, staff determined Waugoo Avenue and Otter
Avenue at the railroad crossings on Broad Street need to be closed to traffic. The time frame will
be limited as much as possible to minimize the impact to the traveling public. Additionally,
worker safety and driver safety will be compromised during this work, if done under traffic.
1.\Engineering\Tracy Taylor\Memos to Mayor&Common Council\2019\CN-Waugoo Ave&Otter Page 1 of 2
Ave Closure Memo_9-19-19.docx
FISCAL IMPACT
There are no fiscal impacts to this ordinance.
RECOMMENDATIONS
I recommend approval of the request to close Waugoo Avenue and Otter Avenue at the railroad
crossings on Broad Street with the following conditions:
• The closure of Waugoo Avenue shall be limited to five (5) consecutive days, weather
permitting, to allow CN to complete the necessary railroad track repairs within a designated
two (2) week period starting October 14, 2019 and ending on October 25,2019.
• The closure of Otter Avenue shall be limited to five (5) consecutive days,weather permitting,
to allow CN to complete the necessary railroad track repairs within a designated two(2)week
period starting October 21, 2019 and ending on November 1,2019.
• CN shall be responsible for posting detour routes, approved by the Department of Public
Works, and posting warning signs at least seven(7) days prior to the closures.
Approved:
71(06----74 44.'44--
Mark A. Rohloff
City Manager
JG/tlt
I:\Engineering\Tracy Taylor\Memos to Mayor&Common Council\2019\CN-Waugoo Ave&Otter Page 2 of 2
Ave Closure Memo 9-19-19.docx